FINAL MINOR PLAT
STAFF REPORT AND PERMIT DECISION
GENERAL INFORMATION
File Number: PLN#1388/ PJ#26-0057
Project Title: Jensen 4
Owner/Applicant: Corstone Contractors, LLC
Contact: Ali Tapert
Description: 4-lot Final Minor Unit Lot Subdivision
Location: 7917 Jensen Farm Lane
Tax Parcel ID: 00893800000500
Lot Size: 0.31 acres (13,674 square feet)
Zoning Classification: Residential High Capacity
Land Use Designation: Residential High Capacity
City Approvals Required: Final Minor Plat, Right of Way Permit, Civil Major Permit,
Building Permits
Date of Decision: February 24, 2026
Decision: APPROVED,with conditions
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 1 of 9
I. NATURE OF APPLICATION
A. Request
The applicant is proposing a 4-lot final minor plat dividing the subject parcel into four (4) fee simple
townhome lots utilizing the AMC 20.44 Unit Lot Subdivision process. Access to the site is via private
access tract off Jensen Farm Lane.Two (2) open space/stormwater tracts are proposed for the required
open space and drainage requirements for the site. An existing gas line easement runs parallel to the
north line of the project at the rear yard of lots 1-4 and tract 997, within the rear yard setback. The
preliminary minor unit lot subdivision was approved by the Community and Economic Development
Department on October 14, 2024 and has subsequently completed all required improvements and met
all required conditions.
B. Project Chronology/Background
A formal application for the final minor plat was submitted to the Community&Economic Development
Department on August 22, 2025, 2025. Staff routed the material to City review staff the same day.
Additional information and documentation was provided on December 3, 2025, December 30, 2025,
January 20, 2026,January 27, 2026 and February 24, 2026.
C. Site Location/Description
c
y
Proposed Site
The project is located on the north side of Jensen Farm Lane,
east of the intersection of Jensen Farm Lane and Anna Lane.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 2of9
D. Site and Adjacent Zoning/Uses
Proposed Site
=Residential High Capacity =Public Semi Public
Area Zoning Existing Use
Subject Site Residential High Capacity Single-Family Residence
North Public/Semi Public Community Park
South Residential High Capacity Single-Family Residence
East Residential High Capacity Single-Family Residence
West Residential High Capacity Community Park
II. COMPLIANCE WITH CONDITIONS OF THE PRELIMINARY MINOR PLAT
1. All development shall be in substantial conformance with the approved Preliminary Unit Lot
Subdivision and Landscape Plans received on August 15, 2024, subject to any conditions or
modifications that may be required as part of the permit review.
The final minor plat site plan is in compliance with the approved preliminary plat site plan.
The signed digital copy was received on January 24,2026.
2. The applicant shall meet all local, state, or federal code requirements. Please refer to the
Arlington Municipal Code for a complete list of code requirements for your project type.
This condition is on-going until the single-family residences receive final occupancy
approval.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 3of9
3. The Preliminary Unit Lot Subdivision shall comply with all permits and conditions thereof from
the City of Arlington and other government agencies with jurisdiction.
This condition is on-going until the single-family residences receive final occupancy
approval.
4. The development is subject to the following traffic impact fees for 4 new PM peak-hour trips for
4 new dwelling units:
o City of Arlington Traffic Impact Fees: $13,420.00 ($3,355.00 for each unit).
Payment of Traffic Impact Fees is required at the time of building permit issuance of the
single-family residence.
S. The development is subject to the following school mitigation fees for 4 new dwelling units:
o Arlington School District Mitigation Fees: $16,008.00 ($4,002.00 for each unit).
Proof of payment to the Arlington School District is required at or prior to the building
permit issuance of each single-family residence.
6. The development is subject to the following neighborhood and community park impact fees for
4 new single-family dwelling units:
o Community Park Impact Fees: $6,648.00 ($1,662.00 for each unit)
Payment of Park Impact Fees is required at the time of building permit issuance of each
single-family residence.
