HomeMy WebLinkAbout102 E Division St_PWD3104_2026
Complete package constitutes all items. Only complete submittals will be accepted.
Civil - Submittal Requirements, Type I:
ï² Complete Application;
ï² Construction Plans including cut / fill quantities;
ï‚§ 2 full size plan sets 22†x 34â€
ï‚§ PDF file of the complete plan set
ï‚§ 2 full size set of landscape plans 22†x 34â€
ï² Marysville Utility plans, if applicable (2 sets);
ï² Drainage Analysis including calculations and downstream analysis (2 sets) and (PDF file); refer to Stormwater Drainage
Requirements;
ï² Geotechnical Report (2 sets) and (PDF file);
ï² SEPA is required if 500 or more cubic yards of cut / fill is proposed (not required if included with a Land Use Permit);
ï² Grading cut / fill quantity: _______________________________;750CY Cut / 600CY Fill
ï² Design Vehicle – demonstrate turning radius include 45’ Fire truck, dual axle, 256 inch wheel base;
ï² Complete Streets Checklist
ï² Drafts of easement(s) dedication(s), and/or CAPE(s) for review;
ï² Flood Hazard Permit Application and required documentation if project is within 100 year flood plain; refer to Flood
Hazard guidance documents;
ï² Construction Calculation Worksheet;
ï² NPDES Permit (if required); See Storm Water Drainage Report, New or Redevelopment Flowcharts;
ï² Assurance Device will be required prior to Permit Issuance (Bond or Assignment of Funds);
ï² Permit Fee due at time of permit submittal.
Grading / Paving / Drainage Submittal Requirements, Type II:
ï² Complete Application;
ï² Construction Plans including import/export quantities;
ï‚§ 2 full size plan sets 22†x 34â€
ï‚§ PDF file of the complete plan set
ï² Drainage Analysis including calculations and downstream analysis (2 sets) and (PDF file); refer to Stormwater Drainage
Requirements;
ï² Geotechnical Report (2 sets) and (PDF file);
ï² SEPA is required if 500 or more cubic yards of cut/fill is proposed (not required if included with a Land Use Permit);
ï² Grading cut / fill quantity: _______________________________;
ï² Construction Calculation Worksheet;
ï² NPDES Permit (if required); See Storm Water Drainage Report, New or Redevelopment Flowcharts;
ï² Permit fee due at time of permit submittal.
Right of Way Submittal Requirements, Type III:
ï² Complete Application;
ï² Construction Plans;
ï² Traffic Control Plan;
ï² Road Closure Request;
ï² Temporary Erosion & Sediment Control (TESC) Plan;
ï² Certificate of Insurance with the City of Arlington named as Additional Insured;
ï² Assurance Device will be required prior to Permit Issuance (Bond or Assignment of Funds);
ï² Engineers Estimated Cost of Construction; $______________________________________;
ï² Permit fee due at time of permit issuance.
Page 2 of 2
COMPLETE STREETS CHECKLIST
Community & Economic Development
City of Arlington • 18204 59th Avenue NE • Arlington, WA 98223 • Phone (360) 403-3551
Project Name: Email:
Project Manager/Owner:
Phone No.:
Description of Scope:
Roadway Classification:
ï² Principal ï² Minor ï² Collector ï² Non-Arterial ï² Boulevard ï² Alley
Cross Connection Type:
ï² Downtown ï² Urban Center Connector ï² Neighborhood Yield
ï² Downtown Neighborhood ï² Industrial Access ï² Mixed Use Overlay
ï² Urban Village Main ï² Neighborhood Corridor ï² Smokey Point Corridor
ï² Urban Village Neighborhood ï² Neighborhood Curbless
Page 1 of 7 Revised 8/18
1. CHANNELIZATION
Average Daily Trips: Should re-channelization
Contact Public Works 360-403-3512 be considered in the
project scope?
Speed Limit:
Current image or typical existing cross-section of street in project area
(showing lane configuration):
2. PAVEMENT CONDITIONS
Does the existing road maintain the minimum Overall Condition Index (OCI) as set
ï² Yes ï² No
forth in the Transportation Benefit District?
Contact Public Works for current OCI and Standards 360-403-3512.
Has the installation of traffic circles been considered? ï² Yes ï² No
Is this project on the city’s Transportation Improvement Plan? ï² Yes ï² No
Should pavement repair be considered through this project? ï² Yes ï² No
If yes, please explain.
3. PEDESTRIAN INFRASTRUCTURE
Is this area identified in the City of Arlington Pedestrian Improvement Plan? If so,
ï² Yes ï² No
have the recommendations been met?
Explain how or why not.
People walking or using a mobility device: Is the project fully served by sidewalks,
ï² Yes ï² No
accessible curb ramps, and safe crosswalks? If not, are new/repaired sidewalks,
curb ramps, and crosswalks included in the project?
Page 2 of 7 Revised 8/18
Explain how or why not.
Are existing sidewalk in good condition? ï² Yes ï² No
Has an initial assessment of trees and sidewalk conditions been conducted with ï² Yes ï² No
and engineer and arborist/landscape architect?
Are there missing sidewalk in the project area?
ï² Yes ï² No
If yes, explain how this will be corrected?
Crossing Width (number of lanes) _______________ Controlled Stop Spacing ______________________________
Does the project propose mid-block crossings to reduce distance between
ï² Yes ï² No
crossings?
Is there pedestrian refuge or flashing beacons in the project area?
ï² Yes ï² No
Explain pedestrian existing crossing convenience, visibility and safety; does the project target improvements to accessibility?
Have the addition of curb bulb outs been considered to slow traffic and reduce
ï² Yes ï² No
crossing width?
Describe how the building(s) have been oriented to address the adjacent roadway with visible connected
sidewalks that encourage and enhance pedestrian circulation.
Describe pedestrian facilities added such as benches, trash receptacles, visual interest, shade and plantings.
Page 3 of 7 Revised 8/18
4. BICYCLE INFRASTRUCTURE
Is this area identified in the City of Arlington Bicycle Improvement Plan?
ï² Yes ï² No
If so, have the recommendations been met? Explain how or why not.
Is the project site fully served by bicycle facilities? If not, are new bicycle facilities
ï² Yes ï² No
included in the project?
Explain how or why not.
Does this project meet the needs of a variety of bicycle users?
ï² Yes ï² No
(Family vs. Commuter) How?
Describe how the building(s) serve and invite bicycle traffic, e.g. covered bike racks, visual interest, smooth
transitions, bicycle focused travel ways.
5. TRANSIT INFRASTRUCTURE
Transit Classification: ï² Major Transit Route ï² Minor Transit Route
Is the project identified on the City of Arlington Transit Expansion Plan? ï² Yes ï² No
ï‚· Are there bus stops on the project area? ï² Yes ï² No
ï‚· Are all bus stops in the project area within close proximity to a controlled
ï² Yes ï² No
crossing?
ï‚· Average distance between bus stops in/adjacent to project area?
ï‚· If bus stops are less than 0.2 miles (1056 ft.) apart, can stops be consolidated?
Explain:
Page 4 of 7 Revised 8/18
Does the stop provide cover and seating? ï² Yes ï² No
How or why not.
Does the project add visual interest, shading, lighting, plantings, or traffic buffers?
ï² Yes ï² No
Explain how the project improves transit users’ comfort and convenience.
Is the transit stop ADA accessible? If not, how does the project propose to provide
ï² Yes ï² No
accessibility?
How or why not.
6. FREIGHT INFRASTRUCTURE
Is the project on an identified City of Arlington Freight Route? ï² Yes ï² No
Does the project area meet the curb radius and clearance standards? ï² Yes ï² No
Are there spot improvements needed for the project area? (pavement depth) ï² Yes ï² No
7. STREET TREES AND LANDSCAPING
Describe any existing street trees and landscaping assets within the project limits that warrant project
investment to sustain (e.g. preservation of street trees):
Is there an opportunity to plant trees or expand landscape? ï² Yes ï² No
Page 5 of 7 Revised 8/18
Will there be long-term street tree and landscaping maintenance required for this
ï² Yes ï² No
project?
How will the maintenance of plants be addressed?
Are street median planting proposed in the project area? ï² Yes ï² No
Does the project include any environmental elements? E.g.: street trees, reduced
ï² Yes ï² No
pavement, bio-infiltration, vegetated bump outs, native/drought tolerant
vegetation, or other environmental improvements to be implemented with the
project?
Explain how or why not.
8. URBAN DESIGN AND PLANNING
If an adopted subarea or action plan applies to this project, has its
ï² Yes ï² No
recommendations relevant to improved streets/ROW been met?
Explain how or why not.
Has connectivity been improved for all modes of travel?
ï² Yes ï² No
Explain specifically for each mode of travel.
Is there an opportunity to implement artistic elements (e.g. sidewalk inlays,
ï² Yes ï² No
creative street furniture, or bollards or planters, creative bicycle racks etc.) in the
project area? Explain how.
Page 6 of 7 Revised 8/18
Describe Public Art or Art Opportunities:
ï² Yes ï² No
Arlington Art Council may be a resource 360-435-3778 or arlingtonartscouncil.net
CITY USE ONLY
Approval Determination
ï² This project meets or exceeds the City of Arlington Complete Streets Standards.
ï² This project will meet the City of Arlington Complete Street Standards with the following changes.
ï² This project does not meet the City of Arlington Complete Street Standards. Please revisit the following
sections and resubmit.
Variance Determination
ï² This project does not meet the City of Arlington Complete Street Standards. Project proponent has
applied for a variance through the variance process and variance has been approved.
ï² The variance has been denied, please revisit the following sections and resubmit.
Page 7 of 7 Revised 8/18
CONTRUCTION PLAN REVIEW &
INSPECTION FEE WORKSHEET
Community & Economic Development Department
City of Arlington ï€ ï€ ï€ ï€ ï€
ï¬ 18204 59th Avenue NE ï¬ Arlington WA 98223 ï¬ (360) 403-3551
This form is to be completed and submitted with Type I , Type II Type III Construction Permit Application.
1) Based on permit type requested (Type I, Type II or Type III), complete the form as follows:
ï¬ï€ Type I permits complete all sections.
ï¬ Type II permits complete as follows:
- Grading Only - Complete Temporary Erosion and Sediment Control (TESC).
- Stormwater Drainage Only - Complete the Temporary Erosion and Sediment Control and Stormwater
Drainage Section for Public or Private
ï¬ï€ Type III permits complete the Temporary Erosion and Sediment Control (TESC).
2) The developer shall enter the quantities shown on the construction drawings into the Construction Calculation
Worksheet. This document is used to determine the amount of plan reivew and inspection fees due to the city.
3) Excel will auto-calculate the relevant fields and subtotals throughout the document. Only the 'Quantity' columns should
be completed.
4)
The summary page calculates the fees due at intake for Civil and Stormwater Drainage construction permits only. This
does not include fees for Grading or those required by other departments or agencies. Grading fees are based on Cubic
Yard Quantity and shall be calculated at time of permit submittal. Grading fees shall be paid at permit submittal.
5) If an item that is part of your project does not exist in the spreadsheet complete the Write-In-Items section with the item,
quantity and associated unit cost. There are a few unit prices that are blank, please complete them accordingly.
6) Inspection fees shall be calculated for Private Development during the review process and shall be paid upon permit
issuance.
PROJECT COSTS PUBLIC TOTAL PRIVATE TOTAL TOTAL PROJECT COST
$ 172,479.38 $ 107,506.25 $ 279,985.63
OK
PLAN REVIEW & INSPECTION FEES
PLAN REVIEW & INSPECTION FEE (6% of Project Value) $ -
GRADING FEE (4) (Cubic Yard ) $ -
Review fees due at time of submittal Total Review Fees Due $ -
An Assurance Device such as a Performance Bond or Assignment of Funds needs to be on file with the City of Arlington prior
to permit issuance. The Assurance Device shall be 150% of the Construction Calculation Worksheet which are as follows:
ï¬ Road and Alley (Public)
ï¬ Stormwater Drainage and Grading (Public)
ï¬ Utilities (Public)
ï¬ Temporary Erosion and Sediment Control (Public and Private)
ASSURANCE DEVICE
Base Calculation of Performance Device $ 172,479.38
PERFORMANCE DEVICE 150% Amount Due $ 258,719.06
Base Calculation of Maintenance Device $ 168,491.25
MAINTENANCE DEVICE 20% Amount Due $ 33,698.25
1 Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
TEMPORARY EROSION & SEDIMENT CONTROL Include Public Improvements & Private Development
Description Unit Price Unit Quantity Cost Reference #
Backfill & compaction-embankment $ 6.50 CY $ -
Check dams $ 78.00 EACH $ - BMP C207
Catch Basin Protection $ 35.50 EACH 11 $ 390.50
Crushed surfacing 1 1/4" minus $ 18.00 TON $ - WSDOT 9-03.9(3)
Ditching $ 8.00 CY $ -
Excavation-bulk $ 3.00 CY $ -
Fence, silt $ 2.00 LF 500 $ 1,000.00 BMP C233
Fence, Temporary (NGPA) $ 2.00 LF $ -
Geotextile Fabric $ 2.50 SY $ -
Hay Bale Silt Trap $ 0.50 EACH $ -
Hydroseeding $ 4,200.00 ACRE $ - BMP C120
Interceptor Swale / Dike $ 1.00 LF $ -
Jute Mesh $ 2.00 SY $ - BMP C122
Level Spreader $ 1.75 LF $ -
Mulch, by hand, straw, 3" deep $ 3.00 SY $ - BMP C121
Mulch, by machine, straw, 2" deep $ 1.00 SY $ - BMP C121
Piping, temporary, CPP, 6" $ 12.50 LF $ -
Piping, temporary, CPP, 8" $ 19.00 LF $ -
Piping, temporary, CPP, 12" $ 24.00 LF $ -
Plastic covering, 6mm thick, sandbagged $ 3.00 SY $ - BMP C123
Rip Rap, machine placed; slopes $ 50.00 CY $ - WSDOT 9-13.1(2)
Rock Construction Entrance, 50'x15'x1' $ 1,800.00 EACH 1 $ 1,800.00 BMP C105
Rock Construction Entrance, 100'x15'x1' $ 3,600.00 EACH $ - BMP C105
Sediment pond riser assembly $ 3,050.00 EACH $ - BMP C241
Sediment trap, 5' high berm $ 21.00 LF $ - BMP C240
Sed. trap, 5' high, riprapped spillway berm section $ 79.00 LF $ - BMP C240
Seeding, by hand $ 1.00 SY $ - BMP C120
Sodding, 1" deep, level ground $ 8.00 SY $ - BMP C120
Sodding, 1" deep, sloped ground $ 9.50 SY $ - BMP C120
TESC Supervisor $ 84.00 HR $ -
Water truck, dust control $ 130.00 HR $ - BMP C140
WRITE-IN-ITEMS
$ - $ -
$ - $ -
$ - $ -
SUBTOTAL (TESC Only): $ 3,190.50
MOBILIZATION 10%: $ 319.05
CONTINGENCY 15%: $ 478.58
TOTAL: $ 3,988.13
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
STORMWATER DRAINAGE Public Private
Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
Access Road, Retention / Detention $ 26.00 SY $ - $ -
* (CBs include frame and lid)
Beehive $ 90.00 EACH $ - $ -
CB Type I $ 1,650.00 EACH $ - $ -
CB Type IL $ 1,850.00 EACH 4 $ 7,400.00 2 $ 3,700.00
CB Type II, 48" Dia $ 2,550.00 EACH $ - $ -
for additional depth over 4' $ 650.00 FT $ - $ -
CB Type II, 54" Dia $ 2,700.00 EACH $ - $ -
for additional depth over 4' $ 600.00 FT $ - $ -
CB Type II, 60" Dia $ 2,900.00 EACH $ - $ -
for additional depth over 4' $ 750.00 FT $ - $ -
CB Type II, 72" Dia $ 4,000.00 EACH $ - $ -
for additional depth over 4' $ 900.00 FT $ - $ -
Through-curb Inlet Framework (Add) $ 550.00 EACH $ - $ -
Cleanout, PVC, 4" $ 200.00 EACH $ - $ -
Cleanout, PVC, 6" $ 250.00 EACH 2 $ 500.00 $ -
Cleanout, PVC, 8" $ 300.00 EACH 1 $ 300.00 $ -
Culvert, Box __ ft x __ ft $ - LS $ - $ -
Culvert, PVC, 4" $ 12.00 LF $ - $ -
Culvert, PVC, 6" $ 17.00 LF $ - $ -
Culvert, PVC, 8" $ 19.00 LF $ - $ -
Culvert, PVC, 12" $ 30.00 LF $ - $ -
Culvert, CMP, 8" $ 23.00 LF $ - $ -
Culvert, CMP, 12" $ 35.00 LF $ - $ -
Culvert, CMP, 15" $ 42.00 LF $ - $ -
Culvert, CMP, 18" $ 47.00 LF $ - $ -
Culvert, CMP, 24" $ 69.00 LF $ - $ -
Culvert, CMP, 30" $ 100.00 LF $ - $ -
Culvert, CMP, 36" $ 150.00 LF $ - $ -
Culvert, CMP, 48" $ 194.00 LF $ - $ -
Culvert, CMP, 60" $ 310.00 LF $ - $ -
Culvert, CMP, 72" $ 400.00 LF $ - $ -
Culvert, Concrete, 8" $ 36.00 LF $ - $ -
Culvert, Concrete, 12" $ 43.00 LF $ - $ -
Culvert, Concrete, 15" $ 52.00 LF $ - $ -
Culvert, Concrete, 18" $ 55.00 LF $ - $ -
Culvert, Concrete, 24" $ 85.00 LF $ - $ -
Culvert, Concrete, 30" $ 136.00 LF $ - $ -
Culvert, Concrete, 36" $ 165.00 LF $ - $ -
Culvert, Concrete, 42" $ 196.00 LF $ - $ -
Culvert, Concrete, 48" $ 210.00 LF $ - $ -
Culvert, CPP, 6" $ 16.00 LF 200 $ 3,200.00 100 $ 1,600.00
