HomeMy WebLinkAbout20260413_PJA26-0201_TIA TRAFFIC IMPACT ANALYSIS REECE SORTING FACILITY JURISDICTION: CITY OF ARLINGTON, WA Prepared for: 2812 Architecture 2812 Colby Avenue Everett, Washington 98201 Prepared by: Kimley ))) Horn February 2026 KH 090225009 Copyright© Kimley-Horn and Associates, Inc. Kimley)))Horn TRAFFIC IMPACT ANALYSIS FOR REECE SORTING FACILITY Prepared for. 2812 Architecture 2812 Colby Avenue Everett, Washington 98201 SAMES w s 1� Prepared by. Kimley-Horn and Associates, Inc. 02i17 26 2828 Colby Avenue Suite 200 �o� 42 307 �ww Everett, Washington 98201 'GIsTERti G� (425) 708-8275 �IONAL This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley- Horn and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc. © February 2026 KH 090225009 Reece Sorting Facility February 2026 Traffic Impact Analysis KH 090225009 Kimley >>> Horn TABLE OF CONTENTS 1. DEVELOPMENT IDENTIFICATION............................................................................................... 1 2. METHODOLOGY ..................................................................................................................... 1 3. TRIP GENERATION ................................................................................................................. 4 4. TRIP DISTRIBUTION ................................................................................................................ 5 5. INTERSECTION LEVEL OF SERVICE CALCULATIONS................................................................... 7 5.2. Turning Movement Volumes ........................................................................................ 7 5.3. Level of Service Calculations......................................................................................11 6. COLLISION HISTORY..............................................................................................................11 6.1. Collision Severity ........................................................................................................11 6.2. Collision Types ...........................................................................................................12 6.3. Collision Rates............................................................................................................12 7. SITE ACCESS........................................................................................................................12 8. TRAFFIC MITIGATION FEES ....................................................................................................13 8.1. City of Arlington ..........................................................................................................13 8.2. Snohomish County......................................................................................................13 8.3. Washington State Department of Transportation ........................................................13 9. CONCLUSIONS......................................................................................................................13 LIST OF FIGURES Figure1: Site Vicinity Map ......................................................................................................... 2 Figure 2: Development Trip Distribution — PM Peak Hour.......................................................... 6 Figure 3: 2025 Existing Turning Movements — PM Peak Hour ................................................... 8 Figure 4: 2028 No-Build Turning Movements - PM Peak Hour................................................... 9 Figure 5: 2028 Build Turning Movements - PM Peak Hour........................................................10 Reece Sorting Facility February 2026 Traffic Impact Analysis Page i KH 090225009 Kimley >>> Horn LIST OF TABLES Table 1: Level of Service Criteria ............................................................................................... 3 Table 2: ITE 12' Edition Trip Generation Summary................................................................... 