Good evening,LaNay,
There is work being done in both areas:
The Olympic Ave leg of the roundabout&the 77th Ave leg of the roundabout.
The original project scope in Anvil refers to HUB h3015 Access(on 77th Ave):
SCOPERNOTES:access hub h3015 and run red jumper.ACCESS TERMI NAU PED AND PULL DROP THROUGH EXISTING CONDUIT. PED ISON THEwESTSIDEOF OLYMPIC PL
Both the original and revised workprints show the following:
THIS JOB WILL RED JUMPER(1)F1 FIBER AT HUB H3015 INTO(1)F2 FIBER.
RED FIBER
JUMPER
C-*
FC105T.71
TO
HM15 122
AT HUB H3015,RED JUMPER
F1 COUNT ARTNWAXX FC1057,71
INTO F2 FIBER H3015,122
It is also shown on the coversheet of the original&revised workprints as well:
WOULD YOU FIND TRAFFIC ON ASSIGNED FIBERS,AT OG RlWIR[D
THE OFFICE OR THE-ONN,PLEASE ESCALATE TO THE 27 ep12
LOCAL NSPECTOR OR SPECIAL TEAM.
601
AR BFF- TERMINAL PUICEMEN T
5 1 ST HE, WA 83—8128216632238,-122.126748963
38936
THIS JOB WILL RED JUMPER(1)F1 FIBER AT HUB H3016INTO 11)F2 FIBER,THIS FIBER WILL RIPPLE THROUGH INTO EXISTING TERMINAL NEAR THE
PROPERTY,WILL INSTALL A DROP IN THIS TERMINAL AND PULL IT THROUGH EXISTING CONDUIT INTO CUSTOMER'S DMARC TO FEED A NEW
SLIMBOX TEMINAL AND SERVE ALL UNITS IN THE BLDG.
C.O:207 E STH ST,ARLINGTON,WA 98223
VIP
Therefore,the jumper installation work occurring on 77th Ave is shown on the TCP
mite 77TH AVE NE
P2-M)
•• m»3
4 1
smroy
WOFN ��
r ARFA
rr
The plan does extend through the Olympic Ave NE leg.The plan set also identifies jumper work at Hub H3015 on 77th Ave NE.
The specific construction activity requiring traffic control is accessing the hub and installing the jumper.Therefore,the TCP
reflects the actual location where crews will be working within the right-of-way.
Please let me know if there is anything we need to do on our end.
Best Regards,
Victoria Pham
Project Manager-TCP&Permits
C:951-519-0871
ATCO Communications Services,LLC
Victoria,Pham()atcotelecom.com
Victoria.phamPziply.com
10A—,,..zip1yf1ber
From:LaNay Pray<Ipray@arlingtonwa.gov>
Sent:Wednesday,April 8,2026 11:14 AM
To:Permits<permits@Atcotelecom.com>
Cc:grpatcopermits@ziplyfiber.com
Subject:City of Arlington 26-0181 ROW
CAUTION:THIS EMAIL IS FROM AN EXTERNAL SENDER.
Do not click on links or open attachments if the sender is unknown or the email is suspect.
Hello,
We are processing your permit application The plans show the work on Olympic Ave leg of the roundabout,but the Traffic Control plans show the
work on the 77th Ave leg of the roundabout.Revise the traffic control plans to match the plan set.
Sincerely,
Ank
;9LaNayPray
Community&Economic Development,Permit Technician
18204 59th Ave NE,Arlington,WA 98223
O:360.403.3437
InravCilarlingtonwa.gov I www.arlingtonwa.gov
Note:Emails and attachments sent to and from the City of Arlington are public records and may be subject to disclosure pursuant to the Public Records Act.