Culvert, CPP, 8" $ 22.00 LF 66 $ 1,452.00 $ -
Culvert, CPP, 12" $ 28.00 LF $ - $ -
Culvert, CPP, 15" $ 34.00 LF $ - $ -
Culvert, CPP, 18" $ 39.00 LF $ - $ -
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
Culvert, CPP, 24" $ 49.00 LF $ - $ -
Culvert, CPP, 30" $ 62.00 LF $ - $ -
Culvert, CPP, 36" $ 69.00 LF $ - $ -
Ditching 12.00$ CY $ - $ -
Flow Dispersal Trench (1,436 base+) $ 40.00 LF $ - $ -
French Drain (3' depth) $ 39.00 LF $ - $ -
Geotextile, laid in trench, polypropylene $ 5.00 SY 471 $ 2,355.00 $ -
Infiltration pond testing $ 125.00 HR $ - $ -
Mid-tank Access Riser, 48" dia, 6' deep $ 2,025.00 EACH $ - $ -
Pipe, High Density Water Pipe (HDWP) $ 160.00 LF $ - $ -
Pipe, C900 $ 90.00 LF $ - $ -
Pond Overflow Spillway $ 18.00 SY $ - $ -
Restrictor/Oil Separator, 12" $ 1,500.00 EACH 4 $ 6,000.00 2 $ 3,000.00
Restrictor/Oil Separator, 15" $ 1,550.00 EACH $ - $ -
Restrictor/Oil Separator, 18" $ 1,680.00 EACH $ - $ -
Riprap, placed $ 52.00 CY $ - $ -
Tank End Reducer (36" Dia) $ 1,280.00 EACH $ - $ -
Thru-Inlet at CB $ 150.00 EACH $ - $ -
Trash Rack, 12" $ 320.00 EACH $ - $ -
Trash Rack, 15" $ 325.00 EACH $ - $ -
Trash Rack, 18" $ 350.00 EACH $ - $ -
Trash Rack, 21" $ 375.00 EACH $ - $ -
WRITE-IN-ITEMS
$ - $ -
$ - $ - $ -
$ - $ - $ -
SUBTOTAL: $ 21,207.00 $ 8,300.00
MOBILIZATION 10%: $ 2,120.70
CONTINGENCY 15%: $ 3,181.05
TOTAL: $ 26,508.75 $ 8,300.00
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
GENERAL ITEMS Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
Backfill & Compaction- embankment $ 8.00 CY $ - $ -
Backfill & Compaction- trench $ 11.00 CY $ - $ -
Clear/Remove Brush, by hand (acre) $ 2,363.00 ACRE $ - $ -
Bollards - fixed $ 325.00 EACH $ - $ -
Bollards - removable $ 600.00 EACH $ - $ -
Clearing/Grubbing/Tree Removal $ 6,000.00 ACRE $ - $ -
Excavation - bulk $ 2.50 CY 250 $ 625.00 500 $ 1,250.00
Excavation - Trench $ 5.00 CY $ - $ -
Fencing, cedar, 6' high $ 25.00 LF $ - $ -
Fencing, chain link, 4' $ 19.50 LF $ - $ -
Fencing, chain link, vinyl coated, 6' high $ 18.00 LF $ - $ -
Fencing, chain link, gate, vinyl coated, 2 $ 1,563.00 EACH $ - $ -
Fencing, split rail, 3' high $ 14.00 LF $ - $ -
Fill & compact - common barrow $ 27.00 CY $ - $ -
Fill & compact - gravel base $ 30.00 CY $ - $ -
Fill & compact - screened topsoil $ 45.00 CY $ - $ -
Gabion, 12" deep, stone filled mesh $ 62.00 SY $ - $ -
Gabion, 18" deep, stone filled mesh $ 86.00 SY $ - $ -
Gabion, 36" deep, stone filled mesh $ 152.00 SY $ - $ -
Grading, fine, by hand $ 2.00 SY $ - $ -
Grading, fine, with grader $ 1.25 SY $ - $ -
Guard Post $ 90.00 EACH $ - $ -
Monuments $ 104.00 EACH $ - $ -
Sensitive Areas Sign $ 20.00 EACH $ - $ -
Sodding, 1" deep, sloped ground $ 10.00 SY $ - $ -
Topsoil Type A (imported) $ 30.00 CY $ - $ -
Traffic control crew ( 2 flaggers ) $ 98.00 HR $ - $ -
Trail, 4" chipped wood $ 9.00 SY $ - $ -
Trail, 4" crushed cinder $ 10.00 SY $ - $ -
Trail, 4" top course $ 9.50 SY $ - $ -
Wall, retaining, concrete $ 66.00 SF $ - $ -
Wall, rockery $ 13.00 SF $ - $ -
WRITE-IN-ITEMS
Fill - Suitable onsite material $ 5.00 CY 50 $ 250.00 550 $ 2,750.00
$ - $ - $ -
$ - $ - $ -
Subtotal $ 875.00 Subtotal $ 4,000.00
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
STREET IMPROVEMENT Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
AC Grinding, 4' wide machine < 1000sy $ 35.00 SY $ - $ -
AC Grinding, 4' wide machine 1000-2000$ 8.50 SY $ - $ -
AC Grinding, 4' wide machine > 2000sy $ 2.50 SY $ - $ -
AC Removal/Disposal/Repair $ 60.00 SY 536 $ 32,160.00 251 $ 15,060.00
Barricade, Type I $ 36.00 LF $ - $ -
Barricade Type II $ 25.00 LF $ - $ -
Barricade, Type III ( Permanent ) $ 55.00 LF $ - $ -
Conduit, 2" $ 5.00 LF $ - $ -
Curb & Gutter, rolled $ 20.00 LF $ - $ -
Curb & Gutter, vertical $ 15.00 LF 283 $ 4,245.00 $ -
Curb and Gutter, demolition and disposa $ 20.00 LF $ - $ -
Curb, extruded asphalt $ 5.00 LF $ - $ -
Curb, extruded concrete $ 4.50 LF 235 $ 1,057.50 68 $ 306.00
Guard Rail $ 30.00 LF $ - $ -
Sawcut, asphalt, 3" depth $ 3.50 LF 85 $ 297.50 28 $ 98.00
Sawcut, concrete, per 1" depth $ 3.00 LF 60 $ 180.00 $ -
Sealant, asphalt $ 2.00 LF $ - $ -
Shoulder, gravel, 4" thick $ 11.00 SY $ - $ -
Sidewalk, 4" thick $ 40.00 SY 193 $ 7,720.00 67 $ 2,680.00
Sidewalk, 4" thick, demolition and dispos $ 36.00 SY 21 $ 756.00 $ -
Sidewalk, 6" thick $ 45.00 SY $ - $ -
Sidewalk, 6" thick, demolition and dispos $ 45.00 SY $ - $ -
Signs $ - LS $ - $ -
Sign, Handicap $ 100.00 EACH $ - 2 $ 200.00
Striping, per stall $ 7.50 EACH 34 $ 255.00 31 $ 232.50
Street Light System $ - LS $ - $ -
Traffic Signal $ - LS $ - $ -
Traffic Signal Modification $ - LS $ - $ -
Striping, thermoplastic, ( for crosswalk ) $ 3.50 SF $ - $ -
Striping, 4" reflectorized line $ 0.40 LF $ - $ -
AC Patching/Trenching Restoration $ 100.00 TON $ - $ -
Controlled Density Fill (CDF) $ 90.00 CY $ - $ -
WRITE-IN-ITEMS
Extruded Curb demolition and disposal $ 10.00 LF 250 $ 2,500.00 $ -
$ - $ - $ -
$ - $ - $ -
Subtotal $ 49,171.00 Subtotal $ 18,576.50
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
STREET SURFACING/PAVEMENT Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
Asphalt Overlay, 1.5" AC $ 12.00 SY $ - $ -
Asphalt Overlay, 2" AC $ 15.00 SY $ - $ -
Asphalt Road 2", First 2500 SY $ 10.00 SY $ - $ -
Asphalt Road 2", Qty. over 2500SY $ 9.00 SY $ - $ -
Asphalt Road 3", First 2500 SY $ 15.00 SY $ - $ -
Asphalt Road 3", Qty. over 2500 SY $ 13.00 SY $ - $ -
Asphalt Road 5", First 2500 SY $ 22.00 SY $ - $ -
Asphalt Road 5", Qty. Over 2500 SY $ 22.00 SY $ - $ -
Asphalt Road 6", First 2500 SY $ 25.00 SY $ - $ -
Asphalt Road 6", Qty. Over 2500 SY $ 24.00 SY $ - $ -
Asphalt Treated Base, 4" thick $ 14.00 SY $ - $ -
Gravel Base Course 2" $ 7.50 SY $ - $ -
Gravel Base Course 4" $ 15.00 SY $ - $ -
Gravel Base Course 6" $ 22.50 SY 1048 $ 23,580.00 1069 $ 24,052.50
Gravel Road, 4" rock, First 2500 SY $ 15.00 SY $ - $ -
Gravel Road, 4" rock, Qty. over 2500 SY $ 11.00 SY $ - $ -
Concrete Road, 5", no base, over 2500 S$ 22.00 SY $ - $ -
Concrete Road, 6", no base, over 2500 $ 32.00 SY $ - $ -
Thickened Edge $ 11.00 LF $ - 135 $ 1,485.00
WRITE-IN-ITEMS
Asphalt Road 4" $ 18.00 SY 365 $ 6,570.00 433 $ 7,794.00
Asphalt Road 2.5" $ 12.00 SY 683 $ 8,196.00 636 $ 7,632.00
$ - $ - $ -
Subtotal $ 38,346.00 Subtotal $ 40,963.50
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
WATER SYSTEM Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
Blowoff $ 1,800.00 EACH $ - $ -
Connection to Existing Water Main $ 2,000.00 EACH $ - 2 $ 4,000.00
Ductile Iron Watermain, CL 52, 6 Inch Dia $ 65.00 LF $ - 121 $ 7,865.00
Ductile Iron Watermain, CL 52, 8 Inch Dia $ 85.00 LF $ - $ -
Ductile Iron Watermain, CL 52, 10 Inch Dia $ 103.00 LF $ - $ -
Ductile Iron Watermain, CL 52, 12 Inch Dia. $ 125.00 LF $ - $ -
Gate Valve, 6 inch Dia $ 250.00 EACH $ - $ -
Gate Valve, 8 Inch Dia $ 380.00 EACH $ - $ -
Gate Valve, 10 Inch Dia $ 425.00 EACH $ - $ -
Gate Valve, 12 Inch Dia $ 500.00 EACH $ - $ -
Fire Hydrant Assembly, with Guard Posts $ 3,000.00 EACH $ - $ -
Fire Hydrant Assembly, without Guard Posts $ 2,500.00 EACH 1 $ 2,500.00 $ -
Air-Vac, 8 Inch Dia $ 6,000.00 EACH $ - $ -
Air-Vac,10 Inch Dia $ 7,500.00 EACH $ - $ -
Air-Vac, 12 Inch Dia $ 12,000.00 EACH $ - $ -
Pressure Reducing Valve Assembly, 8 In. Dia $ 3,800.00 EACH $ - $ -
Pressure Reducing Valve Assembly, 10 In. D $ 4,200.00 EACH $ - $ -
Pressure Reducing Valve Assembly, 12 In. D $ 5,000.00 EACH $ - $ -
Valve Marker Post $ 350.00 EACH $ - $ -
WRITE-IN-ITEMS
$ - $ -
$ - $ - $ -
$ - $ - $ -
Subtotal $ 2,500.00 Subtotal $ 11,865.00
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
SANITARY SEWER Public Improvements Private Development
Description Unit Price Unit Quantity Cost Quantity Cost
Connection to Existing Sewer Main $ - EACH $ - 2 $ -
Clean Outs $ 500.00 EACH $ - 3 $ 1,500.00
Grease Interceptor, 500 gallon $ 6,000.00 EACH $ - $ -
Grease Interceptor, 1000 gallon $ 10,000.00 EACH $ - $ -
Grease Interceptor, 1500 gallon $ 15,000.00 EACH $ - $ -
Side Sewer Pipe, PVC. 4 Inch Dia $ 8.00 LF $ - $ -
Side Sewer Pipe, PVC. 6 Inch Dia $ 12.00 LF $ - 205 $ 2,460.00
Sewer Pipe, PVC, 8 inch Dia $ 33.00 LF 62 $ 2,046.00 $ -
Sewer Pipe, PVC, 12 Inch Dia $ 41.00 LF $ - $ -
Sewer Pipe, PVC, ____ Inch Dia $ - LF $ - $ -
Lift Station (Entire System) $ - LS $ - $ -
Manhole, 48 Inch Dia $ 3,000.00 EACH 3 $ 9,000.00 $ -
for additional depth over 4 feet/per fo $ 532.00 FEET 14 $ 7,448.00 $ -
Manhole, 54 Inch Dia $ 3,500.00 EACH $ - $ -
for additional depth over 4 feet/per fo $ 532.00 FEET $ - $ -
Manhole, 60 Inch Dia $ 3,700.00 EACH $ - $ -
for additional depth over 4 feet/per fo $ 532.00 FEET $ - $ -
Manhole, 72 Inch Dia $ 4,000.00 EACH $ - $ -
for additional depth over 4 feet/per fo $ 625.00 FEET $ - $ -
Manhole, 96 Inch Dia $ 5,000.00 EACH $ - $ -
for additional depth over 4 feet/per foo $ 625.00 FEET $ - $ -
Outside Drop $ - LS $ - $ -
Inside Drop $ - LS $ - $ -
Pipe, C-900 $ 90.00 LF $ - $ -
Pipe, High Density Water Pipe (HDWP) $ 160.00 LF $ - $ -
WRITE-IN-ITEMS
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
Subtotal $ 18,494.00 Subtotal $ 3,960.00
Rev 7/2017
CONSTRUCTION CALCULATION WORKSHEET
LANDSCAPING & VEGETATION Include Public Improvements & Private Development
Description Unit Price Unit Quantity Cost
Street Trees $ 500.00 EACH 4 $ 2,000.00
Root Barrier $ 50.00 EACH 4 $ 200.00
Median Landscaping $ - LS $ -
Right-of-Way Landscaping $ - LS $ -
Wetland Landscaping $ - LS $ -
Private Landscaping $ - LS $ -
WRITE-IN-ITEMS
Trees $ 250.00 EACH 8 $ 2,000.00
$ - $ -
$ - $ -
Subtotal $ 4,200.00 $ - $ -
(INCLUDES GENERAL, STREET, SURFACING, WATER, PUBLIC PRIVATE
SEWER, LANDSCAPING) SUBTOTAL $ 113,586.00 $ 79,365.00
MOBILIZATION 10%: $ 11,358.60 $ 7,936.50
CONTINGENCY 15%: $ 17,037.90 $ 11,904.75
GRANDTOTAL: $ 141,982.50 $ 99,206.25
Rev 7/2017
Paisley Lofts
Project #22923
Table of Contents
Executive Summary .................................................................................................................................. 3
Decision Tree ............................................................................................................................................ 4
Drainage Information Summary Form ..................................................................................................... 5
Vicinity Map ............................................................................................................................................. 6
MR #1 Stormwater Site Plan Narrative .................................................................................................... 7
PROJECT DESCRIPTION ................................................................................................................... 7
METHODOLOGY ................................................................................................................................ 7
EXISTING CONDITIONS ................................................................................................................... 7
DEVELOPED CONDITIONS .............................................................................................................. 8
UPSTREAM ANALYSIS ..................................................................................................................... 8
DOWNSTREAM ANALYSIS .............................................................................................................. 8
FLOW CONTROL ................................................................................................................................ 9
RUNOFF TREATMENT ...................................................................................................................... 9
MR #2 Stormwater Pollution Prevention Plan Narrative ........................................................................ 9
MR #3 Water Pollution Source Control ................................................................................................... 9
MR #4 Preservation of Natural Drainage Patterns ................................................................................... 9
MR #5 On-Site Stormwater Management ................................................................................................ 9
MR #6 Runoff Treatment ....................................................................................................................... 10
MR #7 Flow Control ............................................................................................................................... 10
MR #8 Wetland Protection ..................................................................................................................... 10
MR #9 Operations & Maintenance ......................................................................................................... 10
Appendix ................................................................................................................................................. 11
Cascade Surveying & Engineering Inc. 2
Paisley Lofts
Project #22923
Executive Summary
The 0.39-acre site will have a new four-story building constructed along with paved parking areas. The
site currently has a building and the remaining property is gravel. Frontage improvements are required
on E. Division St. consisting of angled parking, curb, gutter and sidewalk. As part of the proposed
project’s construction, the alleys on both sides of Centennial Trail, west of the site, will be improved to
include additional parking spaces. The project will implement a design to meet the minimum
requirements as outlined below:
Compliance with Minimum Requirements:
Prepare Stormwater
1 A stormwater site plan report is presented in this document.
Site Plan
2 SWPPP A SWPPP is submitted separate to this report.
Water Pollution
3 BMPs for source control will be noted in the SWPPP.
Source Control
Preserve Natural All stormwater runoff from the proposed development will be fully
4
Drainage infiltrated given the existing well-drained soils on-site.
On-site Stormwater All stormwater runoff from the proposed development will be
5
Management collected and fully infiltrated.
Runoff treatment for the proposed parking lot areas will be provided
6 Runoff Treatment
through water quality infiltration trenches.
Flow control for the proposed development will be met using
7 Flow Control
infiltration trenches to fully infiltrate all runoff.
Stormwater
There are no known wetlands existing within the area of disturbance
8 Discharge to
or on-site.
Wetland
Inspection,
Stormwater facilities will be regularly inspected and maintained. The
9 Operation and
Operation & Maintenance Manual can be found in the Appendix.
Maintenance
Cascade Surveying & Engineering Inc. 3
Paisley Lofts
Project #22923
Decision Tree
Copy
`
Figure 1 - Decision Tree (DOE Stormwater Management Manual for Western Wash. 2019)
Cascade Surveying & Engineering Inc. 4
Paisley Lofts
Project #22923
Drainage Information Summary Form
Project Total Area: 0.77 ± acres
Area of Disturbance: 0.77 ± acres
Number of Lots (if applies): N/A
Table 1 - Drainage Information Summary
Individual Basin Information
Drainage Basin Information
Site Drainage Basin
On & Off-Site Sub-Basin Area (acres) 0.70
Type of Storage Proposed N/A
Approx. Dead Storage Vol (cf) N/A
Approx. Live Storage Vol (cf) N/A
Soil Type(s) (Natural Resource Conservation Service) Everett very gravelly sandy loam
Pre-developed Discharge Rates
Q (cfs.) 2 yr. 0.001
10 yr. 0.002
50 yr./ 100 yr. 0.009/0.014
Redevelopment Area (acres)
Post-development Runoff Rates (w/o quantity controls)
Q (cfs.) 2 yr. 0.362
10 yr. 0.580
50 yr./ 100 yr. 0.808/0.916
Post-development Runoff Rates (with quantity controls)
Q (cfs.) 2 yr. 0
10 yr. 0
50 yr. 0
Offsite Upstream Area
Number of acres 0
Offsite Downstream Flow
Q(cfs) 50 yr. 0
Cascade Surveying & Engineering Inc. 5
Paisley Lofts
Project #22923
Vicinity Map
PROPERTY DESCRIPTION
The project site is located in a portion of Section 2, Township 31 North, Range 05 East W.M.
