HomeMy WebLinkAbout20250822_PWD3985_2nd Review_COA Review Comments i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
# Rev. wgSpec. city
Ref. Add'1 Ref. Comment Response/Resolution Approved
1. TN SWPPP Update permit number on cover page to PWD 3985. Permit number TN
updated.
2. TN SWPPP Update references to 2019 SWMMWW to 2024 SWMMWW. References updated TN
throughout SWPPP.
3. TN SSP Update permit number on cover page to PWD 3985. Permit number TN
updated.
4. TN SSP Update references to 2019 SWMMWW to 2024 SWMMWW. References updated TN
throughout SWPPP.
5. TN SSP Pages 1-2 Minimum requirements called at as 1 through 10 and should be 1 through 9. This is true,thank TN
and 1-3 you.Reference
updated.
6. TN C1 Civil Site Include CESCL information.This will be required prior to permit issuance. CESCL from BYK TN
Plan construction,Anna
Hackett is added to
C1-Civil Site Plan.
7. TN C2 Construction Include note 17 in Erosion/Sedimentation Control Notes. Note 17 added. TN
Notes
8. TN C3 Clearing and Add note to maintain access to businesses(Starbucks,Walgreens,Plumbing/Door Notes Added to C1- TN
TESC Plan Company to the north,etc.)or provide detour route around construction as Site plan and C3.
necessary.
9. TN C9 West Aisle Add truncated domes to all driveway crossings and ADA ramps along west aisle. Truncated domes TN
Plan and have been added to
Profile crossings.
Page 1 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
10 TN C16 Stormwater Replace Snohomish County with City of Arlington in Detail 513-Compost Amended Reference to City of TN
Management Soils. Arlington updated,
Details Option 1 is only applicable to sites that have the original,undisturbed soil native to the site.This will most often be forested thank you.
land that is being left undisturbed ir'Fe current-,-Pct,
Option 2:Amend disturbed soil according to the following procedures:
a. Scarify subsoil to a depth of one foot.
b. In planting beds,place three inches of compost and till in to an eight4nch depth.
c. In turf areas,place two inches of compost and fill in to on eight-inch depth.
d. Apply two to four inches of arborist wood chip,coarse bark mulch,or compost mulch to planting beds after final planting.
(Afiernatively,disturbed soil can be amended on a site-customized manner so that it meets the soil quality criteria set forth
above,as determined by a licensed engineer,geologist,landscape architect,or other person as approved b�
Ca__1W
Option 3:Disturbed Soil.
Stockpile existing topsoil during grading and replace it prior to planting.Stockpiled topsoil must be amended if needed
to meet the organic matter and depth requirements by following the procedures in option(4).Remove forest duff layer
and topsoil and stockpile separately,in an approved location prior to grading.Cover soil and duff piles with woven
weed barrier(avoiloble from nursery supply stores)that sheds moisture yet allows airflow.
Option 4:Import topsoil mix with 107.min soil organic matter content.
Impart topsoil mix of sufficient organic content and depth to meet the organic matter and depth requirements.
11 TN C18 Sanitary Include City of Arlington Sewer Notes on plans. COA Sewer System TN
Sewer Plan Construction Notes
have been added to
the Sanitary Sewer
plan
12 TN C24 Lighting Lighting Plan was not included with submittal. Lighting Plan is TN
Plan prepared by
Architect.
13 BIG Sheet C11-Fire lane signing needs to state"Fire Lane No Parking Tow Away Zone" Fire Lane signs have TN
been updated to
state"Fire Lane No
Parking Tow Away
Zone"
Page 2 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
14 JW- Sewer main shall be located on the south and west side of roadways and approx.6' 6-ft from centerline of TN
PW from centerlines.Please revise. a 20-ft drive aisle does
Sewer not provide the
necessary setback to
the building
foundations. Sewer
main placed 5-ft
minimum from
building foundations.
15 JW- Sewer main shall be located within proposed dedicated utility easement. Minimum 10-ft Easement TN
PW easement 10'minimum with pipe centered within easement. provided around sewer
Sewer main.
16 JW- Note Pipe lengths between SSMH's on Plan. Pipe lengths and TN
PW slopes added to
Sewer sewer plan view.
17 JW- SSMH 3,2,5 and SSCO 8&7 shall all have the same offsets along Private Drive A. See This would result in TN
PW note 1. acute angles for
Sewer pipes entering and
leaving manhole.
Manholes
straightened out to
be close.
18 JW- Sheet C19,SCCO 7&8 shall be SSMH's not cleanouts.Label SSMH's on plan view. Manholes are TN
PW provided at ends of
Sewer all sewer runs.Thank
you.
Page 3 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
19 JW- Install Y's instead of T's at the laterals off the main line.Note on plans and include This places the sewer TN
PW detail.All 6"side sewers shall extend 10'past the edge of the property line,and 5' service inside the
Sewer beyond any easements,including the standard 10'utility easements. (EDS 5-3.03 (1)) building foundation.
"Property Line"is at
the edge of drive aisle.