5 Table 3: Level of Service Summary - PM Peak Hour ................................................................11 Table 4: Collision Severity by Year............................................................................................11 Table 5: Collision Type Summary..............................................................................................12 Table 6: Collision Rate Summary..............................................................................................12 LIST OF APPENDICES SITEPLAN...................................................................................................................................A TRIPGENERATION ....................................................................................................................... B COUNTDATA...............................................................................................................................C TURNING MOVEMENT CALCULATIONS............................................................................................D LEVEL OF SERVICE ANALYSIS....................................................................................................... E COLLISIONDATA.......................................................................................................................... F Reece Sorting Facility February 2026 Traffic Impact Analysis Page ii KH 090225009 Kimley)))Horn 1. DEVELOPMENT IDENTIFICATION Kimley-Horn and Associates, Inc. (Kimley-Horn) has been retained to provide a Traffic Impact Analysis (TIA) for the Reece Sorting Development (Development). This report is intended to provide the City of Arlington (City) with the necessary traffic generation and trip distribution analysis to facilitate their review of the Development. Brad Lincoln, responsible for this report and traffic analysis, is a licensed professional engineer(Civil) in the State of Washington and member of the Washington State section of Institute of Transportation Engineers (ITE). The Development is proposed to consist of 33,075 square feet (SF) of a general light industrial debris sorting facility. The site is located on the south side of Cemetery Road, west of 67'h Avenue NE, on parcels 31051500200800 and 31051500200700. The site is currently occupied by industrial uses per the Snohomish County (County) Online Property Information (SCOPI) web map. A site vicinity map is included in Figure 1 and a site plan is provided in Appendix A. The Development is located inside County Transportation Service Area (TSA) A, within the Urban Growth Area (UGA). 2. METHODOLOGY Trip generation calculations for the Development have been performed using data contained in the ITE (2025) Trip Generation Manual, 12'h Edition. Additionally, as the likely use and activities are known, a check against those activities was also performed against the ITE trip generation manual. The distribution of trips generated by the site is based on surrounding land uses and general traffic patterns in the area. The City and County have an interlocal agreement that provides for reciprocal mitigation fees. The County mitigation fees can be calculated based on the default percentage in the interlocal agreement, which is 70%, or based on actual Impacts. The City also has an interlocal agreement with the Washington State Department of Transportation (WSDOT). Traffic mitigation fees are required for City developments when WSDOT improvement projects on the Exhibit C list are impacted with 10 or more PM peak hour trips. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 1 KH 090225009 NOR ,\ : _ F� , 530 ?11Ty (y E HIGHLAND DRIVE � e1ti. r N . W r 204TH STREET NE - `' 204TH STRO' CEMETERY ROAD 1 0 Uj ru rr L p � BJORN ROAD 188TH STREET NE A 1 �I1 W W �Ap ■ D C W W rep _ � X Ld= ■ -� — � J ■ s �m © Study Intersection _I � u� �IIIII ' Development Site FIGURE 1: SITE VICINITY MAP Klmley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) Kimley>))Horn Congestion at intersections and along roadways is generally measured in terms of level of service (LOS). In accordance with the Transportation Research Board's Highway Capacity Manual (HCM), 7t1 Edition, road facilities and intersections are rated between LOS A and LOS F, with LOS A being free flow and LOS F being forced flow or over-capacity conditions. The LOS at signalized, roundabout, and all-way stop-controlled intersections is based on the average delay of all approaches. The LOS for two-way stop-controlled intersections is based on average delays for the critical stopped approach. Geometric characteristics and conflicting traffic movements are taken into consideration when determining LOS values. A summary of the intersection LOS criteria is included in Table 1. Table 1: Level of Service Criteria ExpectedIntersection Control Delay Level of Service' Delay (Seconds per Vehicle) Unsignalized Signalized Intersections Intersections A Little/No Delay <10 <10 B Short Delays >10 and <15 >10 and <20 C Average Delays >15 and <25 >20 and <35 D Long Delays >25 and <35 >35 and <55 E Very Long Delays >35 and <50 >55 and <80 F Extreme Delays2 >50 >80 The City has established an acceptable level of service of LOS D. Source: Highway Capacity Manual, 7th Edition. LOS A: Free-flow traffic conditions, with minimal delay to stopped vehicles(no vehicle is delayed longer than one cycle at signalized intersection). LOS B: Generally stable traffic flow conditions. LOS C: Occasional back-ups may develop but delay to vehicles is short term and still tolerable. LOS D: During short periods of the peak hour, delays to approaching vehicles may be substantial but are tolerable during times of less demand (i.e., vehicles delayed one cycle or less at signal). LOS E: Intersections operate at or near capacity,with long queues developing on all approaches and long delays. LOS F: Jammed conditions on all approaches with excessively long delays and vehicles unable to move at times. 