More specifically the site lies at 540 N. Olympic Avenue, Arlington, WA 98223. The property
is identified by tax parcels #00529900900101 and #00529900900300 and is shown below in
Figure 1, highlighted in red.
Source PDS Map Portal
Figure 2: Vicinity Map. Not to scale.
Cascade Surveying & Engineering Inc. 6
Paisley Lofts
Project #22923
MR #1 Stormwater Site Plan Narrative
PROJECT DESCRIPTION
The proposal is to remove the existing building on site, construct a four-story multi-use
building, and pave the parking lot. The main floor of the proposed building will be for
commercial use while the remaining floors will contain 2 one-bedroom units and 44 studio
units. A 2,500 sf courtyard is located on the third floor. Offsite improvements will include
diagonal parking, curb, gutter, and sidewalk along E. Division St. frontage, and improvements
to the alleys on both sides of Centennial Trail to create additional parking.
METHODOLOGY
Drainage calculations for the on-site area have been prepared using the 2019 Department of
Ecology Stormwater Management Manual for Western Washington (DOE SMMWW). The
site drainage design meets Low Impact Development (LID) standards by fully infiltrating all
stormwater runoff on-site. The infiltration trenches were sized using the 2012 Western
Washington Hydrology Model (WWHM). Given the total proposed new+replaced impervious
surface for the project is over 5,000 sf, the development will be required to meet minimum
requirements (MRs) 1-9 according to Volume I of the DOE SMMWW.
EXISTING CONDITIONS
The 0.39-acre site is located in the Old Town Business District 2 zone of the City of Arlington.
The site has an existing 1,520 sf building with asphalt for parking along the south and west of
the building. The remaining site is gravel that is used as a parking lot. With the existing
conditions of the site being more than 35% impervious, the project is characterized a
redevelopment.
A subsurface exploration was carried out by GeoTest on October 22, 2021 (see separate report).
There were six exploration test pits, the majority of which were advanced to a depth between
10 and 12 ft below ground surface. The test pit located in the area west of Centennial Trail was
advanced to a depth of 5 ft. Four test pits were located in the vicinity of the proposed building
and a test pit was located in the alley on either side of Centennial Trail. Historic fill was
encountered in TP-1,TP-2, and TP-4 between 2 and 8 ft deep over native Arlington gravel
member. TP-3, TP-5, and TP-6 encountered topsoil or surficial fill soils associated with the
parking lot for depths of 1 to 1.5 ft over native Arlington gravel member. Geotest provided an
infiltration rate of 8 in/hr for this Arlington gravel member. Refer to separate report for more
detail.
According to the NRCS (see Appendix A), the entire site is comprised of Everett very gravelly
sandy loam. This soil is described as being very deep, somewhat excessively drained soil found
on terraces and outwash plains. Permeability of the soil is rapid and available water capacity is
low. The top 6 inches is typically a dark brown gravelly sandy loam. The subsoil is about 12
inches thick and is dark brown very gravelly sandy loam. Below these layers the substratum is
brown very gravelly loam for about 5 inches and then dark brown extremely gravely sand to a
depth of 60 inches or more. It is categorized as hydrologic soils group A.
Cascade Surveying & Engineering Inc. 7
Paisley Lofts
Project #22923
DEVELOPED CONDITIONS
The proposed redevelopment will remove the existing structure on-site as well as the existing
asphalt and gravel areas and replace them with a four-story building, new asphalt parking lot
areas, concrete walkways, and landscaped areas. The offsite improvements include diagonal
back-in parking, curb, gutter, and sidewalk along E. Division St. frontage, and improvements to
the alleys on both sides of Centennial Trail to create additional parking. The existing driveway
entrance on N. Olympic Avenue will be expanded north 10 feet to align with the proposed
drive aisle. The proposed areas are outlined in Table 2 and Table 3 below.
Table 2: Onsite Areas
Proposed Areas
Area Description Area (square feet)
Building 9,760
Asphalt Parking/Drive 6,701
Dumpster Pad 160
Landscape areas 328
Total 16,949
Table 3: Offsite Areas
Proposed Areas
Area Description Area (square feet)
E. Division St Frontage:
Asphalt Parking/Drive 3,930
Concrete sidewalk 1,823
Landscape areas 1,076
Alley East of Centennial:
Asphalt 4,700
Alley West of Centennial:
Asphalt 1,760
Total 13,289
Given total proposed new+replaced impervious surface for the project is over 5,000 sf, the
development will be required to meet MRs 1-9 according to Volume I of the DOE SMMWW.
UPSTREAM ANALYSIS
Due to the developed surrounding properties, there is no upstream area that contributes flow to
the subject site.
DOWNSTREAM ANALYSIS
Currently the runoff from the site’s existing conditions flow towards the northwest of the
property. Runoff from the existing gravel parking lot flows onto E. Division St. at the
entrance east of the existing building where it enters the existing catch basin located on E.
Division St west of the property. The proposed development is not anticipated to have any
downstream impact as all the site’s stormwater runoff will be collected and fully infiltrated
Cascade Surveying & Engineering Inc. 8
Paisley Lofts
Project #22923
on-site. Fully infiltrating all runoff is anticipated to meet or lower the site’s runoff from its
predeveloped, native forested condition.
FLOW CONTROL
Flow control will be provided by fully infiltrating all runoff on-site through the use of
infiltration trenches. The infiltration trenches were sized for 100% infiltration of 8% of the
2-year peak flow through the full 50-year peak flow using the 2012 Western Washington
Hydrology Model (WWHM). Specifics about the proposed flow control trenches are further
discussed in MR 7.
RUNOFF TREATMENT
The infiltration trenches have 1.5’ of soil amended to have a cation exchange capacity
(CEC) of 5 milliequivalents CEC/100g of dry soil or better. This will provide runoff
treatment for the pollution generating hard surfaces. The trench was sized for 100%
infiltration so all stormwater runoff will pass through the amended soils. Specifics about the
proposed water quality trench are further discussed in MR 6.
MR #2 Stormwater Pollution Prevention Plan Narrative
See Separate Report.
MR #3 Water Pollution Source Control
No known pollution generating activities described in volume IV, chapters 3 and 4 of the Snohomish
County Drainage Manual will be performed on-site during construction or are proposed for the
developed site following construction. Any sources of pollution that may result from the construction
activity will be controlled according to SWPPP Element #9, Control Pollutants.
MR #4 Preservation of Natural Drainage Patterns
The natural drainage patterns identified in the drainage report under MR #1 and on the stormwater site
plan will be maintained during construction and post development. The natural drainage sheetflows
offsite to the northwest of the property and enters the existing catch basin on E. Division St. west of
the property. The site is designed to fully infiltrate runoff and will reduce the previously unmitigated
discharge downstream.
MR #5 On-Site Stormwater Management
The proposed development will meet Low Impact Development (LID) and flow control requirements
per Sections I-2.5.5 and I-2.5.7 of the 2019 Stormwater Management Manual for Western Washington
(SMMWW). The post-developed conditions will have flow rates meeting 8% of the 2-year peak flow
through the full 50-year peak flow.
Cascade Surveying & Engineering Inc. 9
Paisley Lofts
Project #22923
Three infiltration trenches will be located within the project site:
1. Trench A is located beneath the parking in the alley to mitigate runoff from onsite impervious
areas and the alley east of Centennial Trail.
2. Trench B is located in the E. Division St. frontage to mitigate runoff from E. Division St.
frontage improvements.
3. Trench C is located under the proposed parking in the alley west of Centennial Trail to
mitigate for the proposed parking west of Centennial Trail.
The infiltration rate of 8 in/hr used in the calculations was measured by Geotest. All proposed
impervious surfaces will be conveyed to one of the above trenches. The size of each trench can be seen
in WWHM (Appendix B) and the construction plans.
BMP T5.13 Post Construction Soil Quality and Depth:
Post Construction Soil Quality and Depth will be used on site to recondition those areas that were
impacted due to construction activities. Those areas to be reconditioned have been identified on the
construction plans as landscape areas. The existing on-site topsoil will be tilled, and compost added to
the soil prior to final seeding. The intent of this BMP is to restore the pre-developed drainage
characteristics of the soil.
MR #6 Runoff Treatment
Runoff treatment for the proposed parking lot and driveway areas will be provided through water
quality infiltration trenches. These trenches will have 1.5’ of soil amended to have a cation exchange
capacity (CEC) of 5 milliequivalents CEC/100g of dry soil or better.
The water quality trenches are sized by achieving 100% infiltration using WWHM. Details on the
proposed trench are outlined in the WWHM report provided in Appendix B and the construction plans.
MR #7 Flow Control
Flow control will be provided for the impervious areas onsite through the use of infiltration trenches.
These infiltration trenches are designed using WWHM to detain all runoff from 8% of the 2-year storm
through the full 50-year storm until it fully infiltrates.
Details on the proposed trenches are outlined in the WWHM report provided in Appendix B.
MR #8 Wetland Protection
There are no wetlands on site or within the area of disturbance.
MR #9 Operations & Maintenance
An operation and maintenance manual has been included in Appendix C.
Cascade Surveying & Engineering Inc. 10
Paisley Lofts
Project #22923
Appendix
Appendix A - NRCS SOILS REPORT
Appendix B - WWHM REPORT
Appendix C - OPERATIONS AND MAINTENANCE MANUAL
Cascade Surveying & Engineering Inc. 11
APPENDIX A – NRCS SOILS REPORT
United States A product of the National Custom Soil Resource
Department of Cooperative Soil Survey,
Agriculture a joint effort of the United Report for
States Department of
Agriculture and other Snohomish County
Federal agencies, State
Natural agencies including the
Resources Agricultural Experiment Area, Washington
Conservation Stations, and local
Service participants
October 22, 2021
Preface
Soil surveys contain information that affects land use planning in survey areas.
They highlight soil limitations that affect various land uses and provide information
about the properties of the soils in the survey areas. Soil surveys are designed for
many different users, including farmers, ranchers, foresters, agronomists, urban
planners, community officials, engineers, developers, builders, and home buyers.
Also, conservationists, teachers, students, and specialists in recreation, waste
disposal, and pollution control can use the surveys to help them understand,
protect, or enhance the environment.
Various land use regulations of Federal, State, and local governments may impose
special restrictions on land use or land treatment. Soil surveys identify soil
properties that are used in making various land use or land treatment decisions.
The information is intended to help the land users identify and reduce the effects of
soil limitations on various land uses. The landowner or user is responsible for
identifying and complying with existing laws and regulations.
Although soil survey information can be used for general farm, local, and wider area
planning, onsite investigation is needed to supplement this information in some
cases. Examples include soil quality assessments (http://www.nrcs.usda.gov/wps/
portal/nrcs/main/soils/health/) and certain conservation and engineering
applications. For more detailed information, contact your local USDA Service Center
(https://offices.sc.egov.usda.gov/locator/app?agency=nrcs) or your NRCS State Soil
Scientist (http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?
cid=nrcs142p2_053951).
Great differences in soil properties can occur within short distances. Some soils are
seasonally wet or subject to flooding. Some are too unstable to be used as a
foundation for buildings or roads. Clayey or wet soils are poorly suited to use as
septic tank absorption fields. A high water table makes a soil poorly suited to
basements or underground installations.
The National Cooperative Soil Survey is a joint effort of the United States
Department of Agriculture and other Federal agencies, State agencies including the
Agricultural Experiment Stations, and local agencies. The Natural Resources
Conservation Service (NRCS) has leadership for the Federal part of the National
Cooperative Soil Survey.
Information about soils is updated periodically. Updated information is available
through the NRCS Web Soil Survey, the site for official soil survey information.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its
programs and activities on the basis of race, color, national origin, age, disability,
and where applicable, sex, marital status, familial status, parental status, religion,
sexual orientation, genetic information, political beliefs, reprisal, or because all or a
part of an individual's income is derived from any public assistance program. (Not
all prohibited bases apply to all programs.) Persons with disabilities who require
2
alternative means for communication of program information (Braille, large print,
audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice
and TDD). To file a complaint of discrimination, write to USDA, Director, Office of
Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C. 20250-9410 or
call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity
provider and employer.
3
Contents
Preface....................................................................................................................2
How Soil Surveys Are Made..................................................................................5
Soil Map..................................................................................................................8
Soil Map................................................................................................................9
Legend................................................................................................................10
Map Unit Legend................................................................................................ 11
Map Unit Descriptions.........................................................................................11
Snohomish County Area, Washington............................................................13
17—Everett very gravelly sandy loam, 0 to 8 percent slopes.....................13
References............................................................................................................15
4
How Soil Surveys Are Made
Soil surveys are made to provide information about the soils and miscellaneous
areas in a specific area. They include a description of the soils and miscellaneous
areas and their location on the landscape and tables that show soil properties and
limitations affecting various uses. Soil scientists observed the steepness, length,
and shape of the slopes; the general pattern of drainage; the kinds of crops and
native plants; and the kinds of bedrock. They observed and described many soil
profiles. A soil profile is the sequence of natural layers, or horizons, in a soil. The
profile extends from the surface down into the unconsolidated material in which the
soil formed or from the surface down to bedrock. The unconsolidated material is
devoid of roots and other living organisms and has not been changed by other
biological activity.
Currently, soils are mapped according to the boundaries of major land resource
areas (MLRAs). MLRAs are geographically associated land resource units that
share common characteristics related to physiography, geology, climate, water
resources, soils, biological resources, and land uses (USDA, 2006). Soil survey
areas typically consist of parts of one or more MLRA.
The soils and miscellaneous areas in a survey area occur in an orderly pattern that
is related to the geology, landforms, relief, climate, and natural vegetation of the
area. Each kind of soil and miscellaneous area is associated with a particular kind
of landform or with a segment of the landform. By observing the soils and
miscellaneous areas in the survey area and relating their position to specific
segments of the landform, a soil scientist develops a concept, or model, of how they
were formed. Thus, during mapping, this model enables the soil scientist to predict
with a considerable degree of accuracy the kind of soil or miscellaneous area at a
specific location on the landscape.
Commonly, individual soils on the landscape merge into one another as their
characteristics gradually change. To construct an accurate soil map, however, soil
scientists must determine the boundaries between the soils. They can observe only
a limited number of soil profiles. Nevertheless, these observations, supplemented
by an understanding of the soil-vegetation-landscape relationship, are sufficient to
verify predictions of the kinds of soil in an area and to determine the boundaries.
Soil scientists recorded the characteristics of the soil profiles that they studied. They
noted soil color, texture, size and shape of soil aggregates, kind and amount of rock
fragments, distribution of plant roots, reaction, and other features that enable them
to identify soils. After describing the soils in the survey area and determining their
properties, the soil scientists assigned the soils to taxonomic classes (units).
Taxonomic classes are concepts. Each taxonomic class has a set of soil
characteristics with precisely defined limits. The classes are used as a basis for
comparison to classify soils systematically. Soil taxonomy, the system of taxonomic
classification used in the United States, is based mainly on the kind and character
of soil properties and the arrangement of horizons within the profile. After the soil
5
Custom Soil Resource Report
scientists classified and named the soils in the survey area, they compared the
individual soils with similar soils in the same taxonomic class in other areas so that
they could confirm data and assemble additional data based on experience and
research.
The objective of soil mapping is not to delineate pure map unit components; the
objective is to separate the landscape into landforms or landform segments that
have similar use and management requirements. Each map unit is defined by a
unique combination of soil components and/or miscellaneous areas in predictable
proportions. Some components may be highly contrasting to the other components
of the map unit. The presence of minor components in a map unit in no way
diminishes the usefulness or accuracy of the data. The delineation of such
landforms and landform segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, onsite
investigation is needed to define and locate the soils and miscellaneous areas.
Soil scientists make many field observations in the process of producing a soil map.
The frequency of observation is dependent upon several factors, including scale of
mapping, intensity of mapping, design of map units, complexity of the landscape,
and experience of the soil scientist. Observations are made to test and refine the
soil-landscape model and predictions and to verify the classification of the soils at
specific locations. Once the soil-landscape model is refined, a significantly smaller
number of measurements of individual soil properties are made and recorded.
These measurements may include field measurements, such as those for color,
depth to bedrock, and texture, and laboratory measurements, such as those for
content of sand, silt, clay, salt, and other components. Properties of each soil
typically vary from one point to another across the landscape.
Observations for map unit components are aggregated to develop ranges of
characteristics for the components. The aggregated values are presented. Direct
measurements do not exist for every property presented for every map unit
component. Values for some properties are estimated from combinations of other
properties.
While a soil survey is in progress, samples of some of the soils in the area generally
are collected for laboratory analyses and for engineering tests. Soil scientists
interpret the data from these analyses and tests as well as the field-observed
characteristics and the soil properties to determine the expected behavior of the
soils under different uses. Interpretations for all of the soils are field tested through
observation of the soils in different uses and under different levels of management.
Some interpretations are modified to fit local conditions, and some new
interpretations are developed to meet local needs. Data are assembled from other
sources, such as research information, production records, and field experience of
specialists. For example, data on crop yields under defined levels of management
are assembled from farm records and from field or plot experiments on the same
kinds of soil.
Predictions about soil behavior are based not only on soil properties but also on
such variables as climate and biological activity. Soil conditions are predictable over
long periods of time, but they are not predictable from year to year. For example,
soil scientists can predict with a fairly high degree of accuracy that a given soil will
have a high water table within certain depths in most years, but they cannot predict
that a high water table will always be at a specific level in the soil on a specific date.
After soil scientists located and identified the significant natural bodies of soil in the
survey area, they drew the boundaries of these bodies on aerial photographs and
6
Custom Soil Resource Report
identified each as a specific map unit. Aerial photographs show trees, buildings,
fields, roads, and rivers, all of which help in locating boundaries accurately.
7
Soil Map
The soil map section includes the soil map for the defined area of interest, a list of
soil map units on the map and extent of each map unit, and cartographic symbols
displayed on the map. Also presented are various metadata about data used to
produce the map, and a description of each soil map unit.
8
Custom Soil Resource Report
Soil Map
122° 7' 37'' W
122° 7' 34'' W
564859 564865 564871 564877 564883 564889 564895 564901
564907 564913 564919
48° 11' 54'' N
48° 11' 54'' N
5338731
5338731
5338725
5338725
5338719
5338719
5338713
5338713
5338707
5338707
5338701
5338701
5338695 Soil Map may not be valid at this scale.
5338695
48° 11' 53'' N
48° 11' 53'' N
564859 564865 564871 564877 564883 564889 564895 564901
564907 564913 564919
Map Scale: 1:285 if printed on A landscape (11" x 8.5") sheet.
Meters
122° 7' 37'' WN 0 4 8 16 24
122° 7' 34'' W
Feet
0 10 20 40 60
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS84
9
Custom Soil Resource Report
MAP LEGEND MAP INFORMATION
Area of Interest (AOI) Spoil Area The soil surveys that comprise your AOI were mapped
at
Area of Interest (AOI) 1:24,000.
