1. (5 min) 67th Ave NE Phase III Project – WSDOT Supplement #4 ATTACHMENT A
2. (10 min) Airport Blvd Change Order ATTACHMENT B
3. (5 min) Snohomish PUD Easement Agreement for 91st Ave NE ATTACHMENT C
4. (10 min) Utilities Senior Discount Eligibility Requirements ATTACHMENT D
5. (10 min) 2012 Goals Update Handout
6. (10 min) 2012 Grants Update Handout
7. Miscellaneous Council Items
PUBLIC COMMENT
For members of the public to speak to the Council regarding matters on the Council Workshop agenda.
Please limit your remarks to three minutes.
ADJOURNMENT
To open all attachments, click here
Arlington City Council Workshop
August 13, 2012 – 7 PM
City Council Chambers ~ 110 E. Third
City of Arlington
Council Agenda Bill
Item:
WS #1
Attachment
A
COUNCIL MEETING DATE:
August 13, 2012
SUBJECT:
67th Ave WSDOT Supplement 4
ATTACHMENTS:
WSDOT Supplement 4
DEPARTMENT OF ORIGIN
Public Works – Eric Scott
EXPENDITURES REQUESTED: None
BUDGET CATEGORY: N/A
LEGAL REVIEW:
DESCRIPTION:
Supplement to Arlington-WSDOT agreement reallocating remaining grant funds from
design and right-of-way acquisition to construction.
HISTORY:
The City received several grants totaling $1,677,716 for design and right-of-way (ROW)
acquisition for the 67th Ave Phase III project. At the completion of the design and ROW
phase there is $257,702 remaining in grant funds. The City has petitioned PSRC and
WSDOT to transfer the funds for use in the Construction phase. The enclosed
supplement authorizes the reallocation of those funds.
ALTERNATIVES
• Remand to staff for further consideration
RECOMMENDED MOTION:
No action at this time – discussion/presentation only.
Agency Supplement Number
City of Arlington 4
Federal Aid Project Number Agreement Number
STPUS-2699(001)LA-6591
The Local Agency desires to supplement the agreement entered into and executed on 3/10/2008
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Project Description
Name 67th Ave NE - Roadway Improvements Length 1.00
Termini 204th Street NE on the South and Lebanon Ave on North
Description of Work No Change
Reason for Supplement
Move unexpeded Design and Right of Way funds to Construction.
Does this change require additional Right of Way or Easements? Yes No
(1) (2) (3) (4) (5)
PREVIOUS AGREEMENT/
SUPPLEMENT
SUPPLEMENT ESTIMATED TOTAL
PROJECT FUNDS
ESTIMATED
AGENCY FUNDS
ESTIMATED
FEDERAL FUNDS
P.E.a. Agency: $293,066 -$177,965 $115,101 $15,539 $99,562
86.5_%b. Other __Consultant $1,195,623 $1,195,623 $161,409 $1,034,214
Federal Aid c. Other __
d Other _$5,000 $5,000 $5,000 0.00
e Total PE Cost Est. (a thru e)$1,493,689 ($177,965)$1,315,724 $181,948 $1,133,776
Right of Way f Agency $462,980 -$123,191 $339,789 $53,551 $286,238
84.24__%g Other ___________________
Federal Aid h Other ____________________
Participation i State $5,000 $5,000 $5,000 0.00
Ratio for RW j Total R/W Cost Est. (f thru j)$467,980 ($123,191)$344,789 $58,551 $286,238
Construction k Contract $297,921 $297,921 $40,219 $257,702
l Contract Non-Participation_$7,575,700 $7,575,700 $7,575,700
m Other ___
86.5__%m Other ___
Federal Aid o Agency
Participation p State $5,000 $5,000 $5,000
Ratio for CN q Total Const. Cost Est. (k thru p)$0 $7,878,621 $7,878,621 $7,620,919 $257,702
$1,961,669 $7,577,465 $9,539,134 $7,861,418 $1,677,716
AGENCY OFFICIAL Washington State Department of Transportation
By By
Title
Date Executed
Director of Highways and Local Programs
Estimate of Funding
Type of Work
r.Total Project Cost Estimate (e+j+q)
Local Agency Agreement Supplement
CFDA No. 20.205
The local agency further stipulates that pursuant to said Title 23, regulations and policies and procedures, and as a condition to payment of the
Federal funds obligated, it accepts and will comply with the applicable provisions.