2 When demand volume exceeds the capacity of the lane, extreme delays will be encountered with queuing which may cause severe congestion affecting other traffic movements in the intersection. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 3 KH 090225009 Kimley>))Horn 3. TRIP GENERATION The Development is proposed to consist of 33,075 SF of a general industrial debris sorting facility via an open-sided roof structure. The trip generation calculations have been performed using data published in the ITE (2025) Trip Generation Manual, 12th Edition. The average trip generation rates for ITE Land Use Code (LUC) 110, General Light Industrial for 1,000 SF of Gross Floor Area (GFA) have been used for the trip generation. The existing site includes Reece Construction's corporate and industrial operations; however, these buildings will not be affected by the new construction and were not factored into the trip generation calculations. The ITE trip estimate was checked against the Development's business plan. The facility is expected to average 350 tons of inbound construction material per day. It is expected that 95% of the construction material will be contracted/hauled with container trucks average 15 tons per load. This would account for approximately 333 tons a day in 22 container trucks (333 / 15). The remaining 17 tons of debris are expected to arrive in personal trucks and average 0.75 tons per load, resulting in 23 personal trucks (17 / 0.75). This would account for a total of 45 vehicles (22 + 23) or the equivalent of 90 total vehicle trips (inbound and outbound). The waste will be sorted by two operators, one technical machine operator and one backhoe operator. Both operators are assumed to travel in their own vehicles, which would account for four more vehicle trips (two inbound and two outbound). Once all the waste is sorted, it leaves the facility in 30-ton semis. This would account for approximately 350 tons a day in 12 semis (350 / 30), resulting in 24 vehicle trips (12 x 2). Miscellaneous trips (inspections, visitors, etc.) are expected to account for another 2 to 10 trips a day. In summary, the average daily trip forecast is approximately: • 124 daily trips ■ 90 daily trips — inbound debris ■ 4 daily trips — operators ■ 24 daily trips —total of outbound debris ■ 6 daily trips— miscellaneous trips The facility is expected to be open 7AM to 5PM. Professional drivers typically try to avoid the commuter peak hours, but assuming 10% to 15% of the vehicle trips occur during the PM peak hour, that would result in 12 to 18 PM peak hour trips. The assumption that 10% to 15% of the trips occur in the PM peak hour is based on the comparison of daily to PM peak hour trip rates for industrial uses published by ITE. The evaluation of the business plan shows ITE general light industrial trip generation is in line with the expected trips and therefore the standard ITE rates have been used for the trip generation calculations. The trip generation is documented in Table 2. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 4 KH 090225009 Kimley >>> Horn Table 2: ITE 121 Edition Trip Generation Summary Average33,075 SF D. Trips General Light Industrial In Ou In Out ITE LUC 110 tMAW EPW Generation Rate 3.6 trips per 1,000 SF 0.49 trips per 1,000 SF Splits 50% 50% 100% 24% 76% 100% Trips 60 59 119 4 12 16 The Development is anticipated to generate approximately 119 new ADTs with approximately 16 new PM peak hour trips. The trip generation calculations are provided in Appendix B. 4. TRIP DISTRIBUTION The distribution of trips is based on existing counts at the site access and surrounding uses. The anticipated trip distribution is: • 75% to and from the west along Cemetery Road ■ 50% to and from the south along Smokey Pointe Boulevard ■ 25% to and from the southeast along Airport Boulevard • 25% to and from the east along 204" Street NE ■ 15% to and from the north along 67th Avenue NE ■ 10% from the east along 204th Street NE Detailed trip distributions for the PM peak hour are shown in Figure 2. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 5 KH 090225009 , 530 ?11 Ty E HIGHLAND DRIVE N a NOT TO SCALE29 0� lh'IIlllr ti 41 1�--�3 ice' O�Z-->1 204TH STREET NE � ' 204TH STRO' CEMETERY ROAD _ �uc 0 LU ■ _ _ N W 1 r M ri 1 r-o , - - - - - - - - - -BJ.O.RN-ROAD- - _ _ _� I! 188TH STREET o \ MLU 01 �A Z Z 'O z z m W W F` a x p op ip ® Trip Distribution % � Inbound Trip Path I ' I► IRS V ` 531 _ Study Intersection •--* Outbound Trip Path Trips � _ �=m rllllll�lliiu nL��� ©i_ = r7 _ ' Development Site Outbound AWDT bound •• InTrips l ' FIGURE 2: DEVELOPMENT TRIP DISTRIBUTION - PM PEAK-HOUR Klmley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) Kimley >>> Horn 5. INTERSECTION LEVEL OF SERVICE CALCULATIONS The analysis has been performed for the existing, 2028 no-build, and 2028 build conditions to account for full buildout of the site. The level of service analysis has been performed at the following intersections during the PM peak: 1. Site Access at Cemetery Road Two-Way Stop-Control 5.2. Turning Movement Volumes The PM peak hour turning movement counts for the study intersections were collected by the independent counting firm IDAX in October 2025 from 4:00 PM to 6:00 PM. The analysis in this report is based on the Development trips occurring during the PM peak hour. The 2025 existing turning movement data is shown in Figure 3. The existing count data is included in Appendix C. The 2028 no-build turning movements have been calculated by applying a 2.0% annually compounding growth rate to the 2025 existing turning movements and are shown in Figure 4. The 2028 build turning movements at the study intersection have been calculated by adding the trips generated by the Development to the 2028 no-build turning movements and are shown in Figure 5. The turning movement data is included in Appendix D. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 7 KH 090225009 r r �^ ,\ J, : �� , 530 SITE ACCESS AT ?11Typ 111THIGHLAND DRIVE N \� AM CEMETERY ROAD I L NE JINN NOT TO SCALE j • _ 381 2 r W 204TH STREET NE 317� 1 — 204TH STRI& 4 CEMETERY ROAD I 0 Nzri © � • W I r � � � ■ � BJORN ROAD 188TH STREET NE 11 I� �► W W m O -■W W ' � c R > > ■ ■ D C re0 W W � MMElm mm , © Study Intersection . I r :,.� © _ �J■ _ , ``r.7 r�lllll111mlun���� =�r� - _, -L -, --- Ir Development Site � I�III� I PM—> Turning Movement Volumes • FIGURE 3: 2025 EXISTING TURNING MOVEMENTS Klmley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) �I r r �^ ,\ J,- : SITE ACCESS AT 211Typ "fE HIGHLAND DRIVE N \� sl 0- � , CEMETERY ROAD NOT TO SCALE 404 �2 204TH STREET NE ouu_�_ — 336—> 204TH STROG 4 CEMETERY ROAD 0 Nri © � • W r � � � ■ � i�� �� I� tom. 9 BJORN ROAD 188TH STREET NE 11 ML ' ■� I I� �► W W m -■W W ' ■ ■ D C re0 W W © Study Intersection 16T.11 _ �J■ ` r�lllll111mmn� � -�r� - Ila Development Site Pnn—> Turning Movement Volumes • FIGURE 4: 2028 NO-BUILD TURNING MOVEMENTS Klmley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) 0 Atrom � , 530 SITE ACCESS AT ?11 Ty E HIGHLAND DRIVE \� sl0� �f �� CEMETERY ROAD AL NE N A NOT TO SCALE J �404 T 0� �3 u W I 204TH STREET NE , « � _ 336� T ►, 204TH STR`G � CEMETERY ROAD19 1 = 1, LU CA W - ,� ■• I BJORN ROAD REET NE�L 11 ,�1.88TH�ST I� Z� W W �O O W W • ' W W I _■ G 531 © Study Intersection . , r—.+.� © _ �J■ i _ tv�T/��Illlll�lluuuu���_ ��r7 Development SitePm � Turning Movement Volumes Mimi FIGURE 5: 2028 BUILD TURNING MOVEMENTS Klmley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) Kimley >>> Horn 5.3. Level of Service Calculations The 2025 existing level of service calculations have been performed using the existing channelization, existing intersection control, peak hour factors, and heavy vehicle factors from the 2025 turning movement counts. These parameters have been used for existing, 2028 no-build, and 2028 build conditions. The analysis has been performed for the PM peak hour. The level of service summary for the PM peak hour is included in Table 3. Table 3: Level of Service Summary- PM Peak Hour Existing Conditions 1 • • 2028 Intersection • • • • • LOS Delay V/C 1 Site Access at B 12.8 0.03 B 13.2 0.04 B 14.3 0.07 Cemetery Road V/C=Volume-to-Capacity The analysis shows that the study intersection currently operates at LOS B with a delay of 12.8 seconds. The study intersection is anticipated to continue operating at LOS B under the 2028 no- build and 2028 build conditions. The intersection LOS calculations are provided in Appendix E. 6. COLLISION HISTORY Collision data was obtained from WSDOT for the time period between January 