Stony Spot
Soils
Very Stony Spot
Warning: Soil Map may not be valid at this scale.
Soil Map Unit Polygons
Wet Spot
Soil Map Unit Lines Enlargement of maps beyond the scale of mapping
can cause
Other
Soil Map Unit Points misunderstanding of the detail of mapping and
accuracy of soil
Special Line Features line placement. The maps do not show the small
areas of
Special Point Features contrasting soils that could have been shown at
a more detailed
Blowout Water Features scale.
Streams and Canals
Borrow Pit
Transportation Please rely on the bar scale on each map sheet
for map
Clay Spot
Rails measurements.
Closed Depression
Interstate Highways
Source of Map: Natural Resources Conservation
Service
Gravel Pit
US Routes Web Soil Survey URL:
Gravelly Spot Coordinate System: Web Mercator (EPSG:3857)
Major Roads
Landfill
Local Roads Maps from the Web Soil Survey are based on the
Web Mercator
Lava Flow projection, which preserves direction and shape
but distorts
Background
distance and area. A projection that preserves
area, such as the
Marsh or swamp Aerial Photography Albers equal-area conic projection, should be
used if more
accurate calculations of distance or area are
required.
Mine or Quarry
Miscellaneous Water This product is generated from the USDA-NRCS certified
data as
Perennial Water of the version date(s) listed below.
Rock Outcrop Soil Survey Area: Snohomish County Area, Washington
Saline Spot Survey Area Data: Version 23, Aug 31, 2021
Sandy Spot
Soil map units are labeled (as space allows) for
map scales
Severely Eroded Spot 1:50,000 or larger.
Sinkhole
Date(s) aerial images were photographed: Sep
26, 2018—Oct
Slide or Slip 16, 2018
Sodic Spot
The orthophoto or other base map on which the
soil lines were
compiled and digitized probably differs from the
background
imagery displayed on these maps. As a result,
some minor
shifting of map unit boundaries may be evident.
10
Custom Soil Resource Report
Map Unit Legend
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
17 Everett very gravelly sandy 0.4 100.0%
loam, 0 to 8 percent slopes
Totals for Area of Interest 0.4 100.0%
Map Unit Descriptions
The map units delineated on the detailed soil maps in a soil survey represent the
soils or miscellaneous areas in the survey area. The map unit descriptions, along
with the maps, can be used to determine the composition and properties of a unit.
A map unit delineation on a soil map represents an area dominated by one or more
major kinds of soil or miscellaneous areas. A map unit is identified and named
according to the taxonomic classification of the dominant soils. Within a taxonomic
class there are precisely defined limits for the properties of the soils. On the
landscape, however, the soils are natural phenomena, and they have the
characteristic variability of all natural phenomena. Thus, the range of some
observed properties may extend beyond the limits defined for a taxonomic class.
Areas of soils of a single taxonomic class rarely, if ever, can be mapped without
including areas of other taxonomic classes. Consequently, every map unit is made
up of the soils or miscellaneous areas for which it is named and some minor
components that belong to taxonomic classes other than those of the major soils.
Most minor soils have properties similar to those of the dominant soil or soils in the
map unit, and thus they do not affect use and management. These are called
noncontrasting, or similar, components. They may or may not be mentioned in a
particular map unit description. Other minor components, however, have properties
and behavioral characteristics divergent enough to affect use or to require different
management. These are called contrasting, or dissimilar, components. They
generally are in small areas and could not be mapped separately because of the
scale used. Some small areas of strongly contrasting soils or miscellaneous areas
are identified by a special symbol on the maps. If included in the database for a
given area, the contrasting minor components are identified in the map unit
descriptions along with some characteristics of each. A few areas of minor
components may not have been observed, and consequently they are not
mentioned in the descriptions, especially where the pattern was so complex that it
was impractical to make enough observations to identify all the soils and
miscellaneous areas on the landscape.
The presence of minor components in a map unit in no way diminishes the
usefulness or accuracy of the data. The objective of mapping is not to delineate
pure taxonomic classes but rather to separate the landscape into landforms or
landform segments that have similar use and management requirements. The
delineation of such segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, however,
onsite investigation is needed to define and locate the soils and miscellaneous
areas.
11
Custom Soil Resource Report
An identifying symbol precedes the map unit name in the map unit descriptions.
Each description includes general facts about the unit and gives important soil
properties and qualities.
Soils that have profiles that are almost alike make up a soil series. Except for
differences in texture of the surface layer, all the soils of a series have major
horizons that are similar in composition, thickness, and arrangement.
Soils of one series can differ in texture of the surface layer, slope, stoniness,
salinity, degree of erosion, and other characteristics that affect their use. On the
basis of such differences, a soil series is divided into soil phases. Most of the areas
shown on the detailed soil maps are phases of soil series. The name of a soil phase
commonly indicates a feature that affects use or management. For example, Alpha
silt loam, 0 to 2 percent slopes, is a phase of the Alpha series.
Some map units are made up of two or more major soils or miscellaneous areas.
These map units are complexes, associations, or undifferentiated groups.
A complex consists of two or more soils or miscellaneous areas in such an intricate
pattern or in such small areas that they cannot be shown separately on the maps.
The pattern and proportion of the soils or miscellaneous areas are somewhat similar
in all areas. Alpha-Beta complex, 0 to 6 percent slopes, is an example.
An association is made up of two or more geographically associated soils or
miscellaneous areas that are shown as one unit on the maps. Because of present
or anticipated uses of the map units in the survey area, it was not considered
practical or necessary to map the soils or miscellaneous areas separately. The
pattern and relative proportion of the soils or miscellaneous areas are somewhat
similar. Alpha-Beta association, 0 to 2 percent slopes, is an example.
An undifferentiated group is made up of two or more soils or miscellaneous areas
that could be mapped individually but are mapped as one unit because similar
interpretations can be made for use and management. The pattern and proportion
of the soils or miscellaneous areas in a mapped area are not uniform. An area can
be made up of only one of the major soils or miscellaneous areas, or it can be made
up of all of them. Alpha and Beta soils, 0 to 2 percent slopes, is an example.
Some surveys include miscellaneous areas. Such areas have little or no soil
material and support little or no vegetation. Rock outcrop is an example.
12
Custom Soil Resource Report
Snohomish County Area, Washington
17—Everett very gravelly sandy loam, 0 to 8 percent slopes
Map Unit Setting
National map unit symbol: 2t629
Elevation: 30 to 900 feet
Mean annual precipitation: 35 to 91 inches
Mean annual air temperature: 48 to 52 degrees F
Frost-free period: 180 to 240 days
Farmland classification: Farmland of statewide importance
Map Unit Composition
Everett and similar soils: 80 percent
Minor components: 20 percent
Estimates are based on observations, descriptions, and transects of the mapunit.
Description of Everett
Setting
Landform: Kames, moraines, eskers
Landform position (two-dimensional): Summit, shoulder
Landform position (three-dimensional): Interfluve, crest
Down-slope shape: Convex
Across-slope shape: Convex
Parent material: Sandy and gravelly glacial outwash
Typical profile
Oi - 0 to 1 inches: slightly decomposed plant material
A - 1 to 3 inches: very gravelly sandy loam
Bw - 3 to 24 inches: very gravelly sandy loam
C1 - 24 to 35 inches: very gravelly loamy sand
C2 - 35 to 60 inches: extremely cobbly coarse sand
Properties and qualities
Slope: 0 to 8 percent
Depth to restrictive feature: More than 80 inches
Drainage class: Somewhat excessively drained
Capacity of the most limiting layer to transmit water (Ksat): High (1.98 to 5.95
in/hr)
Depth to water table: More than 80 inches
Frequency of flooding: None
Frequency of ponding: None
Available water supply, 0 to 60 inches: Low (about 3.2 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 4s
Hydrologic Soil Group: A
Ecological site: F002XA004WA - Puget Lowlands Forest
Forage suitability group: Droughty Soils (G002XN402WA), Droughty Soils
(G002XF403WA), Droughty Soils (G002XS401WA)
Other vegetative classification: Droughty Soils (G002XN402WA), Droughty Soils
(G002XF403WA), Droughty Soils (G002XS401WA)
Hydric soil rating: No
13
Custom Soil Resource Report
Minor Components
Indianola
Percent of map unit: 10 percent
Landform: Terraces, kames, eskers
Landform position (three-dimensional): Tread
Down-slope shape: Linear
Across-slope shape: Linear
Hydric soil rating: No
Alderwood
Percent of map unit: 10 percent
Landform: Hills, ridges
Landform position (two-dimensional): Summit
Landform position (three-dimensional): Crest, talf
Down-slope shape: Convex, linear
Across-slope shape: Convex
Hydric soil rating: No
14
References
American Association of State Highway and Transportation Officials (AASHTO).
2004. Standard specifications for transportation materials and methods of sampling
and testing. 24th edition.
American Society for Testing and Materials (ASTM). 2005. Standard classification of
soils for engineering purposes. ASTM Standard D2487-00.
Cowardin, L.M., V. Carter, F.C. Golet, and E.T. LaRoe. 1979. Classification of
wetlands and deep-water habitats of the United States. U.S. Fish and Wildlife
Service FWS/OBS-79/31.
Federal Register. July 13, 1994. Changes in hydric soils of the United States.
Federal Register. September 18, 2002. Hydric soils of the United States.
Hurt, G.W., and L.M. Vasilas, editors. Version 6.0, 2006. Field indicators of hydric
soils in the United States.
National Research Council. 1995. Wetlands: Characteristics and boundaries.
Soil Survey Division Staff. 1993. Soil survey manual. Soil Conservation Service.
U.S. Department of Agriculture Handbook 18. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/national/soils/?cid=nrcs142p2_054262
Soil Survey Staff. 1999. Soil taxonomy: A basic system of soil classification for
making and interpreting soil surveys. 2nd edition. Natural Resources Conservation
Service, U.S. Department of Agriculture Handbook 436. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053577
Soil Survey Staff. 2010. Keys to soil taxonomy. 11th edition. U.S. Department of
Agriculture, Natural Resources Conservation Service. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053580
Tiner, R.W., Jr. 1985. Wetlands of Delaware. U.S. Fish and Wildlife Service and
Delaware Department of Natural Resources and Environmental Control, Wetlands
Section.
United States Army Corps of Engineers, Environmental Laboratory. 1987. Corps of
Engineers wetlands delineation manual. Waterways Experiment Station Technical
Report Y-87-1.
United States Department of Agriculture, Natural Resources Conservation Service.
National forestry manual. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/
home/?cid=nrcs142p2_053374
United States Department of Agriculture, Natural Resources Conservation Service.
National range and pasture handbook. http://www.nrcs.usda.gov/wps/portal/nrcs/
detail/national/landuse/rangepasture/?cid=stelprdb1043084
15
Custom Soil Resource Report
United States Department of Agriculture, Natural Resources Conservation Service.
National soil survey handbook, title 430-VI. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/soils/scientists/?cid=nrcs142p2_054242
United States Department of Agriculture, Natural Resources Conservation Service.
2006. Land resource regions and major land resource areas of the United States,
the Caribbean, and the Pacific Basin. U.S. Department of Agriculture Handbook
296. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?
cid=nrcs142p2_053624
United States Department of Agriculture, Soil Conservation Service. 1961. Land
capability classification. U.S. Department of Agriculture Handbook 210. http://
www.nrcs.usda.gov/Internet/FSE_DOCUMENTS/nrcs142p2_052290.pdf
16
APPENDIX B – WWHM REPORT
WWHM2012
PROJECT REPORT
General Model Information
Project Name: 98223 INFILTRATION REV2
Site Name: PAISLEY LOFTS
Site Address: 102 E. DIVISION ST.
City: ARLINGTON 98223
Report Date: 12/1/2021
Gage: Everett
Data Start: 1948/10/01
Data End: 2009/09/30
Timestep: 15 Minute
Precip Scale: 1.200
Version Date: 2021/08/18
Version: 4.2.18
POC Thresholds
Low Flow Threshold for POC1: 50 Percent of the 2 Year
High Flow Threshold for POC1: 50 Year
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 2
Landuse Basin Data
Predeveloped Land Use
ONSITE BASIN
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Forest, Flat 0.264
A B, Forest, Mod 0.089
A B, Forest, Steep 0.035
Pervious Total 0.388
Impervious Land Use acre
Impervious Total 0
Basin Total 0.388
Element Flows To:
Surface Interflow Groundwater
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 3
DIVISION FRONTAGE
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Forest, Flat 0.046
A B, Forest, Mod 0.067
A B, Forest, Steep 0.041
Pervious Total 0.154
Impervious Land Use acre
Impervious Total 0
Basin Total 0.154
Element Flows To:
Surface Interflow Groundwater
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 4
WEST OF CENTENNIAL TRAIL
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Forest, Flat 0.036
Pervious Total 0.036
Impervious Land Use acre
Impervious Total 0
Basin Total 0.036
Element Flows To:
Surface Interflow Groundwater
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 5
ALLEY AREA
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Forest, Flat 0.089
A B, Forest, Mod 0.024
A B, Forest, Steep 0.012
Pervious Total 0.125
Impervious Land Use acre
Impervious Total 0
Basin Total 0.125
Element Flows To:
Surface Interflow Groundwater
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 6
Mitigated Land Use
ONSITE BASIN
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Lawn, Flat 0.008
Pervious Total 0.008
Impervious Land Use acre
ROADS FLAT 0.133
ROADS MOD 0.02
ROOF TOPS FLAT 0.224
SIDEWALKS FLAT 0.004
Impervious Total 0.381
Basin Total 0.389
Element Flows To:
Surface Interflow Groundwater
Gravel Trench Bed 1 Gravel Trench Bed 1
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 7
DIVISION FRONTAGE
Bypass: No
GroundWater: No
Pervious Land Use acre
A B, Lawn, Flat 0.018
Pervious Total 0.018
Impervious Land Use acre
ROADS FLAT 0.086
SIDEWALKS FLAT 0.049
Impervious Total 0.135
Basin Total 0.153
Element Flows To:
Surface Interflow Groundwater
Gravel Trench Bed 3 Gravel Trench Bed 3
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 8
WEST OF CENTENNIAL TRAIL
Bypass: No
GroundWater: No
Pervious Land Use acre
Pervious Total 0
Impervious Land Use acre
ROADS FLAT 0.036
Impervious Total 0.036
Basin Total 0.036
Element Flows To:
Surface Interflow Groundwater
Gravel Trench Bed 2 Gravel Trench Bed 2
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 9
ALLEY AREA
Bypass: No
GroundWater: No
Pervious Land Use acre
Pervious Total 0
Impervious Land Use acre
ROADS FLAT 0.124
Impervious Total 0.124
Basin Total 0.124
Element Flows To:
Surface Interflow Groundwater
Gravel Trench Bed 1 Gravel Trench Bed 1
98223 INFILTRATION REV2 12/1/2021 9:05:51 AM Page 10
Routing Elements
Predeveloped Routing
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 11
Mitigated Routing
Gravel Trench Bed 1
Bottom Length: 120.00 ft.
Bottom Width: 10.00 ft.
Trench bottom slope 1: 0 To 1
Trench Left side slope 0: 0 To 1
Trench right side slope 2: 0 To 1
Material thickness of first layer: 1.5
Pour Space of material for first layer: 0.3
Material thickness of second layer: 1.5
Pour Space of material for second layer: 0.3
Material thickness of third layer: 0
Pour Space of material for third layer: 0
Infiltration On
Infiltration rate: 8
Infiltration safety factor: 1
Total Volume Infiltrated (ac-ft.): 97.407
Total Volume Through Riser (ac-ft.): 0.003
Total Volume Through Facility (ac-ft.): 97.41
Percent Infiltrated: 100
Total Precip Applied to Facility: 0
Total Evap From Facility: 0
Discharge Structure
Riser Height: 2.9 ft.
Riser Diameter: 50 in.
Element Flows To:
Outlet 1 Outlet 2
Gravel Trench Bed Hydraulic Table
Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs)
0.0000 0.027 0.000 0.000 0.000
0.0333 0.027 0.000 0.000 0.222
0.0667 0.027 0.000 0.000 0.222
0.1000 0.027 0.000 0.000 0.222
0.1333 0.027 0.001 0.000 0.222
0.1667 0.027 0.001 0.000 0.222
0.2000 0.027 0.001 0.000 0.222
0.2333 0.027 0.001 0.000 0.222
0.2667 0.027 0.002 0.000 0.222
0.3000 0.027 0.002 0.000 0.222
0.3333 0.027 0.002 0.000 0.222
0.3667 0.027 0.003 0.000 0.222
0.4000 0.027 0.003 0.000 0.222
0.4333 0.027 0.003 0.000 0.222
0.4667 0.027 0.003 0.000 0.222
0.5000 0.027 0.004 0.000 0.222
0.5333 0.027 0.004 0.000 0.222
0.5667 0.027 0.004 0.000 0.222
0.6000 0.027 0.005 0.000 0.222
0.6333 0.027 0.005 0.000 0.222
0.6667 0.027 0.005 0.000 0.222
0.7000 0.027 0.005 0.000 0.222
0.7333 0.027 0.006 0.000 0.222
0.7667 0.027 0.006 0.000 0.222
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 12
0.8000 0.027 0.006 0.000 0.222
0.8333 0.027 0.006 0.000 0.222
0.8667 0.027 0.007 0.000 0.222
0.9000 0.027 0.007 0.000 0.222
0.9333 0.027 0.007 0.000 0.222
0.9667 0.027 0.008 0.000 0.222
1.0000 0.027 0.008 0.000 0.222
1.0333 0.027 0.008 0.000 0.222
1.0667 0.027 0.008 0.000 0.222
1.1000 0.027 0.009 0.000 0.222
1.1333 0.027 0.009 0.000 0.222
1.1667 0.027 0.009 0.000 0.222
1.2000 0.027 0.009 0.000 0.222
1.2333 0.027 0.010 0.000 0.222
1.2667 0.027 0.010 0.000 0.222
1.3000 0.027 0.010 0.000 0.222
1.3333 0.027 0.011 0.000 0.222
1.3667 0.027 0.011 0.000 0.222
1.4000 0.027 0.011 0.000 0.222
1.4333 0.027 0.011 0.000 0.222
1.4667 0.027 0.012 0.000 0.222
1.5000 0.027 0.012 0.000 0.222
1.5333 0.027 0.012 0.000 0.222
1.5667 0.027 0.012 0.000 0.222
1.6000 0.027 0.013 0.000 0.222
1.6333 0.027 0.013 0.000 0.222
1.6667 0.027 0.013 0.000 0.222
1.7000 0.027 0.014 0.000 0.222
1.7333 0.027 0.014 0.000 0.222
1.7667 0.027 0.014 0.000 0.222
1.8000 0.027 0.014 0.000 0.222
1.8333 0.027 0.015 0.000 0.222
1.8667 0.027 0.015 0.000 0.222
1.9000 0.027 0.015 0.000 0.222
1.9333 0.027 0.016 0.000 0.222
1.9667 0.027 0.016 0.000 0.222
2.0000 0.027 0.016 0.000 0.222
2.0333 0.027 0.016 0.000 0.222
2.0667 0.027 0.017 0.000 0.222
2.1000 0.027 0.017 0.000 0.222
2.1333 0.027 0.017 0.000 0.222
2.1667 0.027 0.017 0.000 0.222
2.2000 0.027 0.018 0.000 0.222
2.2333 0.027 0.018 0.000 0.222
2.2667 0.027 0.018 0.000 0.222
2.3000 0.027 0.019 0.000 0.222
2.3333 0.027 0.019 0.000 0.222
2.3667 0.027 0.019 0.000 0.222
2.4000 0.027 0.019 0.000 0.222
2.4333 0.027 0.020 0.000 0.222
2.4667 0.027 0.020 0.000 0.222
2.5000 0.027 0.020 0.000 0.222
2.5333 0.027 0.020 0.000 0.222
2.5667 0.027 0.021 0.000 0.222
2.6000 0.027 0.021 0.000 0.222
2.6333 0.027 0.021 0.000 0.222
2.6667 0.027 0.022 0.000 0.222
2.7000 0.027 0.022 0.000 0.222
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 13
2.7333 0.027 0.022 0.000 0.222
2.7667 0.027 0.022 0.000 0.222
2.8000 0.027 0.023 0.000 0.222
2.8333 0.027 0.023 0.000 0.222
2.8667 0.027 0.023 0.000 0.222
2.9000 0.027 0.024 0.000 0.222
2.9333 0.027 0.024 0.269 0.222
2.9667 0.027 0.024 0.761 0.222
3.0000 0.027 0.024 1.397 0.222
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 14
Gravel Trench Bed 2
Bottom Length: 42.00 ft.