City of Arlington
Council Agenda Bill
Item:
WS #2
Attachment
B
COUNCIL MEETING DATE:
August 13, 2012
SUBJECT:
Change Order #1 to the Airport Boulevard, Phase 1 construction contract.
ATTACHMENTS:
Airport Boulevard Phase 1 Change Order 1
DEPARTMENT OF ORIGIN
Public Works – Jim Kelly
EXPENDITURES REQUESTED: $143,109.39
BUDGET CATEGORY: Transportation Improvement fund, Airport
CIP, Water CIP and Sewer CIP
LEGAL REVIEW:
DESCRIPTION:
Construction Contract Change Order authorizing additional funds to the contractor for
unforeseen conditions and modifications to the design. Unforeseen conditions include a higher
than anticipated ground water condition, design changes include deletion of a portion of the
sidewalk from the scope of work, deletion of a watermain relocation, and replacement of
concrete driveway.
Original Contract Price $1,143,953.61
Change Order 1 $ 143,109.39
New Contract Price $1,287,063.00
HISTORY:
The original design documents called for a 5’ sidewalk on both sides of Airport Blvd. Based on
subsequent planning meetings with the Airport, it has been decided to eliminate the sidewalk
on the west side of the roadway and construct a 12’ wide trail in Phase 2 of the project (2013).
The original design documents called for relocation of an existing 12” water main due to
potential conflicts with the proposed roadway improvements, namely the rain gardens. After
the watermain was potholed it was determined that it was sufficiently deep to not pose a
conflict with proposed roadway improvements.
The driveway apron to an existing business along Airport Blvd needs to be removed and
replaced to accommodate grades along the proposed alignment of Airport Blvd and meet ADA
guidelines for the adjacent sidewalk.
Groundwater was assessed during design and it was determined that groundwater would be
sufficiently deep to not pose an issue for the project. If groundwater was encountered, it was
assumed that a trash pump could be placed in the trench to remove incidental water.
Unfortunately due to a very wet winter and several large thunderstorms passing through the
area prior to construction the groundwater elevation within the project limits rose
substantially, thus creating an impact to the project during construction.
The situation was further impeded by the unusually high rate at which ground water was
seeping into the open trenches, which was faster than can be dealt with by a typical trash
pump. It was decided that a full dewatering system needed to be installed immediately to keep
the project on schedule and avoid delays.
An array of point wells was installed at each sewer service connection and sewer main
extension at cross streets. First attempts to install the 2” well points via a least cost jet drill rig
met with difficulty, as the subsurface hydraulics prevented the drill from making efficient
progress below 10’. An auger drill rig was then brought to the site to complete the drilling
operations. Unfortunately, this type of drilling system is more expensive than the jet drill
system.
It is typical for groundwater elevations to experience seasonal fluctuations. Additionally, the
dynamics of how subsurface water flows is very difficult to ascertain as the soil media can vary
significantly below grade. Based on the information available during design, the high ground
water table and the high flow rate were not anticipated.
The proposed adjusted construction contract price of $1,287,063 is less than the original
Engineer’s Estimate for the project of $1,293,000; overall project costs have not exceeded
original anticipated levels.
ALTERNATIVES
• Remand to staff for additional information
RECOMMENDED MOTION:
No action at this time – discussion/presentation only.
CITY OF ARLINGTON
CONTRACT CHANGE ORDER AGREEMENT
DATE:CONTRACTOR:
PROJECT:CHANGE ORDER #:
SUMMARY OF PROPOSED CHANGES:
Unit Unit Change
in
#Price Quantity Add Credit
117 Crushed Surfacing Top Course TON $13.40 (198) $ (2,657.84)
130 Cement Conc Sidewalk SY $26.00 (1972) $ (51,277.78)
139 Type 1 Concrete Driveway LS $7,795.00 1 $ 7,795.00
140 Unforseen Dewatering Force
Account
EST $205,000.00 1 $ 205,000.00
207 Ductile Iron Pipe for Water
Main 12 in Dia
LF $71.00 (250) $ (17,750.00)
220 Cap Watermain Lateral LS $2,000.00 1 $ 2,000.00
$ 214,795.00 $ (71,685.61)
$ 143,109.39 Add
Reece Trucking
1
The cost shown below shall be full compensation for the items as indicated in summary above and shall be considered full
payment for all materials, labor, and equipment for the work. Materials and workmanship shall be in accordance with contract
specifications.