1, 2020, through December 31, 2024. The data shows a total of one collision at the site access and one collision within close proximity to the site access. The five-year collision rate has been calculated using PM peak hour volumes and a K-factor of 10 for the conversion of PM peak hour volumes to average daily traffic. The collision data is provided in Appendix F. 6.1. Collision Severity The number of collisions by severity are summarized by year in Table 4. Table 4: Collision Severity by Year Severity 2020 2021 _ 1423 2024 (K) Fatal Injury 0 0 0 0 0 0 (A) Suspected Serious Injury 0 0 0 0 0 0 (B) Suspected Minor Injury 0 1 0 0 0 1 (C) Possible Injury 0 0 0 0 0 0 (0) No Apparent Injury/ PDO 1 0 0 0 0 1 Total 1 1 0 0 0 2 Reece Sorting Facility February 2026 Traffic Impact Analysis Page 11 KH 090225009 Kimley >>> Horn The five-year collision data shows that there were zero fatal or serious injury collisions (0% of collisions), zero suspected minor injury collisions (0% of collisions), one possible injury collisions (50% of collisions), and one no apparent injury/property damage only collisions (50% of collisions). 6.2. Collision Types The number and types of collisions at the study intersection are summarized in Table 5. Table 5: Collision Type Summary Collision Type Per ersecti Rear- At Side • . . Same Fixed • Other . . Angle swipe Dir Dir. Object 1 Site Access at 0 0 0 1 0 1 0 7707 Cemetery Road The collision types are consistent with the anticipated collisions for the study intersections. 6.3. Collision Rates The collision rates at the study intersections have also been evaluated. The collisions per million entering vehicles (MEV) is the standard rate for intersections. The ADTs at the study intersection have been estimated using a rate of ten daily trips to one PM peak hour trip. The collision rates at the study intersections are summarized in Table 6. Table 6: Collision Rate Summary PM Peak Hour Total Collision 0 terse��klii Intersection Vol. K-Factor Collisions Rate 3 "L' 1. Site Access at Cemetery Road 652 10 2 0.17 The collision rate shows that the study intersection in the vicinity of the Development does not have an annual rate or a rate per MEV that would typically be deemed significant. 7. SITE ACCESS Site access for the Development is already existing via a driveway connecting to Cemetery Road. The site access is anticipated to remain operating at an acceptable LOS with the Development. 3 The collision rate is based on collisions per MEVs Reece Sorting Facility February 2026 Traffic Impact Analysis Page 12 KH 090225009 Kimley >>> Horn 8. TRAFFIC MITIGATION FEES The City collects traffic mitigation fees based on the number of new PM peak hour trips generated by a development. The City also has interlocal agreements with the County and WSDOT for traffic mitigation fees. 8.1. City of Arlington The City has a traffic mitigation fee of $3,355 per PM peak hour trip based on the current City Impact and Mitigation Fees worksheet. Additionally, the site is within the boundaries of the Cascade Industrial Center, as identified in the City Comprehensive Plan Section III: Subareas. The traffic mitigation fee for the Cascade Industrial Center is currently $5,841.39 per PM peak hour trip. The Development is anticipated to generate 16 new PM peak hour trips. These trips result in standard City traffic mitigation fees of$53,680.00 and Cascade Industrial Center fees of $93,462.24. The total City traffic mitigation fees for the Development will be $147,142.24. It is important to note that City traffic mitigation fees do not vest to the time of application. It is possible that the City mitigation fees will increase between the time of this report and when the traffic mitigation fees are required to be paid. 8.2. Snohomish County The City has an interlocal agreement with the County that provides for mitigation payments for impacts to County improvement projects. County fees are based on impacts to improvement projects included in the Transportation Needs Report (TNR). There are not any County projects on the TNR that will be impacted by three directional PM peak hour trips generated by the Development. County traffic mitigation fees should therefore not be a condition of approval for the Development. 8.3. Washington State Department of Transportation WSDOT improvement projects and their associated fees are based on the most recent Exhibit C list, which is part of the interlocal agreement between the County and WSDOT and is included in the attachments. WSDOT traffic mitigation fees are required for City developments when WSDOT improvement projects on the Exhibit C list are impacted with 10 or more PM peak hour trips. There are not any WSDOT projects on the Exhibit C List that will meet this threshold. WSDOT traffic mitigation fees should therefore not be required for the Development. 