Bottom Width: 2.00 ft.
Trench bottom slope 1: 0 To 1
Trench Left side slope 0: 0 To 1
Trench right side slope 2: 0 To 1
Material thickness of first layer: 1.5
Pour Space of material for first layer: 0.3
Material thickness of second layer: 1.5
Pour Space of material for second layer: 0.3
Material thickness of third layer: 0
Pour Space of material for third layer: 0
Infiltration On
Infiltration rate: 8
Infiltration safety factor: 1
Total Volume Infiltrated (ac-ft.): 6.606
Total Volume Through Riser (ac-ft.): 0
Total Volume Through Facility (ac-ft.): 6.606
Percent Infiltrated: 100
Total Precip Applied to Facility: 0
Total Evap From Facility: 0
Discharge Structure
Riser Height: 2.9 ft.
Riser Diameter: 50 in.
Element Flows To:
Outlet 1 Outlet 2
Gravel Trench Bed Hydraulic Table
Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs)
0.0000 0.001928 0.000000 0.000 0.000
0.0333 0.001928 0.000019 0.000 0.015
0.0667 0.001928 0.000039 0.000 0.015
0.1000 0.001928 0.000058 0.000 0.015
0.1333 0.001928 0.000077 0.000 0.015
0.1667 0.001928 0.000096 0.000 0.015
0.2000 0.001928 0.000116 0.000 0.015
0.2333 0.001928 0.000135 0.000 0.015
0.2667 0.001928 0.000154 0.000 0.015
0.3000 0.001928 0.000174 0.000 0.015
0.3333 0.001928 0.000193 0.000 0.015
0.3667 0.001928 0.000212 0.000 0.015
0.4000 0.001928 0.000231 0.000 0.015
0.4333 0.001928 0.000251 0.000 0.015
0.4667 0.001928 0.000270 0.000 0.015
0.5000 0.001928 0.000289 0.000 0.015
0.5333 0.001928 0.000309 0.000 0.015
0.5667 0.001928 0.000328 0.000 0.015
0.6000 0.001928 0.000347 0.000 0.015
0.6333 0.001928 0.000366 0.000 0.015
0.6667 0.001928 0.000386 0.000 0.015
0.7000 0.001928 0.000405 0.000 0.015
0.7333 0.001928 0.000424 0.000 0.015
0.7667 0.001928 0.000444 0.000 0.015
0.8000 0.001928 0.000463 0.000 0.015
0.8333 0.001928 0.000482 0.000 0.015
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 15
0.8667 0.001928 0.000501 0.000 0.015
0.9000 0.001928 0.000521 0.000 0.015
0.9333 0.001928 0.000540 0.000 0.015
0.9667 0.001928 0.000559 0.000 0.015
1.0000 0.001928 0.000579 0.000 0.015
1.0333 0.001928 0.000598 0.000 0.015
1.0667 0.001928 0.000617 0.000 0.015
1.1000 0.001928 0.000636 0.000 0.015
1.1333 0.001928 0.000656 0.000 0.015
1.1667 0.001928 0.000675 0.000 0.015
1.2000 0.001928 0.000694 0.000 0.015
1.2333 0.001928 0.000713 0.000 0.015
1.2667 0.001928 0.000733 0.000 0.015
1.3000 0.001928 0.000752 0.000 0.015
1.3333 0.001928 0.000771 0.000 0.015
1.3667 0.001928 0.000791 0.000 0.015
1.4000 0.001928 0.000810 0.000 0.015
1.4333 0.001928 0.000829 0.000 0.015
1.4667 0.001928 0.000848 0.000 0.015
1.5000 0.001928 0.000868 0.000 0.015
1.5333 0.001928 0.000887 0.000 0.015
1.5667 0.001928 0.000906 0.000 0.015
1.6000 0.001928 0.000926 0.000 0.015
1.6333 0.001928 0.000945 0.000 0.015
1.6667 0.001928 0.000964 0.000 0.015
1.7000 0.001928 0.000983 0.000 0.015
1.7333 0.001928 0.001003 0.000 0.015
1.7667 0.001928 0.001022 0.000 0.015
1.8000 0.001928 0.001041 0.000 0.015
1.8333 0.001928 0.001061 0.000 0.015
1.8667 0.001928 0.001080 0.000 0.015
1.9000 0.001928 0.001099 0.000 0.015
1.9333 0.001928 0.001118 0.000 0.015
1.9667 0.001928 0.001138 0.000 0.015
2.0000 0.001928 0.001157 0.000 0.015
2.0333 0.001928 0.001176 0.000 0.015
2.0667 0.001928 0.001196 0.000 0.015
2.1000 0.001928 0.001215 0.000 0.015
2.1333 0.001928 0.001234 0.000 0.015
2.1667 0.001928 0.001253 0.000 0.015
2.2000 0.001928 0.001273 0.000 0.015
2.2333 0.001928 0.001292 0.000 0.015
2.2667 0.001928 0.001311 0.000 0.015
2.3000 0.001928 0.001331 0.000 0.015
2.3333 0.001928 0.001350 0.000 0.015
2.3667 0.001928 0.001369 0.000 0.015
2.4000 0.001928 0.001388 0.000 0.015
2.4333 0.001928 0.001408 0.000 0.015
2.4667 0.001928 0.001427 0.000 0.015
2.5000 0.001928 0.001446 0.000 0.015
2.5333 0.001928 0.001466 0.000 0.015
2.5667 0.001928 0.001485 0.000 0.015
2.6000 0.001928 0.001504 0.000 0.015
2.6333 0.001928 0.001523 0.000 0.015
2.6667 0.001928 0.001543 0.000 0.015
2.7000 0.001928 0.001562 0.000 0.015
2.7333 0.001928 0.001581 0.000 0.015
2.7667 0.001928 0.001601 0.000 0.015
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 16
2.8000 0.001928 0.001620 0.000 0.015
2.8333 0.001928 0.001639 0.000 0.015
2.8667 0.001928 0.001658 0.000 0.015
2.9000 0.001928 0.001678 0.000 0.015
2.9333 0.001928 0.001697 0.269 0.015
2.9667 0.001928 0.001716 0.761 0.015
3.0000 0.001928 0.001736 1.397 0.015
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 17
Gravel Trench Bed 3
Bottom Length: 40.00 ft.
Bottom Width: 8.00 ft.
Trench bottom slope 1: 0 To 1
Trench Left side slope 0: 0 To 1
Trench right side slope 2: 0 To 1
Material thickness of first layer: 1.5
Pour Space of material for first layer: 0.3
Material thickness of second layer: 1.5
Pour Space of material for second layer: 0.3
Material thickness of third layer: 0
Pour Space of material for third layer: 0
Infiltration On
Infiltration rate: 8
Infiltration safety factor: 1
Total Volume Infiltrated (ac-ft.): 25.759
Total Volume Through Riser (ac-ft.): 0.001
Total Volume Through Facility (ac-ft.): 25.759
Percent Infiltrated: 100
Total Precip Applied to Facility: 0
Total Evap From Facility: 0
Discharge Structure
Riser Height: 2.9 ft.
Riser Diameter: 50 in.
Element Flows To:
Outlet 1 Outlet 2
Gravel Trench Bed Hydraulic Table
Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs)
0.0000 0.007 0.000 0.000 0.000
0.0333 0.007 0.000 0.000 0.059
0.0667 0.007 0.000 0.000 0.059
0.1000 0.007 0.000 0.000 0.059
0.1333 0.007 0.000 0.000 0.059
0.1667 0.007 0.000 0.000 0.059
0.2000 0.007 0.000 0.000 0.059
0.2333 0.007 0.000 0.000 0.059
0.2667 0.007 0.000 0.000 0.059
0.3000 0.007 0.000 0.000 0.059
0.3333 0.007 0.000 0.000 0.059
0.3667 0.007 0.000 0.000 0.059
0.4000 0.007 0.000 0.000 0.059
0.4333 0.007 0.001 0.000 0.059
0.4667 0.007 0.001 0.000 0.059
0.5000 0.007 0.001 0.000 0.059
0.5333 0.007 0.001 0.000 0.059
0.5667 0.007 0.001 0.000 0.059
0.6000 0.007 0.001 0.000 0.059
0.6333 0.007 0.001 0.000 0.059
0.6667 0.007 0.001 0.000 0.059
0.7000 0.007 0.001 0.000 0.059
0.7333 0.007 0.001 0.000 0.059
0.7667 0.007 0.001 0.000 0.059
0.8000 0.007 0.001 0.000 0.059
0.8333 0.007 0.001 0.000 0.059
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 18
0.8667 0.007 0.001 0.000 0.059
0.9000 0.007 0.002 0.000 0.059
0.9333 0.007 0.002 0.000 0.059
0.9667 0.007 0.002 0.000 0.059
1.0000 0.007 0.002 0.000 0.059
1.0333 0.007 0.002 0.000 0.059
1.0667 0.007 0.002 0.000 0.059
1.1000 0.007 0.002 0.000 0.059
1.1333 0.007 0.002 0.000 0.059
1.1667 0.007 0.002 0.000 0.059
1.2000 0.007 0.002 0.000 0.059
1.2333 0.007 0.002 0.000 0.059
1.2667 0.007 0.002 0.000 0.059
1.3000 0.007 0.002 0.000 0.059
1.3333 0.007 0.002 0.000 0.059
1.3667 0.007 0.003 0.000 0.059
1.4000 0.007 0.003 0.000 0.059
1.4333 0.007 0.003 0.000 0.059
1.4667 0.007 0.003 0.000 0.059
1.5000 0.007 0.003 0.000 0.059
1.5333 0.007 0.003 0.000 0.059
1.5667 0.007 0.003 0.000 0.059
1.6000 0.007 0.003 0.000 0.059
1.6333 0.007 0.003 0.000 0.059
1.6667 0.007 0.003 0.000 0.059
1.7000 0.007 0.003 0.000 0.059
1.7333 0.007 0.003 0.000 0.059
1.7667 0.007 0.003 0.000 0.059
1.8000 0.007 0.004 0.000 0.059
1.8333 0.007 0.004 0.000 0.059
1.8667 0.007 0.004 0.000 0.059
1.9000 0.007 0.004 0.000 0.059
1.9333 0.007 0.004 0.000 0.059
1.9667 0.007 0.004 0.000 0.059
2.0000 0.007 0.004 0.000 0.059
2.0333 0.007 0.004 0.000 0.059
2.0667 0.007 0.004 0.000 0.059
2.1000 0.007 0.004 0.000 0.059
2.1333 0.007 0.004 0.000 0.059
2.1667 0.007 0.004 0.000 0.059
2.2000 0.007 0.004 0.000 0.059
2.2333 0.007 0.004 0.000 0.059
2.2667 0.007 0.005 0.000 0.059
2.3000 0.007 0.005 0.000 0.059
2.3333 0.007 0.005 0.000 0.059
2.3667 0.007 0.005 0.000 0.059
2.4000 0.007 0.005 0.000 0.059
2.4333 0.007 0.005 0.000 0.059
2.4667 0.007 0.005 0.000 0.059
2.5000 0.007 0.005 0.000 0.059
2.5333 0.007 0.005 0.000 0.059
2.5667 0.007 0.005 0.000 0.059
2.6000 0.007 0.005 0.000 0.059
2.6333 0.007 0.005 0.000 0.059
2.6667 0.007 0.005 0.000 0.059
2.7000 0.007 0.006 0.000 0.059
2.7333 0.007 0.006 0.000 0.059
2.7667 0.007 0.006 0.000 0.059
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 19
2.8000 0.007 0.006 0.000 0.059
2.8333 0.007 0.006 0.000 0.059
2.8667 0.007 0.006 0.000 0.059
2.9000 0.007 0.006 0.000 0.059
2.9333 0.007 0.006 0.269 0.059
2.9667 0.007 0.006 0.761 0.059
3.0000 0.007 0.006 1.397 0.059
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 20
Analysis Results
POC 1
+ Predeveloped x Mitigated
Predeveloped Landuse Totals for POC #1
Total Pervious Area: 0.703
Total Impervious Area: 0
Mitigated Landuse Totals for POC #1
Total Pervious Area: 0.026
Total Impervious Area: 0.676
Flow Frequency Method: Log Pearson Type III 17B
Flow Frequency Return Periods for Predeveloped. POC #1
Return Period Flow(cfs)
2 year 0.000856
5 year 0.001967
10 year 0.003268
25 year 0.005949
50 year 0.009049
100 year 0.013494
Flow Frequency Return Periods for Mitigated. POC #1
Return Period Flow(cfs)
2 year 0
5 year 0
10 year 0
25 year 0
50 year 0
100 year 0
Annual Peaks
98223 INFILTRATION REV2 12/1/2021 9:05:52 AM Page 21
Annual Peaks for Predeveloped and Mitigated. POC #1
Year Predeveloped Mitigated
1949 0.001 0.000
1950 0.002 0.000
1951 0.001 0.000
1952 0.001 0.000
1953 0.001 0.000
1954 0.005 0.000
1955 0.003 0.000
1956 0.001 0.000
1957 0.001 0.000
1958 0.001 0.000
1959 0.001 0.000
1960 0.001 0.000
1961 0.003 0.097
1962 0.001 0.000
1963 0.001 0.000
1964 0.002 0.000
1965 0.001 0.000
1966 0.001 0.000
1967 0.001 0.000
1968 0.001 0.000
1969 0.001 0.000
1970 0.001 0.000
1971 0.003 0.000
1972 0.001 0.000
1973 0.001 0.000
1974 0.002 0.000
1975 0.001 0.000
1976 0.002 0.000
1977 0.001 0.000
1978 0.001 0.000
1979 0.001 0.000
1980 0.001 0.000
1981 0.001 0.000
1982 0.001 0.000
1983 0.001 0.000
1984 0.001 0.000
1985 0.001 0.000
1986 0.006 0.000
1987 0.004 0.000
1988 0.001 0.000
1989 0.001 0.000
1990 0.001 0.000
1991 0.001 0.000
1992 0.001 0.000
1993 0.001 0.000
1994 0.001 0.000
1995 0.001 0.000
1996 0.008 0.000
1997 0.020 0.000
1998 0.001 0.000
1999 0.001 0.000
2000 0.001 0.000
2001 0.000 0.000
2002 0.001 0.000
2003 0.000 0.000
2004 0.001 0.000
98223 INFILTRATION REV2 12/1/2021 9:08:44 AM Page 22
2005 0.001 0.000
2006 0.022 0.000
2007 0.001 0.000
2008 0.001 0.000
2009 0.001 0.000
Ranked Annual Peaks
Ranked Annual Peaks for Predeveloped and Mitigated. POC #1
Rank Predeveloped Mitigated
1 0.0221 0.0966
2 0.0198 0.0000
3 0.0079 0.0000
4 0.0059 0.0000
5 0.0046 0.0000
6 0.0039 0.0000
7 0.0034 0.0000
8 0.0032 0.0000
9 0.0031 0.0000
10 0.0021 0.0000
11 0.0020 0.0000
12 0.0018 0.0000
13 0.0015 0.0000
14 0.0015 0.0000
15 0.0014 0.0000
16 0.0014 0.0000
17 0.0013 0.0000
18 0.0012 0.0000
19 0.0012 0.0000
20 0.0011 0.0000
21 0.0010 0.0000
22 0.0010 0.0000
23 0.0008 0.0000
24 0.0006 0.0000
25 0.0006 0.0000
26 0.0006 0.0000
27 0.0006 0.0000
28 0.0006 0.0000
29 0.0006 0.0000
30 0.0006 0.0000
31 0.0006 0.0000
32 0.0006 0.0000
33 0.0006 0.0000
34 0.0006 0.0000
35 0.0006 0.0000
36 0.0006 0.0000
37 0.0006 0.0000
38 0.0006 0.0000
39 0.0006 0.0000
40 0.0006 0.0000
41 0.0006 0.0000
42 0.0006 0.0000
43 0.0006 0.0000
44 0.0006 0.0000
45 0.0006 0.0000
46 0.0006 0.0000
47 0.0006 0.0000
48 0.0006 0.0000
49 0.0006 0.0000
98223 INFILTRATION REV2 12/1/2021 9:08:44 AM Page 23
50 0.0006 0.0000
51 0.0006 0.0000
52 0.0006 0.0000
53 0.0006 0.0000
54 0.0006 0.0000
55 0.0005 0.0000
56 0.0005 0.0000
57 0.0005 0.0000
58 0.0005 0.0000
59 0.0005 0.0000
60 0.0005 0.0000
61 0.0004 0.0000
98223 INFILTRATION REV2 12/1/2021 9:08:44 AM Page 24
LID Duration Flows
The Facility PASSED
Flow(cfs) Predev Mit Percentage Pass/Fail
0.0001 27399 2 0 Pass
0.0001 26180 2 0 Pass
0.0001 25239 2 0 Pass
0.0001 24105 2 0 Pass
0.0001 23185 2 0 Pass
0.0001 22351 2 0 Pass
0.0001 21496 2 0 Pass
0.0001 21025 2 0 Pass
0.0001 20384 2 0 Pass
0.0001 19860 2 0 Pass
0.0001 19447 2 0 Pass
0.0001 18925 2 0 Pass
0.0001 18431 2 0 Pass
0.0001 18080 2 0 Pass
0.0001 17635 2 0 Pass
0.0001 17314 2 0 Pass
0.0001 16906 2 0 Pass
0.0001 16461 2 0 Pass
0.0001 16106 2 0 Pass
0.0001 15644 2 0 Pass
0.0001 15190 2 0 Pass
0.0001 14822 2 0 Pass
0.0001 14380 2 0 Pass
0.0002 13963 2 0 Pass
0.0002 13663 2 0 Pass
0.0002 13285 2 0 Pass
0.0002 12955 2 0 Pass
0.0002 12549 2 0 Pass
0.0002 12207 2 0 Pass
0.0002 11903 2 0 Pass
0.0002 11573 2 0 Pass
0.0002 11255 2 0 Pass
0.0002 11049 2 0 Pass
0.0002 10769 2 0 Pass
0.0002 10532 2 0 Pass
0.0002 10262 2 0 Pass
0.0002 10001 2 0 Pass
0.0002 9835 2 0 Pass
0.0002 9621 2 0 Pass
0.0002 9409 2 0 Pass
0.0002 9261 2 0 Pass
0.0002 9086 2 0 Pass
0.0002 8846 2 0 Pass
0.0002 8680 2 0 Pass
0.0002 8493 2 0 Pass
0.0002 8365 2 0 Pass
0.0002 8181 2 0 Pass
0.0002 7993 2 0 Pass
0.0002 7884 2 0 Pass
0.0002 7732 2 0 Pass
0.0003 7572 2 0 Pass
0.0003 7460 2 0 Pass
0.0003 7304 2 0 Pass
98223 INFILTRATION REV2 12/1/2021 9:08:44 AM Page 25
0.0003 7193 2 0 Pass
0.0003 7039 2 0 Pass
0.0003 6889 2 0 Pass
0.0003 6782 2 0 Pass
0.0003 6579 2 0 Pass
0.0003 6417 2 0 Pass
0.0003 6282 2 0 Pass
0.0003 6074 2 0 Pass
0.0003 5873 2 0 Pass
0.0003 5709 2 0 Pass
0.0003 5533 2 0 Pass
0.0003 5358 2 0 Pass
0.0003 5153 2 0 Pass
0.0003 4962 2 0 Pass
0.0003 4855 2 0 Pass
0.0003 4697 2 0 Pass
0.0003 4554 2 0 Pass
0.0003 4453 2 0 Pass
0.0003 4297 2 0 Pass
0.0003 4211 2 0 Pass
0.0003 4070 2 0 Pass
0.0003 3953 2 0 Pass
0.0003 3865 2 0 Pass
0.0003 3724 2 0 Pass
0.0003 3583 2 0 Pass
0.0004 3491 2 0 Pass
0.0004 3358 2 0 Pass
0.0004 3230 2 0 Pass
0.0004 3161 2 0 Pass
0.0004 3067 2 0 Pass
0.0004 3005 2 0 Pass
0.0004 2920 2 0 Pass
0.0004 2845 2 0 Pass
0.0004 2793 2 0 Pass
0.0004 2731 2 0 Pass
0.0004 2661 2 0 Pass
0.0004 2609 2 0 Pass
0.0004 2537 2 0 Pass
0.0004 2488 2 0 Pass
0.0004 2421 2 0 Pass
0.0004 2346 2 0 Pass
0.0004 2299 2 0 Pass
0.0004 2216 2 0 Pass
0.0004 2150 2 0 Pass
0.0004 2115 2 0 Pass
0.0004 2061 2 0 Pass
0.0004 1999 2 0 Pass
98223 INFILTRATION REV2 12/1/2021 9:08:44 AM Page 26
Duration Flows
The Facility PASSED
Flow(cfs) Predev Mit Percentage Pass/Fail
0.0004 1999 2 0 Pass
0.0005 797 2 0 Pass
0.0006 142 2 1 Pass
0.0007 119 2 1 Pass
0.0008 109 2 1 Pass
0.0009 94 2 2 Pass
0.0010 79 2 2 Pass
0.0010 68 2 2 Pass
0.0011 61 2 3 Pass
0.0012 59 2 3 Pass
0.0013 54 2 3 Pass
0.0014 51 2 3 Pass
0.0015 49 2 4 Pass
0.0016 47 2 4 Pass
0.0016 43 2 4 Pass
0.0017 40 2 5 Pass
0.0018 36 2 5 Pass
0.0019 36 2 5 Pass
0.0020 31 2 6 Pass
0.0021 31 2 6 Pass
0.0022 29 2 6 Pass
0.0023 29 2 6 Pass
0.0023 29 2 6 Pass
0.0024 26 2 7 Pass
0.0025 26 2 7 Pass
0.0026 26 2 7 Pass
0.0027 25 2 8 Pass
0.0028 23 2 8 Pass
0.0029 23 2 8 Pass
0.0030 23 2 8 Pass
0.0030 23 2 8 Pass
0.0031 22 2 9 Pass
0.0032 20 2 10 Pass
0.0033 19 2 10 Pass
0.0034 17 2 11 Pass
0.0035 16 2 12 Pass
0.0036 16 2 12 Pass
0.0036 15 2 13 Pass
0.0037 15 2 13 Pass
0.0038 15 2 13 Pass
0.0039 15 2 13 Pass
0.0040 13 2 15 Pass
0.0041 13 2 15 Pass
0.0042 13 2 15 Pass
0.0043 13 2 15 Pass
0.0043 13 2 15 Pass
0.0044 13 2 15 Pass
0.0045 13 2 15 Pass
0.0046 11 2 18 Pass
0.0047 11 2 18 Pass
0.0048 11 2 18 Pass
0.0049 11 2 18 Pass
0.0050 11 2 18 Pass
98223 INFILTRATION REV2 12/1/2021 9:09:29 AM Page 27
0.0050 11 2 18 Pass
0.0051 11 2 18 Pass
0.0052 11 2 18 Pass
0.0053 11 2 18 Pass
0.0054 11 2 18 Pass
0.0055 11 2 18 Pass
0.0056 11 2 18 Pass
0.0057 11 2 18 Pass
0.0057 11 2 18 Pass
0.0058 11 2 18 Pass
0.0059 9 2 22 Pass
0.0060 9 2 22 Pass
0.0061 9 2 22 Pass
0.0062 9 2 22 Pass
0.0063 9 2 22 Pass
0.0063 9 2 22 Pass
0.0064 9 2 22 Pass
0.0065 8 2 25 Pass
0.0066 8 2 25 Pass
0.0067 8 2 25 Pass
0.0068 8 2 25 Pass
0.0069 8 2 25 Pass
0.0070 7 2 28 Pass
0.0070 7 2 28 Pass
0.0071 7 2 28 Pass
0.0072 7 2 28 Pass
0.0073 7 2 28 Pass
0.0074 7 2 28 Pass
0.0075 7 2 28 Pass
0.0076 7 2 28 Pass
0.0077 7 2 28 Pass
0.0077 7 2 28 Pass
0.0078 7 2 28 Pass
0.0079 7 2 28 Pass
0.0080 6 2 33 Pass
0.0081 6 2 33 Pass
0.0082 6 2 33 Pass
0.0083 6 2 33 Pass