NET TOTAL
August 13, 2012
Airport Blvd Phase 1a
Item Cost to Contract
Subtotal
Description
1) Replace existing concrete driveway, per CCD-1
2) Increase force account allowance to accomodate additional unforsee work outlined in CCD-2
3) Reduce quantity of sidewalk, per CCD-4
4) Delete watermain relocation from Contract, per CCD-5
The time provided for completion in the contract is unchanged _________, increased ____X_____,
decreased__________ by ___15_______ working days.
Will this change effect expiration or extent of insurance coverage __________yes ____X______no.
If “yes”, will the policies be extended __________yes __________no.
Contractor’s Signature City of Arlington Authorized Signature Date
PROJECT RECAP TO DATE:
Original Contract Amount 1,143,953.61$
Previous Change Orders -$
This Change Order 143,109.39$
New Contract Amount 1,287,063.00$
This document shall become an amendment to the contract and all provisions of the contract will apply hereto.
City of Arlington
Council Agenda Bill
Item:
WS #3
Attachment
C
COUNCIL MEETING DATE:
August 13, 2012
SUBJECT:
Snohomish County PUD Utility Easement
ATTACHMENTS:
Easement Agreement
DEPARTMENT OF ORIGIN
Public Works – Eric Scott
EXPENDITURES REQUESTED: None
BUDGET CATEGORY: N/A
LEGAL REVIEW:
DESCRIPTION:
Utility easement agreement granting Snohomish County PUD easement rights to the
City’s 520 Reservoir property, parcel 31052500101700, for an area approximately 5’x10’
located at the SW corner of the parcel.
HISTORY:
Snohomish County PUD is relocating their power poles located along 91st Avenue, east
of the WSDOT roundabout currently being constructed. The relocation will result in
overhead power lines crossing the SW corner of the City’s 520 Reservoir property. The
size of the easement is 5’x10’ and is located in the SW corner of the parcel. SnoPUD
will compensate the City $500 for the easement.
ALTERNATIVES
• Remand to staff for further consideration
RECOMMENDED MOTION:
No action at this time – discussion/presentation only.
91st Ave NE
172nd St NE
Legend
Easem ent
Street ROW
County Parcels Scal e:Date:
File Name:
Drawn By:
PUD_91stAve t8.5x11_1 2.mxd
7/2/20 12 lb
PU D No. 1 of Snohomish CountyElectrical Transmission Easement
City of Ar lington
1 inch = 5 0 fee t
5'x10' E lectrica l Tran sm ission Ea seme nt on P arce l # 31 0525 0010 1700
Ma ps and GIS data are distribu te d “AS-IS ” without wa rranties of any kin d, either express or implied,includin g but not limited to warran ties o fsuitability for a partic ular purp ose or use . Ma p data are compiled from a va riety of sources wh ich may co ntain e rrors and us ers w ho re ly u pon the informa tion do so at their o wn risk . Users agree to in demnify, d efend, and h old h armles s th e City of Arlington for any an d all lia bility of a ny nature aris in g out of or res ulting from the lac k of ac curacy or co rrectne ss of the d ata, or th e u se of the d ata pre sen te d in the maps .
City of Arlington
Council Agenda Bill
Item:
WS #4
Attachment
D
COUNCIL MEETING DATE:
August 13, 2012
SUBJECT:
Ordinance amending Arlington Municipal Code 13.12.160(b)
ATTACHMENTS:
None at this time, an ordinance will be attached to the CAB for the August 20th Council
meeting
DEPARTMENT OF ORIGIN
Public Works – Jim Kelly
EXPENDITURES REQUESTED: None
BUDGET CATEGORY:
LEGAL REVIEW:
DESCRIPTION:
This is an ordinance amending Arlington Municipal Code 13.12.160(b) that will raise
the Low Income Senior Citizens maximum income eligibility threshold that allows
them to qualify for the utility rate discount.
HISTORY:
The City of Arlington offers a 40% discount on utility rates to low income senior
citizens. Currently low income senior citizens can qualify for this discount if they earn
$28,000.00 or less. This proposed change would raise the eligibility threshold to those
earning incomes of $30,000.00 or less.
AMC 13.12.160(b) For purposes of this section, the term "qualifying senior citizens" shall
mean those ratepayers who are sixty-one years of age or older, whose household income is
twenty-eight thirty thousand dollars or less. For purposes of verifying income, ratepayers
seeking to qualify under this section shall provide annual proof of age and income as may be
required by the city upon forms retained by the finance director for that purpose.
ALTERNATIVES
• Remand to staff for further consideration
RECOMMENDED MOTION:
No action at this time – discussion/presentation only.