9. CONCLUSIONS The Development is proposed to consist of 33,075 SF of a general light industrial debris sorting facility. The site is located on the south side of Cemetery Road, west of 67th Avenue NE, on parcels 31051500200800 and 31051500200700. The site is currently occupied by industrial uses per the SCOPI web map. The Development is anticipated to generate approximately 119 new ADTs with approximately 16 new PM peak hour trips. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 13 KH 090225009 Kimley>))Horn The analysis shows that the study intersection currently operates at LOS B with a delay of 12.8 seconds. The study intersection is anticipated to continue operating at LOS B under the 2028 no- build and 2028 build conditions. The Development is anticipated to have City traffic mitigation fees totaling $147,142.24 based on the current City Impact and Mitigation Fees worksheet. County or WSDOT fees should not be required since the impacts will not reach the County and WSDOT thresholds. Reece Sorting Facility February 2026 Traffic Impact Analysis Page 14 KH 090225009 Kimley >>> Horn APPENDIX A SITE PLAN Page A PROJEOfi ORI TER IA SCOPE OF WORK 7 - � CONSTRUCT A NEW 21,512 S.F. OPEN SIDED ROOFED STRUCTURE THAT WILL PROTECT MATERIALS AND EQUIPMENT ASSOCIATED WITH A NEW CONSTRUCTION .:.-' - DEBRIS SORTING FACILITY. TAX ACCOUNT NO.: 51051500200500, 51051500200700 R I ` OPO CEM 31051500100500 51051500200aOO: Section 15 Township 31 Range OS Quarter NW PAR B z PER CITY ARL BLA PROD FILE NO PLN-468 REG AFN 201 a 1 1505002; BEIN6 PTN OF 5E1/4 NE1/4 51) SEC L — -� 31051500200100: L -- -- --—--—--� - EXISTING OFFICE 5ectlon 15 Township 31 Range 5 Quarter NW PAR A ® BUILDIN6 PER CITY ARL BLAPROJ FILE NO PLN-468 REG AFN r+ 201811305002; BEING PTN OF 5E1/4NE1/4 5D SEC N •EX 15T 1 N6 OFFICE ' • • • - -- - _ a Q BUILDING ' - - - GORES 0 � _ 2021 INTERNATIONAL BUILDIN6 CODE (IBC) EX. BLO6. IN TERNATIONAL NTERNATIONAL MECHANICAL CODE (IMG) _ 00746300001600 2021 NTERNATONAL FIRE CODE (IFG) 2021 UNIFORM PLUMBING CODE (UPG) 8 of E BUILDIN6 CRITERIA N oco -�;-__ ,.,,�M1 ■i ZONING: 6I - GENERAL INDUSTRIAL pp MAX. LOT COVERA6E: 100% _ EXISTING STORAGE (p I MAX. HE16HT (ZONIN6): 50' p BULDIN6 OCCUPANCY: F-I m CONSTRUCTION TYPE: IIB MAX. HEIGHT (IB(): 55' TABLE 504.3 E 31051500200800, FIRE 5PRINKLER5: YES 00 F I RE ALARM: NO O U (o ALLOWABLE BUILDIN6 AREA:(TABLE 504.3) d N t 00146500000-100 -12,000 S.F. ¢¢ E N •• I I PARKINS GALGULAT I ONS _ 559.91, REQU I RED PARKING: `2 ` EXISTING STORAGE N jN BUILDING S 88°52'48" E ----- TBD NIiJ� TOTAL REQUIRED: - LANDSGAP I NS GAL ONS NONE LANDSCAPE CATEGORY: NONE Ex I sT I N6 SCALE Ex 1571 N6 5TORA6E UTILITY DISTRICTS HOU5E ----------------____-- -{- BUILDIN65 POWER: SNOHOMISH CO. PUP -� E WATER: CITY OF ARLIN67ON _ ' SEWER: CITY OF APLIN67ON I I I 00746300001100 I " I CD cn I I I I r I � m 5 I o 51 FNT z Proton` O SITE p7;;M-E� r 1`, a N x z • 00146300001300 CD zi z U m00 Q ' CEMETERY, LL �I 200 NEW CONSTRUCTION DEBRIS m; SORTING FACILITY q: 10 1 X O O W d CD T CD I I m _._- w Ir a'J E Z �L < O W °' o O x • I .� 3 _ __ 250' •.� __ '� o W 0 N c w i •-' S T NE c N Q � rn -- .--- -- - �S88°10'10E 560.06' J a� f� 51051500201000 - _-v_ �' 510515002 00TOO Drawing: SITE PLAN VIOINITY MAP A1 .1 1" = b0'-011 ® NO SCALE ® >N­ NORTH NORTH 23c-4550 A - 1 Kimley >>> Horn APPENDIX B TRIP GENERATION Page B Reece Sorting Facility KH 090225009 Full Build ADT Trip Generation Calculations DIRECTIONALTRIP GENERATION CHARACTERISTICS . Land Use+Code Source ITE LUC Scale ITE Unit Equation/Rate Entering% Exiting% In Out Total 1 (110) General Light Industrial ITE 12th Ed 110 33.075 KSF T = 3.6(X) 50% 50% 60 59 119 2 Total: 60 59 119 Full Build PM Peak Hour Trip Generation Calculations DIRECTIONAL BASELINE TRIPS TRIP GENERATION CHARACTERISTICS DISTRIBUTION Land Use+Code Source ITE LUC Scale ITE Unit Equation/Rate Entering% Exiting% In Out Total 1 (110) General Light Industrial ITE 12th Ed 110 33.075 KSF T =0.49(X) 24% 76% 4 12 16 2 Total: 4 12 16 B - 1 Kimley >>> Horn APPENDIX C COUNT DATA Page C www.idaxdata.com Reece Access Rd Cemetery Rduja�, Date: 10/30/2025 N Peak Hour Count Period: 4:00 PM to 6:00 PM Peak Hour: 4:15 PM to 5:15 PM Cemetery Rd 4-- 381 <... 0 > 388 A < 0 TEV: 719 r 2 � * 0~ • 321> 317 PHF: 0.95 0 > �O 0 ~ o /� L 1 r 0 A325 0-1 Q 4 0 Cemetery Rdn 1 o 1.