0.0084 6 2 33 Pass
0.0084 6 2 33 Pass
0.0085 6 2 33 Pass
0.0086 6 2 33 Pass
0.0087 6 2 33 Pass
0.0088 5 2 40 Pass
0.0089 5 2 40 Pass
0.0090 5 2 40 Pass
0.0090 5 2 40 Pass
98223 INFILTRATION REV2 12/1/2021 9:09:29 AM Page 28
Water Quality
Water Quality BMP Flow and Volume for POC #1
On-line facility volume: 0 acre-feet
On-line facility target flow: 0 cfs.
Adjusted for 15 min: 0 cfs.
Off-line facility target flow: 0 cfs.
Adjusted for 15 min: 0 cfs.
98223 INFILTRATION REV2 12/1/2021 9:09:29 AM Page 29
LID Report
98223 INFILTRATION REV2 12/1/2021 9:09:29 AM Page 30
Model Default Modifications
Total of 0 changes have been made.
PERLND Changes
No PERLND changes have been made.
IMPLND Changes
No IMPLND changes have been made.
98223 INFILTRATION REV2 12/1/2021 9:09:36 AM Page 31
Appendix
Predeveloped Schematic
98223 INFILTRATION REV2 12/1/2021 9:09:36 AM Page 32
Mitigated Schematic
98223 INFILTRATION REV2 12/1/2021 9:09:36 AM Page 33
APPENDIX C – OPERATION AND MAINTENANCE MANUAL
STORMWATER FACILITY
MAINTENANCE MANUAL
FOR PUBLIC & PRIVATELY OWNED
STORMWATER FACILITIES
PREPARED BY:
CASCADE SURVEYING & ENGINEERING, INC.
December 2021
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................................. 2
INTRODUCTION ........................................................................................................................................ 3
CATCH BASIN ........................................................................................................................................... 4
CATCH BASIN INSERT ............................................................................................................................. 7
CONVEYANCE STORMWATER PIPE ...................................................................................................... 9
OIL WATER SEPORATOR CATCH BASIN ............................................................................................ 10
INFILTRATION TRENCH ......................................................................................................................... 12
YARD DRAIN & CLEANOUT ................................................................................................................... 14
INTRODUCTION
Background
All residential, commercial, and industrial developments have some form of stormwater
drainage facilities. Stormwater facilities generally drain to roadside ditches, underground storm
pipe systems, streams, lakes, or to groundwater from infiltration facilities. Stormwater facilities
generally consist of pipes, catch basins, swales, ditches, ponds, oil/water separators,
underground infiltration trenches, and any other structure that collects, conveys, controls, and
treats stormwater.
Stormwater facilities are either privately owned or publicly owned. Private stormwater facility
owners consist of individual residential property owners, a home owners’ association,
commercial and industrial land owners. Privately owned stormwater facilities are generally
installed on private property within the bounds of the private land, in a separate tract, or in an
easement on land owned by others.
Publicly owned stormwater facilities are usually owned and operated by a city, county, state, or
federal entities. In either case, the owner of the system is responsible for operating and
maintaining all elements of the facility.
Purpose
The objective of this manual is to ensure that stormwater control facilities are adequately
maintained and operated properly.
Storm system maintenance is necessary to protect streams, lakes, wetlands, and groundwater.
Proper maintenance assures that storm systems operate as they were designed, and that they
are cleaned of pollutants that they trap, such as sediment and oils, so that the storm system is
not overwhelmed and becomes a pollutant source.
Stormwater System Inspection Schedule
The drainage system should be monitored periodically. For the first year after completion of
construction, the system should be monitored after every large storm event (> 1-in in 24-hrs),
and, during the period Oct. 1- Mar. 31 inspections should be conducted monthly. From April 1-
Sept. 30, the facility should be monitored on a quarterly basis. Once the performance
characteristics of the facility have been verified, the monitoring schedule can be reduced to an
annual basis unless the performance data indicate that a more frequent schedule is required.
(CATCH BASIN)
Yard Drain & Cleanout
What is a Yard Drain?
A Yard Drain is similar to a Type 1 Catch Basin but smaller (most are 12 to 18 inches in diameter).
ï‚· Currently, the most frequently used type of yard drain is a high density polyethylene (HDPE) pipe:
o set vertically on end,
o with the bell end up fitted with a grate, and
o the bottom end resting on washed drain rock.
ï‚· There are older versions which are made of either polyvinylchloride (PVC) or Concrete Pipe.
How does a Yard Drain work?
Yard Drain systems usually consist of several yard drains and 6â€-8†diameter HDPE pipe between them. They are
designed for use in private residential or commercial property and not for use in public or private streets and
roads.
ï‚· They function as an intermediary stormwater conveyance system that connects roof and building
foundation footing drains (4â€-6†diameter HDPE pipe) to the main stormwater conveyance system of:
o Type 1 or 2 Catch Basins, and
o 12†and larger diameter HDPE pipe.
ï‚· Typically, in residential subdivisions these systems can be located along lot lines.
ï‚· Yard Drains also have commercial property applications, often being installed to connect building roof
and footing drains To the parking area and driveway drainage systems.
NOTE: If Yard Drains are not visible, it is possible that Cleanouts were installed as a substitute. This is generally
the case when the depth from the top of the Yard Drain grate to what would be the top of the washed drain
rock exceeds 42â€. (See drawings below.)
Common maintenance needs
The most common tool for cleaning Yard Drains or Cleanouts is a yard hose. Cleaning by a vactor truck with its
very high pressure and volume washing and vacuum system can destroy both the older Yard Drains or Cleanouts
and pipe. It is better to use a low pressure washing system and scoop out by hand any mud and debris collecting
in the Yard Drains or Cleanouts.
Snohomish County Drainage Facility Maintenance Guide
11
Yard Drain
Snohomish County Drainage Facility Maintenance Guide
12
Cleanout
Snohomish County Drainage Facility Maintenance Guide
13
Yard Drain & Cleanout
Drainage Results expected when
system Potential Conditions when maintenance is performed
feature defect maintenance is needed or not needed
Metal Excessive ï‚· Obstruction Immediately in front of the ï‚· Obstruction removed.
Grates accumulation drain grate or covering it is reducing
of trash, flow causing ponding or partial flow
debris, bypass.
sediment
and ï‚· Obstructing more than 1/3 of inlet or ï‚· Obstruction removed.
vegetation outlet pipe diameter.
ï‚· Decaying and generating odors that ï‚· Vegetation removed.
could cause complaints or dangerous
gases (e.g., methane).
Not in place ï‚· Missing or only partially in place. ï‚· Grate in place, repaired or
replaced.
Damaged ï‚· Broken ï‚· Grate repaired or replaced.
Sump Sediment, ï‚· Sediment exceeds 60 percent of the ï‚· Sediment removed.
accumulation sump depth.
ï‚· Measure from bottom of basin to invert
of the lowest, but in no case less than a
minimum of 6 inches clearance from the
sediment surface to the invert of the
lowest pipe.
Structure Cracks in wall ï‚· Cracks in wall ï‚· Basin repaired or replaced.
ï‚· Pipe is re-grouted and secure at
basin wall.
Settlement ï‚· Settlement or misalignment ï‚· Basin raised, realigned, repaired
or or replaced.
misalignment
Pollutants in ï‚· Most commonly occurring are herbicides ï‚· Pollutants removed.
water or and insecticides.
sediment
ï‚· Identify and remove source.
Snohomish County Drainage Facility Maintenance Guide
14
Construction Stormwater General Permit
Stormwater Pollution Prevention Plan
(SWPPP)
for
Paisley Lofts Construction Plans
Tax Parcel Numbers:
00529900900101 / 00529900900300
Prepared for:
The Washington State Department of Ecology
Northwest Region
Permittee / Owner Developer Operator / Contractor
Grandview North, LLC N/A N/A
Certified Erosion and Sediment Control Lead (CESCL)
Name Organization Contact Phone Number
N/A N/A N/A
SWPPP Prepared By
Name Organization Contact Phone Number
Josh Hogan Cascade Surveying & (360) 435-5551
Engineering
SWPPP Preparation Date
April 2022
Project Construction Dates
Activity / Phase Start Date End Date
Civil Construction Application June 1st, 2022 October 1st, 2023
Table of Contents
1 Project Information .............................................................................................................. 4
1.1 Existing Conditions ...................................................................................................... 4
1.2 Proposed Construction Activities .................................................................................. 4
2 Construction Stormwater Best Management Practices (BMPs) ........................................... 6
2.1 The 13 Elements .......................................................................................................... 6
2.1.1 Element 1: Preserve Vegetation / Mark Clearing Limits ........................................ 6
2.1.2 Element 2: Establish Construction Access ............................................................ 6
2.1.3 Element 3: Control Flow Rates ............................................................................. 7
2.1.4 Element 4: Install Sediment Controls .................................................................... 7
2.1.5 Element 5: Stabilize Soils ..................................................................................... 8
2.1.6 Element 6: Protect Slopes..................................................................................... 9
2.1.7 Element 7: Protect Drain Inlets ............................................................................. 9
2.1.8 Element 8: Stabilize Channels and Outlets ..........................................................10
2.1.9 Element 9: Control Pollutants ...............................................................................10
2.1.10 Element 10: Control Dewatering ..........................................................................11
2.1.11 Element 11: Maintain BMPs .................................................................................11
2.1.12 Element 12: Manage the Project ..........................................................................13
2.1.13 Element 13: Protect Low Impact Development (LID) BMPs .................................14
3 Pollution Prevention Team .................................................................................................15
4 Monitoring and Sampling Requirements ............................................................................16
4.1 Site Inspection ............................................................................................................16
4.2 Stormwater Quality Sampling ......................................................................................16
4.2.1 Turbidity Sampling ...............................................................................................16
4.2.2 pH Sampling ........................................................................................................16
5 Discharges to 303(d) or Total Maximum Daily Load (TMDL) Waterbodies .........................17
5.1 303(d) Listed Waterbodies ..........................................................................................17
5.2 TMDL Waterbodies .....................................................................................................17
6 Reporting and Record Keeping ..........................................................................................18
6.1 Record Keeping ..........................................................................................................18
6.1.1 Site Log Book ......................................................................................................18
6.1.2 Records Retention ...............................................................................................18
6.1.3 Updating the SWPPP ...........................................................................................18
6.2 Reporting ....................................................................................................................18
6.2.1 Discharge Monitoring Reports ..............................................................................18
6.2.2 Notification of Noncompliance ................................ Error! Bookmark not defined.
P a g e | 1
List of Tables
Table 1 – Summary of Site Pollutant Constituents ................................................................ 4
Table 2 – Pollutants ................................................................................................................10
Table 3 – pH-Modifying Sources ............................................................................................10
Table 5 – Management ............................................................................................................13
Table 6 – BMP Implementation Schedule ..............................................................................14
Table 7 – Team Information ....................................................................................................15
List of Appendices
Appendix/Glossary
A. Site Map
B. BMP Detail
C. Correspondence
D. Site Inspection Form
E. Construction Stormwater General Permit (CSWGP)
F. 303(d) List Waterbodies / TMDL Waterbodies Information
G. Contaminated Site Information
H. Engineering Calculations
P a g e | 2
List of Acronyms and Abbreviations
Acronym / Abbreviation Explanation
303(d) Section of the Clean Water Act pertaining to Impaired Waterbodies
BFO Bellingham Field Office of the Department of Ecology
BMP(s) Best Management Practice(s)
CESCL Certified Erosion and Sediment Control Lead
CO2 Carbon Dioxide
CRO Central Regional Office of the Department of Ecology
CSWGP Construction Stormwater General Permit
CWA Clean Water Act
DMR Discharge Monitoring Report
DO Dissolved Oxygen
Ecology Washington State Department of Ecology
EPA United States Environmental Protection Agency
ERO Eastern Regional Office of the Department of Ecology
ERTS Environmental Report Tracking System
ESC Erosion and Sediment Control
GULD General Use Level Designation
NPDES National Pollutant Discharge Elimination System
NTU Nephelometric Turbidity Units
NWRO Northwest Regional Office of the Department of Ecology
pH Power of Hydrogen
RCW Revised Code of Washington
SPCC Spill Prevention, Control, and Countermeasure
su Standard Units
SWMMEW Stormwater Management Manual for Eastern Washington
SWMMWW Stormwater Management Manual for Western Washington
SWPPP Stormwater Pollution Prevention Plan
TESC Temporary Erosion and Sediment Control
SWRO Southwest Regional Office of the Department of Ecology
TMDL Total Maximum Daily Load
VFO Vancouver Field Office of the Department of Ecology
WAC Washington Administrative Code
WSDOT Washington Department of Transportation
WWHM Western Washington Hydrology Model
P a g e | 3
1 Project Information
Project/Site Name: Paisley Lofts Construction Plans
Street/Location: 102 E. Division St.