This is not a standard
subdivision.Y's are
noted on plan.
20 JW- Add PAD elevations for each lot on Sewer plan. Pad elevations are TN
PW noted on each unit-
Sewer lot within the sewer
plan.
21 JW- Ex SSMH lid conflict with proposed flowline on West Aisle Sta.3+50. This is an existing TN
PW manhole with road
Sewer located as required.
We have obtained
additional survey and
the manhole is located
so that we may rotate
the lid to be behind
the curb.
22 JW- See PDF WM&SS Exhibit attached. Thank you TN
PW
Sewer
23 GT- The proposed watermain shall be accessible from within private drive-isles and Agreement for water TN
PW within proposed dedicated utility easements. Minimum 10'horizontal separation main routing and
Water from Sewer main,and 5'Horizontal separation from storm.Main located approx.6' meter services are now
from roadway centerline,along north and east side of roadway.(EDS 4-1.07) represented on plans.
Page 4 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
24 GT- Water and Sewer Easement may be combined in a minimum 20'easement and 10-ft easement is TN
PW maintain a minimum 10'separation.Utilities shall be centered within the easement provided around the
Water and shall not have less than 5-fet setback from edge of easement(EDS 1-7.01/1-7.03) sewer and water
mains.In areas where
the sewer and water
are run side by side,
outside of the ROW,a
20-ft easement is
provided.
25 GT- Proposed watermain shall be 12"in size.Please revise all callouts. (EDS 4-1.08) 8-inch is allowed in TN
PW residential
Water developments and
was provided
through the Binding
Site Plan lots. As
agreed upon with
meetings with PS,
12"is provided along
north and east sides,
8"is provided to
bridge connection
between north line
and existing line
along the south.
26 GT- Existing 6"WM along the east boundary of site shall be replaced with a 12"HDPE and Provided with a TN
PW extended 5'beyond property line 31051100400700 to S Hazel St within existing separate plan for bore
Water watermain easement and panhandle of contiguous parcel also owned by applicant. under creek.
27 GT- Profile all proposed watermains. Water main is added TN
PW to profile sheets.
Water Water main profile
along north is added
as a separate sheet.
Page 5 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
28 GT- Note meter size and reference standard detail on plan.Water meters shall be set in Location of meters TN
PW soft scape,not in driveways nor in alleys.Show proposed driveways on plan. and main have
Water been updated
based on
resolution of
location per
meetings with Jim
Kelly and PW.
There are no
"driveways"only
garage doors 4?
29 GT- The irrigation meter shall be separate meter.Please show and note. Irrigation meter with TN
PW DCVA is added to
Water meter back adjacent
to Lot 48 for
irrigation of the open
space areas.
30 GT- Note Building height on plans. Building Height is TN
PW noted on water plans
Water
31 GT- Fire hydrants adjacent to private alley shall note/reference W-030&W-020.Show Fire hydrant TN
PW concrete pad and bollards on plan. specifications
Water updated to include
W-020 and W-030
32 GT- Fire hydrants shall not be closer than 50-feet of structures(EDDS 4-1.15). This was discussed TN
PW with Public Works
Water and locations as
Residential Sites do not have Hydrant Setbacks of 50'in other Jurisdictions depicted have been
accepted.
Page 6 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
33 GT- Proposed Watermain within the West Aisle shall be installed within the roadway and Water main extension TN
PW separated from the existing sewer by a minimum 10'. WM at the north side shall end discussed with Public
Water in a fire hydrant and blow off. The WM shall extend south to the existing main in Works and updated
204th St.The alignment of the watermain connection point on 204th is still being configuration is
discussed by COA. consistent with
agreement and
location of proposed
water main.
34 GT- Connect proposed watermain loop into the existing 8"WM at the SW corner of site Water main extension TN
PW within the north side most southern private drive. Min 10'Watermain easement will discussed with Public
Water be required. Works and updated
configuration is
consistent with
agreement and
location of proposed
water main.
35 GT- All Tee's shall be fully valved. Fully valved Tee's TN
PW have been provided.
Water
Page 7 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
36 GT- No water or sewer utility shall be installed within a proposed bio-cell/drainage area. Water main has been TN
PW See note 21. moved into the
Water existing pavement
adjacent to Starbucks.
However,it must be
noted that water main
and other utilities are
consistently run
through these
vegetated bio-cells.
These areas are really
no different than
landscaped areas.
Groundwater will still
be in contact with
buried utilities.
37 GT- See PDF WM&SS Exhibit attached. Thank you. TN
PW
Water
38 KS- Tract 999,Private Drive Isle(EDDS 1-7.01)-Minimum 25'Access easement required. Private drive aisles TN
PW Access and Utility Easement may be combined.See (EDDS 1-7.04)for all other Utility here are 25-ft in
General Easement requirements. width
39 KS- Portage Creek is located on adjacent property to the north. The Buffer from creek See Site Plan TN
PW shall be shown on all plans,as the buffer may impact the development. Approval and prior
General BSP.