7. Impact fees do not vest and are based off the fees in pace at the time of payment or building
permit issuance.
This condition is on-going until the single-family residences receive final occupancy
approval.
8. The applicant is required to apply for a Civil Construction Permit and receive approval prior to
any land disturbance or work commencing to the site.
The city issued approval of Civil Major permit#3841 on May 28,2025 for site civil work for
the townhome project.
9. The applicant shall submit a lighting plan meeting requirements of 20.60 with the Civil
construction Permit.
No street lighting is proposed with this application as Jensen Farm Lane is adequately lit.
Building lighting is to be reviewed and approved at building permit per condition of
Administrative Design Review approval dated January 22,2025.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 4of9
10. The project is subject to submit a Right-of-Way Permit for all work within the public rights-of-
way.
This condition is on-going. Any work, use, or occupancy within City right-of-way shall
require a separate right-of-way permit issued by the city prior to commencement of such
work. Compliance will be verified through the City's right-of-way permitting and inspection
process.
11. The project is required to meet the most current version of the Department of Ecology
Stormwater Manual for Western Washington and the City of Arlington Engineering Standards
for the specific details of the project.
The city issued approval of Civil Major Permit#3841 on May 28,2025 for site civil work for
the townhome project,satisfying this condition.
12. The applicant shall submit a copy of the incorporation of the Homeowner's Association and the
Covenants,Conditions,and Restrictions with the final minor unit lot subdivision application.The
CC&Rs shall include the following:
o No storage of inoperable motor vehicles.
o Maintenances of private lots,buildings and abutting right-of-way for the site.
The applicant provided the required documents demonstrating compliance with this
condition. This condition has been satisfied.
13. The proposed townhouse structure is required to meet the Development Design Standards. Per
AMC 20.44.020A(c) prior to submittal of the final plat,the design of all buildings shall meet the
design standards and shall have received design review approval.
The design of all buildings was reviewed for conformance with the Development Design
Standards and received design review approval on January 22,2025.
14. The applicant shall complete all required Civil Construction improvements on the site.
All required Civil Construction improvements on the site have been completed, satisfying
this condition.
15. The applicant shall submit as-builts, acquire all required bonds, and complete the civil
construction punch list for the project.
As-builts, bonds, and civil construction punch list for the project have been approved with
Civil Major Permit#3841,satisfying this condition.
16. The applicant shall provide the conditions found in AMC 20.44.020N on the face of the final plat
document.
The required conditions are shown as items 1-4 under the Conditions, Covenants and
Restrictions on sheet 2 of the final plat document.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 5of9
17. The applicant shall provide language to be placed on the final unit lot subdivision that notifies
future property owners of possible effects from aviation activities and the proximity of the
Arlington Municipal Airport.
The required notification is shown as item #5 under the Conditions, Covenants and
Restrictions on sheet 2 of the final plat document. This condition has been met.
18. The proposed townhome garages shall be recessed from the face of the primary structure a
minimum of four (4) feet and approved with Design Review prior to final minor unit lot
subdivision submittal.
The design of all buildings was reviewed for conformance with the Development Design
Standards and received design review approval on January 22,2025.
19. The proposed project shall provide sufficient lighting throughout the site that will illuminate the
public road,private drive,parking areas and residences.The final lighting plan shall be approved
with the Civil Permit.
No street lighting is provided with this application as Jensen Farm Lane is adequately lit.
Building lighting is to be reviewed and approved at building permit per condition of Design
Review approval.
20. A condition of final minor unit lot subdivision approval shall be specification of ownership of the
common areas within the subdivision.The applicant shall provide a condition on the face of the
final minor unit lot subdivision that the ownership of the common areas is the responsibility of
the homeowners association.
Declaration on the face of the final minor unit lot subdivision designates the Jensen Farm
Townhomes Association (HOA) as having ownership of the common areas in perpetuity,
satisfying this condition.
21. The applicant shall provide a condition on the face of the final minor unit lot subdivision that no
parking is allowed along the private drive.