City: Arlington State: WA Zip code: 98223
Subdivision: N/A
Receiving waterbody: N/A
1.1 Existing Conditions
Total acreage (including support activities such as off-site equipment staging yards, material
storage areas, borrow areas).
Total acreage: 0.77 acres
Disturbed acreage: 0.77 acres
Existing structures: One structure
Landscape Small shrubs and trees around building
topography:
Drainage patterns: Site slopes northwest and runoff flows off the site
Existing Vegetation: None – fully developed
Critical Areas (wetlands, streams, high erosion None onsite
risk, steep or difficult to stabilize slopes):
List of known impairments for 303(d) listed or Total Maximum Daily Load (TMDL) for the
receiving waterbody: N/A
Table 1 includes a list of suspected and/or known contaminants associated with the construction
activity.
Table 1 – Summary of Site Pollutant Constituents
Constituent
Location Depth Concentration
(Pollutant)
1.2 Proposed Construction Activities
Description of site development (example: subdivision): Multi Use Development
Description of construction activities (example: site preparation, demolition, excavation):
Approximate anticipated grading for the site:
Cut = 750 cu. yds.
Fill = 600 cu. yds.
Net (Cut) = 150 cu. yds.
P a g e | 4
Description of site drainage including flow from and onto adjacent properties. Must be consistent
with Site Map in Appendix A:
The site has well-draining soils so no flow from or onto adjacent properties is expected.
Description of final stabilization (example: extent of revegetation, paving, landscaping):
The site will consist of building, paved parking lot with landscaping area. The landscaping will be
amended soils.
Contaminated Site Information:
Proposed activities regarding contaminated soils or groundwater (example: on-site treatment
system, authorized sanitary sewer discharge):
N/A
P a g e | 5
2 Construction Stormwater Best Management Practices (BMPs)
The SWPPP is a living document reflecting current conditions and changes throughout the life
of the project. These changes may be informal (i.e., hand-written notes and deletions). Update
the SWPPP when the CESCL has noted a deficiency in BMPs or deviation from original design.
2.1 The 13 Elements
2.1.1 Element 1: Preserve Vegetation / Mark Clearing Limits
To protect adjacent properties and to reduce the area of soil exposed to construction, the limits of
construction will be clearly marked before land-disturbing activities begin. Trees that are to be
preserved, as well as all sensitive areas and their buffers, shall be clearly delineated, both in the
field and on the plans. In general, natural vegetation and native topsoil shall be retained in an
undisturbed state to the maximum extent possible. The BMPs relevant to marking the clearing
limits that will be applied for this project include:
o Preserving Natural Vegetation (BMP C101)
o High Visibility Plastic or Metal Fence (BMP C103)
BMP C101: Clearing limits will be marked both on the plans and in the field, where natural
vegetation is to be protected.
BMP C103: High visibility plastic fence will be used to delineate clearing limits and areas of
vegetation to be protected.
Alternate BMPs for marking clearing limits are included in Appendix C as a quick reference tool
for the onsite inspector in the event the BMP(s) listed above are deemed ineffective or
inappropriate during construction, the Certified Erosion and Sediment Control Lead will
promptly initiate the implementation of one or more of the alternative BMPs listed in Appendix
C after the first sign that existing BMPs are ineffective or failing.
2.1.2 Element 2: Establish Construction Access
Construction access or activities occurring on unpaved areas shall be minimized, yet where
necessary, access points shall be stabilized to minimize the tracking of sediment onto public
roads, and wheel washing, street sweeping, and street cleaning shall be employed to prevent
sediment from entering state waters. All wash wastewater shall be controlled on site. The
specific BMPs related to establishing construction access that will be used on this project
include:
o Stabilized Construction Entrance (BMP C105)
BMP C105: A stabilized construction entrance will be located at the entrance to the site.
P a g e | 6
Alternate construction access BMPs are included in Appendix C as a quick reference tool for the
onsite inspector in the event the BMP(s) listed above are deemed ineffective or inappropriate
during construction, the Certified Erosion and Sediment Control Lead will promptly initiate the
implementation of one or more of the alternative BMPs listed in Appendix C after the first sign
that existing BMPs are ineffective or failing.
2.1.3 Element 3: Control Flow Rates
In order to protect the properties and waterways downstream of the project site, stormwater
discharges from the site will be controlled if increased. The specific BMPs for flow control that
is being used on this project include:
o Silt Fence (BMP C233)
Alternate flow control BMPs are included in Appendix C as a quick reference tool for the onsite
inspector in the event the BMP(s) listed above are deemed ineffective or inappropriate during
construction, the Certified Erosion and Sediment Control Lead will promptly initiate the
implementation of one or more of the alternative BMPs listed in Appendix C after the first sign
that existing BMPs are ineffective or failing.
In general, discharge rates of stormwater from the site will be controlled where increases in
impervious area or soil compaction during construction could lead to downstream erosion, or
where necessary to meet local agency stormwater discharge requirements (e.g. discharge to
combined sewer systems).
Will you construct stormwater retention and/or detention facilities?
Yes No
Will you use permanent infiltration ponds or other low impact development (example: rain
gardens, bio-retention, porous pavement) to control flow during construction?
Yes No
2.1.4 Element 4: Install Sediment Controls
All stormwater runoff from disturbed areas shall pass through an appropriate sediment removal
BMP before leaving the construction site or prior to being discharged to an infiltration facility.
The specific BMPs to be used for controlling sediment on this project include:
o Silt Fence (BMP C233)
Alternate sediment control BMPs are included in Appendix C as a quick reference tool for the
onsite inspector in the event the BMP(s) listed above are deemed ineffective or inappropriate
during construction, the Certified Erosion and Sediment Control Lead will promptly initiate the
P a g e | 7
implementation of one or more of the alternative BMPs listed in Appendix C after the first sign
that existing BMPs are ineffective or failing.
In addition, sediment will be removed from paved areas in and adjacent to construction work
areas manually or using mechanical sweepers, as needed, to minimize tracking of sediments on
vehicle tires away from the site and to minimize washoff of sediments from adjacent streets in
runoff.
Whenever possible, sediment laden water shall be discharged into onsite, relatively level,
vegetated areas (BMP C240 paragraph 5, page 4-102).
2.1.5 Element 5: Stabilize Soils
Exposed and unworked soils shall be stabilized with the application of effective BMPs to prevent
erosion throughout the life of the project. The specific BMPs for soil stabilization that shall be
used on this project include:
o Preserve Natural Vegetation (BMP C101)
o Temporary and Permanent Seeding (BMP C120)
o Mulching (BMP C121)
o Plastic Covering (BMP C123)
o Topsoiling/Composting (BMP C125)
Alternate soil stabilization BMPs are included in Appendix C as a quick reference tool for the
onsite inspector in the event the BMP(s) listed above are deemed ineffective or inappropriate
during construction, the Certified Erosion and Sediment Control Lead will promptly initiate the
implementation of one or more of the alternative BMPs listed in Appendix C after the first sign
that existing BMPs are ineffective or failing.
The project site is located west of the Cascade Mountain Crest. As such, no soils shall remain
exposed and unworked for more than 7 days during the dry season (May 1 to September 30) and
2 days during the wet season (October 1 to April 30). Regardless of the time of year, all soils
shall be stabilized at the end of the shift before a holiday or weekend if needed based on weather
forecasts.
In general, cut and fill slopes will be stabilized as soon as possible and soil stockpiles will be
temporarily covered with plastic sheeting. All stockpiled soils shall be stabilized from erosion,
protected with sediment trapping measures, and where possible, be located away from storm
drain inlets, waterways, and drainage channels.
P a g e | 8
West of the Cascade Mountains Crest
Number of Days Soils Can
Season Dates
be Left Exposed
During the Dry Season May 1 – September 30 7 days
During the Wet Season October 1 – April 30 2 days
Soils must be stabilized at the end of the shift before a holiday or weekend if needed based on
the weather forecast.
Anticipated project dates: Start date: June 2022 End date: October 2023
Will you construct during the wet season?
Yes No
Responsible Staff: Scott Wammack
2.1.6 Element 6: Protect Slopes
All cut and fill slopes will be designed, constructed, and protected in a manner than minimizes
erosion. The following specific BMPs will be used to protect slopes for this project:
o Temporary and Permanent Seeding (BMP C120)
Alternate slope protection BMPs are included in Appendix C as a quick reference tool for the
onsite inspector in the event the BMP(s) listed above are deemed ineffective or inappropriate
during construction, the Certified Erosion and Sediment Control Lead will promptly initiate the
implementation of one or more of the alternative BMPs listed in Appendix C after the first sign
that existing BMPs are ineffective or failing.
Will steep slopes be present at the site during construction?
Yes No
2.1.7 Element 7: Protect Drain Inlets
All storm drain inlets and culverts made operable during construction shall be protected to
prevent unfiltered or untreated water from entering the drainage conveyance system. However,
the first priority is to keep all access roads clean of sediment and keep street wash water separate
from entering storm drains until treatment can be provided. Storm Drain Inlet Protection (BMP
C220) will be implemented for all drainage inlets and culverts that could potentially be impacted
by sediment-laden runoff on and near the project site. The following inlet protection measures
will be applied on this project:
o Storm Drain Inlet Protection (BMP C220).
P a g e | 9
If the BMP options listed above are deemed ineffective or inappropriate during construction, the
Certified Erosion and Sediment Control Lead shall implement one or more of the alternative
BMP inlet protection options listed in Appendix C.
2.1.8 Element 8: Stabilize Channels and Outlets
There are no outlets proposed on site.
2.1.9 Element 9: Control Pollutants
The following pollutants are anticipated to be present on-site:
Table 2 – Pollutants
Pollutant (List pollutants and source, if applicable)
All pollutants, including waste materials and demolition debris, that occur onsite shall be
handled and disposed of in a manner that does not cause contamination of stormwater. Good
housekeeping and preventative measures will be taken to ensure that the site will be kept clean,
well-organized, and free of debris. If required, BMPs to be implemented to control specific
sources of pollutants are discussed below.
The facility does not require a Spill Prevention, Control, and Countermeasure (SPCC) Plan under
the Federal regulations of the Clean Water Act (CWA).
Will maintenance, fueling, and/or repair of heavy equipment and vehicles occur on-site?
Yes No
Will wheel wash or tire bath system BMPs be used during construction?
Yes No
Will pH-modifying sources be present on-site?
Yes No
Table 3 – pH-Modifying Sources
None
Bulk cement
Cement kiln dust
P a g e | 10
Fly ash
Other cementitious materials
New concrete washing or curing waters
Waste streams generated from concrete grinding and sawing
Exposed aggregate processes
Dewatering concrete vaults
Concrete pumping and mixer washout waters
Recycled concrete
Recycled concrete stockpiles
Other (i.e., calcium lignosulfate) [please describe: ]
Concrete trucks must not be washed out onto the ground, or into storm drains, open ditches,
streets, or streams. Excess concrete must not be dumped on-site, except in designated
concrete washout areas with appropriate BMPs installed.
Will uncontaminated water from water-only based shaft drilling for construction of building, road,
and bridge foundations be infiltrated provided the wastewater is managed in a way that prohibits
discharge to surface waters?
Yes No
2.1.10 Element 10: Control Dewatering
There will be no dewatering during the duration of the project.
2.1.11 Element 11: Maintain BMPs
All temporary and permanent Erosion and Sediment Control (ESC) BMPs shall be maintained
and repaired as needed to ensure continued performance of their intended function.
Maintenance and repair shall be conducted in accordance with each particular BMP
specification (see Volume II of the SWMMWW or Chapter 7 of the SWMMEW).
Visual monitoring of all BMPs installed at the site will be conducted at least once every calendar
week and within 24 hours of any stormwater or non-stormwater discharge from the site. If the
site becomes inactive and is temporarily stabilized, the inspection frequency may be reduced to
once every calendar month.
All temporary ESC BMPs shall be removed within 30 days after final site stabilization is
achieved or after the temporary BMPs are no longer needed.
Trapped sediment shall be stabilized on-site or removed. Disturbed soil resulting from removal
of either BMPs or vegetation shall be permanently stabilized.
P a g e | 11
Additionally, protection must be provided for all BMPs installed for the permanent control of
stormwater from sediment and compaction. BMPs that are to remain in place following
completion of construction shall be examined and restored to full operating condition. If
sediment enters these BMPs during construction, the sediment shall be removed and the facility
shall be returned to conditions specified in the construction documents.
P a g e | 12
2.1.12 Element 12: Manage the Project
The project will be managed based on the following principles:
• Projects will be phased to the maximum extent practicable and seasonal work limitations
will be taken into account.
• Inspection and monitoring:
o Inspection, maintenance and repair of all BMPs will occur as needed to ensure
performance of their intended function.
o Site inspections and monitoring will be conducted in accordance with Special
Condition S4 of the CSWGP. Sampling locations are indicated on the Site Map.
Sampling station(s) are located in accordance with applicable requirements of
the CSWGP.
• Maintain an updated SWPPP.
o The SWPPP will be updated, maintained, and implemented in accordance with
Special Conditions S3, S4, and S9 of the CSWGP.
As site work progresses the SWPPP will be modified routinely to reflect changing site
conditions. The SWPPP will be reviewed monthly to ensure the content is current.
Table 5 – Management
Design the project to fit the existing topography, soils, and drainage patterns
Emphasize erosion control rather than sediment control
Minimize the extent and duration of the area exposed
Keep runoff velocities low
Retain sediment on-site
Thoroughly monitor site and maintain all ESC measures
Schedule major earthwork during the dry season
Other (please describe)
P a g e | 13
Table 6 – BMP Implementation Schedule
Phase of Construction Wet/Dry
Stormwater BMPs Date
Project Season
[Insert construction [Insert BMP] [MM/DD/YYYY] [Insert
activity] Season]
2.1.13 Element 13: Protect Low Impact Development (LID) BMPs
Infiltration will be used to meet the LID flow requirements as outlined in the 2012 Department of
Ecology Stormwater Management Manual. Where grading is required, BMP T5.13 Post
Construction Soil Quality and Depth shall be used to return soils to pre-disturbed conditions.
All heavy equipment must be kept off existing soils under LID facilities that have been
excavated to final grade to retain the infiltration rate of the soils.
P a g e | 14
3 Pollution Prevention Team
Table 7 – Team Information
Title Name(s) Phone Number
Certified Erosion and N/A N/A
Sediment Control Lead
(CESCL)
Resident Engineer Kimberly Busteed 360-435-5551
Emergency Ecology Chris Wilson 425-953-3206
Contact
Emergency Permittee/ Scott Wammack 360-435-7171
Owner Contact
Non-Emergency Owner Scott Wammack 360-435-7171
Contact
Monitoring Personnel N/A N/A
Ecology Regional Office Washington Northwest Regional Office 425-649-7000
Note:
CESCL is not required for this project since the area of disturbance is less than 1 acre.
P a g e | 15
4 Monitoring and Sampling Requirements
Monitoring includes visual inspection, sampling for water quality parameters of concern, and
documentation of the inspection and sampling findings in a site log book. A site log book will be
maintained for all on-site construction activities and will include:
• A record of the implementation of the SWPPP and other permit requirements
• Site inspections
• Stormwater sampling data
A Construction Stormwater Site Inspection Form File can be found under Appendix D.
The site log book must be maintained on-site within reasonable access to the site and be made
available upon request to Ecology or the local jurisdiction.
Numeric effluent limits may be required for certain discharges to 303(d) listed waterbodies. See
CSWGP Special Condition S8 and Section 5 of this template.
4.1 Site Inspection
Site inspections are not required for this project.
4.2 Stormwater Quality Sampling
4.2.1 Turbidity Sampling
Sampling is not required for this project.
4.2.2 pH Sampling
pH monitoring is not required for this project.
P a g e | 16
5 Discharges to 303(d) or Total Maximum Daily Load (TMDL)
Waterbodies
5.1 303(d) Listed Waterbodies:
Is the receiving water 303(d) (Category 5) listed for turbidity, fine sediment, phosphorus, or pH?
Yes No
5.2 TMDL Waterbodies
Waste Load Allocation for CWSGP discharges:
N/A
Discharges to TMDL receiving waterbodies will meet in-stream water quality criteria at the point
of discharge.
The Construction Stormwater General Permit Proposed New Discharge to an Impaired Water
Body form is included in Appendix F.
P a g e | 17
6 Reporting and Record Keeping
6.1 Record Keeping
6.1.1 Site Log Book
Site log book is not required for this project.
6.1.2 Records Retention
Records retention is not required for this project.
6.1.3 Updating the SWPPP
The SWPPP will be modified if:
• Found ineffective in eliminating or significantly minimizing pollutants in stormwater
discharges from the site.
• There is a change in design, construction, operation, or maintenance at the construction
site that has, or could have, a significant effect on the discharge of pollutants to waters
of the State.
The SWPPP will be modified within seven (7) days if inspection(s) or investigation(s) determine
additional or modified BMPs are necessary for compliance. An updated timeline for BMP
implementation will be prepared.
6.2 Reporting
6.2.1 Discharge Monitoring Reports
Cumulative soil disturbance is less than one (1) acre; therefore, Discharge Monitoring
Reports (DMRs) will not be submitted to Ecology because water quality sampling is not being
conducted at the site.