Page 8 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
40 KS- There shall be no bioswales within Right of Way dedicated area along West Aisle. From City"The city TN
pW Bipod's would be an approved alternative. All drainage within West Aisle shall have will allow this project
General maintain a minimum 5'separation from the existing sanitary sewer main. to have the
bioretention swales
within the ROW along
the east side of"West
Aisle"so long as they
are only receiving
runoff from the ROW
surfaces and not also
from the private
development."
Page 9 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
41 KS- The City needs to discuss/resolve the extension of West Aisle north through Tract A, From City,"An TN
PW the contiguous parcel owned by the applicant,and/or the dedication of Tract A to the amendment to the
General City. There is an existing bridge on the creek crossing that could be a liability to the original Binding Site
City if not brought up to public standards. Plan will be needed to
create at lot over the
bridge and easement
area that runs through
Tract A creating
"Tract"B".Tract A
would still be
dedicated to the City
of Arlington and the
new Tract E would
remain in private
ownership either by
the current owner or
sold to the adjacent
owner who benefits
from the bridge.The
amendment to the
BSP would be
separate from the
review and approval
of the civil permit for
the Harmony project.
We would just require
the final BSP
amendment prior to
either closeout of the
civil permit or prior to
certificate of
occupancy for any of
the residential units.
to be determined)"
Page 10 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
42 JH- Review pending Minor Modification approval for the Prelim Unit Lot Minor Mod TN
Planning Approved,thankyou
43 Please send revisions documents to CEI)Oarlingtonwa.gov for processing.
44 JW- Proposed Sewer main easement shall end at dedicated right-of-way boundary Yes it should,this has
PW (Entrance Road). Easement to read: 10'COA Sewer Easement been updated.Thank
Sewer you.
45 JW- Ex Sanitary Sewer Manhole lid conflict with proposed flowline on West Aisle @ Sta. Bioretention swale
PW 3+50.Rotating the lid within the slop of the proposed drainage ditch is not a solution. has been eliminated
Sewer adjacent to the
46 GT- Label/dimension all Water Easements: 10'COA Water Easement. Easements added.
PW
Water
47 GT- The proposed COA Water Easement along the north property line shall extend to the Easement extended
PW south side of the paved walking path to allow full access on to the paved walkway for to include path,
Water future maintenance.Show/label as necessary,maintaining consistent width.
48 GT- See Plan C17/C18 Markups for water revisions needed. Modifications and
PW notes on C17/C18
Water have been added to
plans.
Page 11 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
49 GT- Ensure the location of the proposed water main on West Aisle is not in the wheel The current location
PW path.Adjust to 6-foot offset from centerline as noted in(Sec.4-1.04) of the water main is
Water 6-ft from the
centerline.Further,
road width is 25-ft,
centerline at 12.5-ft.
The average vehicle
track width is 5-ft
from tire CL.Placing
vehicle in center of
12.5-ft lane and 2-ft
width for vehicle
tracks results in the
water main location
as displayed.
50 GT- Buildings exceeding thirty feet in height require double check valve assemblies. Note added,
pW Backflow preventer shall be located after the meter on the customer side of the buildings do not
Water service. (Sec 4-1.26 Cross-Connection Control) exceed 30-ft in
height.
51 GT- Install pipe casing under bio-cell,north of West Aisle,where proposed water main Main has been
pW crosses under bio-cell. Extend casing 10'beyond top of bio-cell on each side. moved north and no
Water longer beneath the
bioretention Swale.
52 GT- This is comment 9 referenced in redlines.Water mains shall be located a minimum Watermain is outside
pW 10'from buildings. (Sec 4-1.07) this area,hydrant
Water spools extend between
buildings.
53 TN Submit new civil permit application for watermain extension through tract A and Plans have been
reference permit number on these plans.Review documents have already been prepared. Submittal in
submitted by Paul Woodmansee. progress.
54 TN C1 Update Sheet list table(C24 is Composite Utility Plan) Sheet list updated.
Civil Site Plan Thank you.
Page 12 of 13
i
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name:Harmony at Arlington Permit No.:PWD3985 Review Date: 05/28/2025
Contact: Adele Phone No.: 360-652-9727 Review Phase: 2ND Review Report Date:04/29/2025
Reviewing Dept.:CED Applicant: Harmony at Arlington LLC DWG Issue Date: 04/29/2025
55 TN C9 Adjust Road Horizontal Curve Table on sheet as it cut off. Changes to our font
West Aisle definitions has
Plan and widened a lot of these
Profie automatically
generated tables.This
is not the only planset
to be affected.Thank
you.
56 TN Informational Provide photometric analysis to ensure Public Road(West Aisle)meets minimum Architect to provide.
Comments roadway illumination levels outlined in Table 2-5 of Street Lighting Guide. Thank you.
that can be
addressed Water easement to extend over all water meters/manifolds. (Easement exhibits and
now or will legal descriptions will be reviewed at time of their submittal)
be conditions
of approval
57 Please send revisions documents to CEDC@arlingtonwa.gov for processing.
58
59
60
61
62
Page 13 of 13