- 00 HV%: PHF r li"i) EB 4.0% 0.90 WB 1.0% 0.90 NB 20.0% 0.94 010 Ln SB - - TOTAL 2.8% 0.95 Two-Hour Count Summaries Cemetery Rd Cemetery Rd Reece Access Rd 0 Interval 15-min Rolling Start Eastbound Westbound Northbound Southbound Total One Hour UT LT TH RT UT LT TH RT UT LT TH RT UT LT TH RT 4:00 PM 0 0 73 0 0 1 84 0 0 5 0 5 0 0 0 0 168 0 4:15 PM 0 0 74 2 0 1 99 0 0 3 0 1 0 0 0 0 180 0 4:30 PM 0 0 89 0 0 0 86 0 0 1 0 3 0 0 0 0 179 0 4:45 PM 0 0 78 2 0 1 105 0 0 1 0 3 0 0 0 0 190 717 5:00 PM 0 0 76 0 0 0 91 0 0 2 0 1 0 0 0 0 170 719 5:15 PM 0 0 70 0 0 0 79 0 0 1 0 3 0 0 0 0 153 692 5:30 PM 0 0 67 0 0 0 87 0 0 0 0 0 0 0 0 0 154 667 5:45 PM 1 0 0 53 0 0 0 55 0 0 1 0 1 0 0 0 0 110 1 587 Count Total 0 0 580 4 0 3 686 0 0 14 0 17 0 0 0 0 1,304 0 All 0 0 317 4 0 2 381 0 0 7 0 8 0 0 0 0 719 0 Peak HV 0 0 10 3 0 1 3 0 0 2 0 1 0 0 0 0 20 0 Hour HV% - - 3% 75% - 50% 1% - - 29% - 13% - - - - 3% 0 Note:Two-hour count summary volumes include heavy vehicles but exclude bicycles in overall count. Interval Heavy Vehicle Totals Bicycles Pedestrians(Crossing Leg) Start EB WB NB SB Total EB WB NB SB Total East West North South Total 4:00 PM 3 1 1 0 5 0 0 0 0 0 0 0 0 0 0 4:15 PM 2 1 1 0 4 0 0 0 0 0 0 0 0 0 0 4:30 PM 4 0 1 0 5 0 0 0 0 0 0 0 0 0 0 4:45PM 3 2 1 0 6 0 0 0 0 0 0 0 0 0 0 5:00 PM 4 1 0 0 5 0 0 0 0 0 0 0 0 0 0 5:15 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5:30 PM 2 3 0 0 5 0 0 0 0 0 0 0 0 0 0 5:45 PM 1 0 0 0 1 0 0 0 0 0 1 0 0 0 0 0 Count Total 19 8 4 0 31 1 0 0 0 0 0 0 0 0 0 0 Peak Hr 13 4 3 0 20 1 0 0 0 0 0 0 0 0 0 0 project.manager.wa@igxdatl.com www.idaxdata.com Two-Hour Count Summaries - Heavy Vehicles Cemetery Rd Cemetery Rd Reece Access Rd 0 Interval 15-min Rolling Start Eastbound Westbound Northbound Southbound Total One Hour UT LT TH RT UT LT TH RT UT LT TH RT UT LT TH RT 4:00 PM 0 0 3 0 0 0 1 0 0 0 0 1 0 0 0 0 5 0 4:15PM 0 0 0 2 0 0 1 0 0 0 0 1 0 0 0 0 4 0 4:30 PM 0 0 4 0 0 0 0 0 0 1 0 0 0 0 0 0 5 0 4:45 PM 0 0 2 1 0 1 1 0 0 1 0 0 0 0 0 0 6 20 5:00 PM 0 0 4 0 0 0 1 0 0 0 0 0 0 0 0 0 5 20 5:15PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16 5:30 PM 0 0 2 0 0 0 3 0 0 0 0 0 0 0 0 0 5 16 5:45 PM 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 1 11 Count Total 0 0 16 3 0 1 7 0 0 2 0 2 0 0 0 0 31 0 Peak Hour 1 0 0 10 3 0 1 3 0 0 2 0 1 0 0 0 0 20 0 Two-Hour Count Summaries - Bikes Cemetery Rd Cemetery Rd Reece Access Rd 0 Interval 15-min Rolling Start Eastbound Westbound Northbound Southbound Total One Hour LT TH RT LT TH RT LT TH RT LT TH RT 4:00 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4:15PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4:30 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4:45PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5:00 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5:15PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5:30 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5:45 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Count Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Peak Hour 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Note:U-Turn volumes for bikes are included in Left-Turn,if any. project.manager.wa@icgdxdat�.com Kimley >>> Horn APPENDIX D TURNING MOVEMENT CALCULATIONS Page D 1 Driveway at Cemetery Road Synchro ID: 1 Existing Peds a 0 b Average Weekday Bikes 8 0 1 8 PM Peak-Hour 0 0 0 w 0 0 1 0 m a a u ❑ 4 R 0 a 4 Date: 10/30/2025 388 a 381 383 0 a 2 a T Data Source: TDG 0 709 Cemetery Road 719 Cemetery Road 708 0 North a 0 PHF: 0.95 0 321 317 a 325 8 a 4 ❑ Reece Site Access 8 EB HVF= 4% a d R p 0 d WB HVF= a co7 0 8 F NB HVF= 20% 6 21 15 SB HVF= 0% p 0 p Bikes a 0 a Peds No-Build Peds a 0 a Average Weekday Bikes 8 0 4 PM Peak-Hour 0 0 0 Y " 0 0 0 m 0- Year: 2028 a 8 ❑ Years of Growth= 3 p 0 a 0 p p Growth Rate= 2.0% 411 a 404 406 0 Growth Factor= 1.06 p 2 a T 0 751 Cemetery Road 761 Cemetery Road 750 0 North Grow Peds? No b 0 Grow Bikes? No 0 340 336 b 344 8 b 4 ❑ Reece Site Access 4 a d a 4 Za a in 7 0 8 6 21 15 F p 0 p Bikes a 0 b Peds Development Trips Peds a 0 b Average Weekday Bikes 8 0 8 PM Peak-Hour 0 0 0 0 0 0_j in a Development a 8 ❑ 4 0 a 0 a ft 9 a 0 1 0 a 1 a T 0 12 Cemetery Road 16 Cemetery Road 4 0 North a [T3 0 b 3 4 b ❑ Reece Site Access 8 a in 9 0 3 4 16 12 F p 0 p Bikes a 0 b Peds Build Trips Peds a 0 b Average Weekday Bikes 4 0 4 PM Peak-Hour I 0 0 0 Y _J 0 0 0 in a ? 