This condition has been met via Condition, Covenants and Restrictions number 9 on sheet 2
of the final minor unit lot subdivision.
22. The utilities proposed with the preliminary minor unit lot subdivision are required to be
installed per the Public Works Construction Standards and Specifications. The final approval of
all utilities is completed with the civil permit. All utility installation shall be approved prior to
final unit lot subdivision approval.
The city issued approval of Civil Major permit#3841 on May 28,2025 for site civil work for
the townhome project and as-builts were approved on February 6,2026.
23. The final unit lot subdivision shall be recorded at Snohomish County Auditor's Office and the
recorded document returned to the City of Arlington prior to issuance of any Building Permits.
If a conformed copy of the recorded documents are not returned to the City of Arlington
within 30 days of the date signed by the city, the city may expire the final plat decision and
withhold building permits.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 6of9
24. The proposed building plans shall be incompliance with the approved Design Review Board
Decision issued on February 23, 2024.
This condition is on-going until the single-family residences receive final occupancy
approval.
25. The project is subject to applicable water and sewer utility fees. These fees are collected at the
time of building permit issuance.
This condition is on-going until the single-family residences receive final occupancy
approval.
26. Prior to issuance of building permits, all associated impact fees shall be paid.
This condition is on-going until the single-family residences receive final occupancy
approval.
27. All contractors working on the site are required to obtain a Washington State Business License
and a City of Arlington Endorsement.
This condition is on-going until the single-family residences receive final occupancy
approval.
28. The placement of Snohomish County PUD transformer cases shall be reviewed and approved by
the city.All cases that abut public right-of-way are required to be decoratively wrapped.
This condition is on-going until the single-family residences receive final occupancy
approval.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 7 of 9
III. CONCLUSIONS
Under AMC 20.16.220(b),the Community Development Director shall issue the requested zoning
permit unless he concludes after reviewing the application that:
Regulation Analysis Meets
(1)The requested permit is not within its The requested final minor plat is within
jurisdiction according to the table of the City of Arlington's jurisdiction per the Yes
permissible uses. zoning map and permissible use table.
(2)The application is incomplete. The application for the subject final minor
plat was deemed complete on December 8, Yes
2025.
(3) If completed as proposed in the The proposed final minor plat complies
application,the development will not comply with all required sections of AMC Title 20 Yes
with one or more of the requirements of this per the above staff analysis.
title.
(4) The proposed project has not complied WAC 197-11-800(1) allows exemptions
with SE PA. from review under the State
Environmental Policy Act for minor new Yes
construction resulting in 4 multi-family
residential units.
(5)The proposed project is not in The proposed final minor plat divides the
conformance with the Comprehensive Plan, property into four parcels,which complies
Transportation Plan,and the Arlington with the Arlington Municipal Code, Yes
Municipal Code. Comprehensive Plan,and Transportation
Plan.
IV. APPEAL
This decision may be appealed pursuant to AMC 20.20.010, which provides for a hearing of the
zoning permit decision before the Hearing Examiner. Any aggrieved party of record may file an
appeal within 14 days of the permit decision. An appeal shall be considered filed when a written
notice of appeal,specifying the grounds and arguments,therefore,is delivered to the Department of
Community and Economic Development by 5:00 PM on Tuesday.March 10,2026,and the appeal fee
as set by resolution is paid.
Zoning Permit
Jensen 4 Final Minor Plat-PLN#1388/PJ#26-0057
Page 8of9
V. DECISION
The zoning permit is hereby APPROVED, subject to the conditions specified above.
VI. EXHIBITS
1. Jensen 4 Final Minor Plat-Zoning Permit- PLN #1388/PJ#26-0057 (on file at CED Office)
2. Jensen 4 Preliminary Minor Plat-Zoning Permit- PLN #1228 (on file at CED Office)
Prepared by: Jen Haugen, Planning Manager
Date: February 24, 2026
ORDERED THIS ON THE 24th DAY OF February 2026
/YL-
Amy Rusko, Community and Economic Development Department Director