4 ❑ p 0 a 0 a 4 420 a 404 407 0 a 3 a T 0 763 Cemetery Road 777 Cemetery Road 754 0 North a 0 [�7 b 347 8 b ❑ Reece Site Access 8 a in 16 0 11 F 10 37 27 p 0 p Bikes 0 b Peds D - 1 Kimley >>> Horn APPENDIX E LEVEL OF SERVICE ANALYSIS Page E HCM 7th TWSC 1: Site Access & Cemetery Road Reece Sorting Facility Lteised Int Delay,s/veh 0.3 NbvementW EBT EBR WBL W3T NBL Lane Configurations to 4 Y Traffic Vol,veh/h 317 4 2 381 7 8 Future Vol,veh/h 317 4 2 381 7 8 Conflicting Peds,#/hr 0 0 0 0 0 0 Sign Control Free Free Free Free Stop Stop RT Channelized - None - None - None Storage Length - - - - 0 - Veh in NEdian Storage,# 0 - - 0 0 - Grade,% 0 - - 0 0 - Peak Hour Factor 95 95 95 95 95 95 Heavy Vehicles,% 3 3 1 1 20 20 Mvmt Flow 334 4 2 401 7 8 Nhjor/Mnor Major Nlajor� Mnorl Conflicting Flow All 0 0 338 0 741 336 Stage 1 - - - - 336 - Stage 2 - - - - 405 - Critical Wray - - 4.11 - 6.6 6.4 Critical Hdwy Stg 1 - - - - 5.6 - Critical Hdv y Stg 2 - - - - 5.6 - Follow-up Hdwy - - 2.209 - 3.68 3.48 Pot Cap-1 Maneuver - - 1227 - 359 667 Stage 1 - - - - 686 - Stage 2 - - - - 636 - Platoon blocked,% - - - Nbv Cap-1 Maneuver - - 1227 - 358 667 Nbv Cap-2 Maneuver - - - - 358 - Stage 1 - - - - 686 - Stage 2 - - - - 635 - Approach EB W3 NB k1CMCtr1 D1y,s/v 0 0.04 12.83 HCMLOS B Mnorlane/NhjorMvmt MLnl EBT EBR WBL W3T Capacity(veh/h) 475 - - 9 - HCMLane V/C Ratio 0.033 - - 0.002 - I C-MCtrl Dly(s/v) 12.8 - - 7.9 0 F"Lane LOS B - - A A HCM95th°/file Q(veh) 0.1 - - 0 - 2025 Existing Conditions PM Peak Hour Kimley-Horn and Associates, Inc. [AB 090225009] Synchro 12 Report E - 1 HCM 7th TWSC 1: Site Access & Cemetery Road Reece Sorting Facility Lteisectio Int Delay,s/veh 0.3 NbvementW EBT EBR WBL WBT NBL Lane Configurations 11� .r Y Traffic Vol,veh/h 336 4 2 404 7 8 Future Vol,veh/h 336 4 2 404 7 8 Conflicting Peds,#/hr 0 0 0 0 0 0 Sign Control Free Free Free Free Stop Stop RT Channelized - None - None - None Storage Length - - - - 0 - Veh in Ntdian Storage,# 0 - - 0 0 - Grade,% 0 - - 0 0 - Peak Hour Factor 95 95 95 95 95 95 Heavy Vehicles,% 3 3 1 1 20 20 Mvmt Flow 354 4 2 425 7 8 Nhjor/Mnor Nhjor Nhjo—rT--Mnorl Conflicting Flow All 0 0 358 0 785 356 Stage 1 - - - - 356 - Stage 2 - - - - 429 - Critical Hdwy - - 4.11 - 6.6 6.4 Critical Hdwy Stg 1 - - - - 5.6 - Critical I Idv y Stg 2 - - - - 5.6 - Follow-up Hdwy - - 2.209 - 3.68 3.48 Pot Cap-1 Nhneuver - - 1206 Stage 1 - - - - 671 - Stage 2 - - - Platoon blocked,% - - - Nbv Cap-1 Nhneuver - - 1206 Nbv Cap-2 Nhneuver - - - - 336 - Stage 1 - - - Stage 2 - - - - 618 - approach EB WB k1 MCtrl D1y,s/v 0 0.04 HCMLOS B T Mnorlane/NhjorMvmt NBLnl EBT EBR WBL WBT Capacity(veh/h) 453 - - 9 - HCMLane V/C Ratio 0.035 - - 0.002 - 1"Ctrl Dly(s/v) 13.2 - - 8 0 HCMLane LOS B - - A A HCM95th°/file Q(veh) 0.1 - - 0 - 2028 No-Build Conditions PM Peak Hour Kimley-Horn and Associates, Inc. [AB 090225009] Synchro 12 Report E - 2 HCM 7th TWSC 1: Site Access & Cemetery Road Reece Sorting Facility Lteisect'. Int Delay,s/veh 0.5 NbvementW EBT EBR WBL WBT NBL NBR Lane Configurations 11� .j Y Traffic Vol,veh/h 336 7 3 404 16 11 Future Vol,veh/h 336 7 3 404 16 11 Conflicting Peds,#/hr 0 0 0 0 0 0 Sign Control Free Free Free Free Stop Stop RT Channelized - None - None - None Storage Length - - - - 0 - Veh in Nhdian Storage,# 0 - - 0 0 - Grade,% 0 - - 0 0 - Peak Hour Factor 95 95 95 95 95 95 Heavy Vehicles,% 3 3 1 1 20 20 Mvmt Flow 354 7 3 425 17 12 Nhjor/Mnor Major Nhjor2 — Mnorl Conflicting Flow All 0 0 361 0 789 357 Stage 1 - - - - 357 - Stage 2 - - - - 432 - Critical Hdwy - - 4.11 - 6.6 6.4 Critical Hdwy Stg 1 - - - - 5.6 - Critical Hdv y Stg 2 - - - - 5.6 - Follow-up Hdwy - - 2.209 - 3.68 3.48 Pot Cap-1 Nhneuver - - 1203 - 336 648 Stage 1 - - - - 670 - Stage 2 - - - - 618 - Platoon blocked,% - - - Nbv Cap-1 Nhneuver - - 1203 - 334 648 Nbv Cap-2 Nhneuver - - - - 334 - Stage 1 - - - - 670 - Stage 2 - - - - 616 - Approach EB WB NB k1 MCtrl D1y,s/v 0 0.06 14.28 HCMLOS B Mnorlane/NhjorMvmt MLnl EBT EBR WBL WBT Capacity(veh/h) 417 - - 13 - F"Lane V/C Ratio 0.068 - - 0.003 - 1"CO Dly(s/v) 14.3 - - 8 0 HCMLane LOS B - - A A HCM95th°/file Q(veh) 0.2 - - 0 - 2028 Build Conditions PM Peak Hour Kimley-Horn and Associates, Inc. [AB 090225009] Synchro 12 Report E - 3 Kimley >>> Horn APPENDIX F COLLISION DATA Page F N NOT TO SCALE CEMETERY ROAD W Z W n Z W G Q Q = O OG � t- W U) Z W 2024 Collisions 2023 Collisions 2022 Collisions 2021 Collisions 2020 Collisions 2020 - 2024 COLLISION HISTORY Kimley>>> Horn REECE SORTING FACILITY - CITY OF ARLINGTON, WA (KH 090225009) Collision Data Table Reece Sorting Facility-Arlington, WA REPORT NUMBER DATE TIME PRIMARY ROADWAY CROSS STREET SEVERITY #VEHICLES #PEDS #BIKES COLLISION TYPE VEHICLE 1 MANEUVER VEHICLE 2 MANEUVER EA65569 2020-09-21 8:30 CEMETERY RD SITE ACCESS No Apparent Injury 2 0 0 From opposite direction-one left turn-one straight Making Left Turn Going Straight Ahead EB34272 2021-05-29 8:26 CEMETERY RD SITE ACCESS Suspected Minor Injury 1 0 0 Utility Pole Negotiating a Curve - Kimley>>>Horn F - 2