P a g e | 18
Appendix/Glossary
A. Site Map
P a g e | 19
B. BMP Detail
The following includes a list of possible alternative BMPs for each of the 12 elements not described
in the main SWPPP text. This list can be referenced in the event a BMP for a specific element is not
functioning as designed and an alternative BMP needs to be implemented.
Element #1 – Mark Clearing Limits
Buffer Zones (BMP C102)
Element #2 – Establish Construction Access
Wheel Wash (BMP C106)
Element #3 - Control Flow Rates
Triangular Silt Dike (BMP C208)
Element #4 – Install Sediment Controls
Straw Wattles (BMP C235)
Element #5 – Stabilize Soils
Sodding (BMP C124)
Surface Roughening (BMP C130)
Element #6 – Protect Slopes
Gradient Terrace (BMP C131)
Element #7 – Protect Drain Inlets
Brush Barrier (BMP C231)
Element #8 – Stabilize Channels and Outlets
Interceptor Dike and Swale (BMP C200)
Element #9 – Control Pollutants
Vegetated Strip (BMP C234)
P a g e | 20
C. Correspondence
Ecology
EPA
Local Government
D. Site Inspection Form
The Construction Stormwater Site Inspection Form is attached, and can also be found at the
following address;
https://ecology.wa.gov/Regulations-Permits/Permits-certifications/Stormwater-general-
permits/Construction-stormwater-permit
P a g e | 21
E. Construction Stormwater General Permit (CSWGP)
Download the CSWGP:
http://www.ecy.wa.gov/programs/wq/stormwater/construction/index.html
F. 303(d) List Waterbodies / TMDL Waterbodies Information
N/A
G. Contaminated Site Information
N/A
H. Engineering Calculations
See Drainage Report
P a g e | 22
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.:
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
DATUM: NAVD 88
CASCADE
SURVEYING &
·
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
LEGEND:
NI E
C
Y
E N
17.67'
21.33' 6' E.
DIVISION STREET
V I
R S
U
8.41'
S
E
D
ACSAC
37.27 FT.
PATH OF FRONT WHEEL
PATH OF REAR WHEEL
PATH OF OVERHANG
90°
C C
C C C C
C C
CENTENNIAL TRAIL
PATH OF OVERHANG
6' 21.33' 17.67'
PATH OF FRONT WHEEL
89°
8.41'
PATH OF REAR WHEEL
N. OLYMPIC AVENUE
37.27 FT.
DATEDATEDATE
37.27 FT.
6'
21.33'
DESIGNEDDRAWNCHECKEDFIELD BOOK
17.67'
8.41'
PATH OF FRONT WHEEL
89°
PATH OF OVERHANG PATH OF REAR WHEEL
CITY FILE NO.:
PAISLEY LOFTS
GRANDVIEW NORTH LLC
TRUCK TURNING RADIUS
CITY OF ARLINGTON
1 OF 1
# 22923
PLANT
SCHEDULE
S.R. 530 DIVISION
STREET
SR 530 - DIVISION ST.
EXISTING LANDSCAPE BED TO BE TREES
CODE QTY BOTANICAL NAME COMMON NAME SIZE
'FRESHENED UP' WITH ALL WEEDS
REMOVE EXISTING PLANT
REMOVED AND ADDITION OF 2" OF
MATERIAL IN THIS AREA. ANY
MULCH SO AS TO BE IN A NEWLY
AME GRA 2 Amelanchier x grandiflora `Autumn Brilliance` Autumn Brilliance Serviceberry 2" Cal.
POT DRO STUMPS TO BE CUT TO BELOW
TREE SPECIES TO BE CONFIRMED WITH INSTALLED CONDITION
GRADE
CITY OF ARLINGTON MASTER STREET
TREE PLAN
PAR PAR 2 Parrotia persica Persian Parrotia 2" Cal.
21'-0" 30'-7"
PYR CLE 5 Pyrus calleryana `Cleveland Select` Chanticleer Callery Pear 2" Cal.
34'-11"
88 sf
88 sf
MAH RE4
ZEL GRE 8 Zelkova serrata `Green Vase` Green Vase Sawleaf Zelkova 2" Cal.
5'-0"
PIE CA2 ILE GGI SHRUBS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
150 sf POL MU2
1961 sf ILE SKY
18'-0" 165 sf POL MU2
HEU B21 NAN LE8 SYR MEY
CHA GRA 1 Chamaecyparis obtusa `Gracilis` Slender Hinoki Cypress 5 gal.
CHA GRA
HEM YH3
CONTRACTOR MAY INSTALL 'TREE
CIS COR 6 Cistus corbariensis White Rockrose 2 gal.
6-FOOT PLANTING PIT
GATOR' OR EQUAL WATERING BAGS
AND MULCH RING
ON ALL TREES. CONFIRM WITH
3095 sf AROUND TREES IN LAWN.
OWNER.
COR KE3 2 Cornus stolonifera `Kelseyi` Kelsey Dogwood 2 gal.
10 DAFFODIL BULBS
13'-8"
AROUND EACH TREE
ILE SKY 3 Ilex crenata `Sky Pencil` Sky Pencil Japanese Holly 5 gal.
C C C C C C
C C
ILE GGI 10 Ilex glabra `Gem Box` Inkberry Holly 2 gal.
15'-7"
CENTENNIAL TRAIL EXISTING LAWN AREA TO HAVE ALL
MAH RE4 13 Mahonia repens Creeping Mahonia 2 gal.
LOW SPOTS LEVELED WITH TOPSOIL,
OLYMPIC AVE.
HAND SEEDED, AND FERTILIZED
OLYMPIC AVENUE
NAN LE8 4 Nandina domestica `Lemon Lime` Lemon Lime Nandina 2 gal.
12'-10" 9'-1"
ONE WAY 161 sf
ONE WAY 9'-7"
PIE CA2 8 Pieris japonica `Cavatine` Lily of the Valley Bush 2 gal.
Hybrid Daylily
POT DRO 9 Potentilla fruticosa 'Gold Drop' Gold Drop Bush Cinquefoil 2 gal.
ZEL GRE
18'-2"
18'-0"
SYR MEY 2 Syringa meyeri 'Palibin' Dwarf Korean Lilac 2 gal.
152 sf
THU EM2 12 Thuja occidentalis `Emerald` Emerald Arborvitae 5` Ht.
CIS COR
PAR PAR
THU EM2
WEI MID 5 Weigela florida `Midnight Wine` TM Weigela 2 gal.
PERENNIALS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
CAR OS2 4 Carex oshimensis `Everoro` Everoro Japanese Sedge 1 gal.
HEM YH3 18 Hemerocallis x Hybrid Daylily 1 gal.
PLANTING PLAN
HEU B21 10 Heuchera x `Black Beauty` Coral Bells 1 gal.
1" = 20'-0" (CHECK SCALE BAR FOR ACCURACY)
OPH BLA 3 Ophiopogon japonicus `Black` Black Mondo Grass 1 gal.
POL MU2 14 Polystichum munitum Western Sword Fern 1 gal.
Landscape Statistics GROUND
COVERS CODE QTY BOTANICAL NAME COMMON NAME SIZE
S.R. 530 DIVISION STREET
TOTAL LANDSCAPE
SR 530 - DIVISION ST.
ARC UVA 83 Arctostaphylos uva-ursi Kinnikinnick 6"
Site 16,949 sf
Onsite Landscape 313 sf 1.88%
SOD/SEED
CODE QTY BOTANICAL NAME COMMON NAME SIZE
2" caliper approved tree
GRA ENM 5,135 sf Low Grow Lawn Seed Mix Locally Proven Overseed of existing Lawn Area seed
STREET FRONTAGE provided per code.
every 30' o.c. required
C C C C C C
C C
PARKING LOT LANDSCAPE 65 STALLS
CENTENNIAL TRAIL
OLYMPIC AVE.
OLYMPIC AVENUE vehicle accommodation area 10,343 SF
ONE WAY
ONE WAY
793 SF COMBINED
shade required (20% VAC) 2,069 SF required 2,491 SF provided
Number of trees required
258 SF TYPICAL
13 required 14 provided
(1 tree / 5 stalls)
VEHICLE ACCOMOMDATION SHADE AREA
NO SCALE
NORTH
one inch
0 20 40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd
Grandview North
eccosDesign
Paisley Lofts; project # 918 HORIZONTAL : 1" = 20'
DRAWING: 2146 site
2 3.16.22 UPDATED per COA comments pd pd
Paisley Lofts
LANDSCAPE PLAN
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273
E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com
Arlington, WA DRAWN: PD
PL-1
CHECKED: PD
GENERAL NOTES
SOIL NOTES
1. ALL WORK SHALL BE PERFORMED
BY PERSONS FAMILIAR WITH THIS KIND OF WORK AND 1. CONTRACTOR MAY STOCKPILE SITE TOPSOIL FOR POSSIBLE RE-USE IN
UNDER THE SUPERVISION
OF A QUALIFIED FOREMAN. LANDSCAPE BEDS. STOCKPILED TOPSOIL TO BE APPROVED BY OWNERS
REPRESENTATIVE. ROAD BASE, GLACIAL TILL, GRAVEL OR CONTAMINATED
2. ALL PLANT MATERIAL
SIZES AND QUALITY TO CONFORM TO AMERICAN ASSOC. OF SOILS ARE NOT ACCEPTABLE AND WILL BE REJECTED.
NURSERYMEN, AMERICAN
STANDARD FOR NURSERY STOCK, MOST RECENT PUBLISHED.
2. SITE TOPSOIL SHALL HAVE ALL ROCKS, GRASS CLODS AND DEBRIS LARGER
3. PLANT LOCATIONS ON
THE PLANS ARE DIAGRAMMATIC AND MAY BE SUBJECT TO THAN 1" WHENEVER VISIBLE ON THE SURFACE
ADJUSTMENT IN THE FIELD
BY THE LANDSCAPE CONTRACTOR.
3. EXISTING SITE TOPSOIL TO BE AMENDED WITH COMPOST AT A RATIO OF 3:1. 3
4. ALL PLANT MATERIAL
SHALL BE OF NURSERY STOCK AND SHALL BE OF THE TYPE, SIZE UNITS OF EXISTING SOIL TO ONE UNIT OF COMPOST. COMPOST TO BE WSDOT
AND CONDITION SPECIFIED.
THE PLANT MATERIAL SHALL EXHIBIT NORMAL HABITS OF CERTIFIED.
GROWTH FOR THE SPECIES,
SHALL HAVE BUDS INTACT AND SHALL BE FREE OF DISEASE,
INSECTS, SCARS, BRUISES,
BREAKS, SEED AND WEED ROOTS. 4. IN LIEU OF AMENDING SITE TOPSOIL CONTRACTORS MAY CHOOSE TO USE
IMPORTED 2-WAY TOPSOIL.
5. SEE NOTES THIS SHEET
FOR TOPSOIL DEPTH AND SPECIFICATION.
5. TOPSOIL DEPTHS
6. MEDIUM BARK MULCH IS
TO BE INSTALLED AT ALL NEW PLANTING AREAS WITH A MINIMUM
OF 2 INCHES.
5.1. TOPSOIL TO BE PLACED AT A MINIMUM OF 9" IN ALL LANDSCAPE BED AREAS
AND INCORPORATED INTO EXISTING SUBGRADE. LIGHTLY TAMP 6" LAYERS
8. ALL LANDSCAPE AREAS
SHALL HAVE PLANTING BACKFILL AMENDED WITH A WETTING OF SOIL BY HAND OR LIGHTLY WITH EXCAVATOR.
AGENT (TERAWET OR EQUAL)
APPLIED AT MANUFACTURES RECOMMENDED RATE.
5.2. TOPSOIL TO BE PLACE AT AT MINIMUM OF 12" IN ALL TREE-PIT AREAS. SEE
9. LANDSCAPE CONTRACTOR
SHALL VERIFY LOCATION OF ALL SITE UTILITIES PRIOR TO DETAIL THIS PAGE.
LANDSCAPE IMPLEMENTATION.
PLANT LOCATIONS MAY BE ADJUSTED TO AVOID CONFLICT.
5.3. TOPSOIL SHALL NOT BE MOVED, MIXED OR PLACE WHILE SATURATED.
10. LANDSCAPE CONTRACTOR
SHALL TAKE NECESSARY PRECAUTIONS TO PROTECT EXISTING
SITE IMPROVEMENTS,
PAVING, WALLS, AND UNDERGROUND UTILITIES. DAMAGE SHALL BE 6. IN ALL INSTANCES, PLACED TOPSOIL TO BE INCOPRPORTED INTO EXISTING
REPAIRED TO THE OWNER'S
SATISFACTION AND AT NO ADDITIONAL COST. GRADE.
11. PLANT COUNT IS FOR THE
CONTRACTOR'S CONVENIENCE; IF THERE IS A DISCREPANCY,
THE PLAN SHALL GOVERN.
ACTUAL PLANT QUANTITIES TO BE DETERMINED BY REQUIRED
PLANT SPACING.
12. ALL AREAS TO BE PLANTED
WITH GROUNDCOVER ARE INDICATED ON THE PLAN WITH A
HATCH PATTERN. SEE
PLANT LIST FOR PLANT TYPE, SIZE, AND SPACING.
13. SUBSTITUTION OF PLANT
VARIETIES DUE TO LACK OF AVAILABILITY SUBJECT TO
APPROVAL BY THE OWNERS
REPRESENTATIVE AND CITY.
MAINTENANCE NOTES -
14. ALL DIMENSIONS ARE ASSUMED
TO BE PARALLEL OR PERPENDICULAR UNLESS
1 COA TREE IN 4X4 GRATE DETAIL
2 COA TREE PLANTING DETAIL OTHERWISE NOTED.
1. UNDER NO CIRCUMSTANCE ARE STREET TREES TO BE TOPPED OR PRUNED
L-2 NO SCALE
L-2 NO SCALE 15. ALL SOIL GRADES TO BE
A MINIMUM SIX INCHES BELOW ADJACENT FINISH FLOOR WITHOUT PERMISSION OF THE CITY ARBORIST.
ELEVATIONS UNLESS NOTED
OTHERWISE ALL GRADES ADJACENT TO A BUILDING SHALL
HAVE A MAXIMUM SLOPE
OF 5% 3' FROM FOUNDATION. 2. UNDER NO CIRCUMSTANCE ARE SHRUBS TO BE SHEARED OR SHAPED
WITHOUT EXPLICIT PERMISSION FROM THE OWNER. SHRUBS ARE DESIGNED
16. ALL FINISH GRADES TO
BE FLUSH WITH ADJACENT SURFACES, SUCH AS TOP OF CURB. TO FILL AND GROW IN TO A PERMANENT MATURE SIZE.
17. ALL GRADES, DIMENSIONS
AND EXISTING CONDITIONS SHALL BE VERIFIED BY THE 3. GROUNDCOVER THAT GROWS 'OUT' OF BEDS AND INTO ADJACENT WALKS OR
CONTRACTOR PRIOR TO
CONSTRUCTION. ANY DISCREPANCIES SHALL BE BROUGHT TO ROADS ARE TO BE CUT-BACK AS NEEDED.
GROUNDCOVER PLANT.
THE ATTENTION OF THE
LANDSCAPE ARCHITECT.
CUTBACK, PULL OUT AND DISTURB ALL
SEE PLANT LIST
4. PERENNIAL AND GRASSES WHICH ARE DECIDUOUS MAY BE CUT BACK AT
CIRCLING ROOTS FROM ANY CONTAINER 1. PLANT SHRUB 1/2"
HIGHER THAN DEPTH
GROWN PLANTS BARK MULCH GROWN AT NURSERY.
18. SUPPLEMENTAL HAND WATERING
TO BE DONE DURING FIRST TWO YEARS TO GUARANTEE OWNERS DISCRETION, ONCE PER YEAR, DURING THE MONTHS OF FEBRUARY,
2. FERTILIZE ALL
PLANTS WITH APPROVED PLANT ESTABLISHMENT.
IF CITY REQUIRES AUTOMATED IRRIGATION SYSTEM THEN MARCH OR APRIL.
STARTER FERTILIZER
APPLIED AT BIDDER DESIGNED SYSTEM WILL
BE PROVIDED.
MANUFACTURER'S
SUGGESTED RATES
5. LAWN TO BE FERTILIZED ONCE PER YEAR MIN PER PRODUCT INSTRUCTIONS.
TOPSOIL DEPTH AND 3. SCARIFY ROOTBALL
OF
TYPE AS SPECIFIED CONTAINER-GROWN
PLANTS. PRIOR TO 19. BASEMAP PROVIDED BY ENGINEERS,
CASCADE SURVEYING AND ENGINEERING, INC,
BACKFILLING
360-435-5551
6. WEEDS TO BE REMOVED IN A TIMELY MANNER BY MECHANICAL OR CHEMICAL
EXISTING
MEANS, IN COMPLIANCE WITH ALL LOCAL AND STATE GUIDELINES AND
SECTION SUBGRADE
REQUIREMENTS.
2" DEPTH BARK MULCH
7. BARK MULCH IN PLANTER BEDS TO BE TOPPED OFF WITH 1" LIFT MIN, ONCE
4" WATERING BASIN
PER YEAR IN THE SPRING.
SURROUNDING PLANT
GROUNDCOVER PLANT
EQUAL
FINISH GRADE
SPACING AS INDICATED
DISTANCE
ON PLANT LIST (TYPICAL)
COMPLETELY REMOVE ALL
DISTANCE
EDGE OF PLANTER
BURLAP, GROWBAG, STRING
EQUAL
AND FOREIGN MATERIALS
60
FROM THE ROOT BALL.
EQUAL
DISTANCE
PLANTING BACKFILL
1/2 DISTANCE
SCARIFY PLANTING PIT WALLS
PLAN
EXISTING SUBGRADE
2 TIMES
SET ROOTBALL ON MOUND OF
ROOTBALL
DIA.
COMPACTED PLANTING BACKFILL MIX
3 TYPICAL PLANTING DETAILS
L-2 NO SCALE
NORTH
one inch
0 20
40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd Grandview North
eccosDesign Paisley Lofts; project
# 918 HORIZONTAL : 1" = 20' DRAWING:
2146 site
2 3.16.22 UPDATED per COA comments pd pd Paisley Lofts
LANDSCAPE DETAILS
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273 E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com Arlington, WA
DRAWN: PD AND NOTES
L-2
CHECKED: PD
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 6/8/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 1 Report Date: 6/8/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
1. NEH Put detail for dumpster on civil plans. (there have Dumpster detail is added to sheet C 3.2
been issues with civil contractors building the
dumpster enclosure and not following standards)
2. NEH Include information about sidewalk restoration along The two water services on Olympic are now
N Olympic at meter changes, etc. identified on sheet C 5.0 to be decommissioned
at the main with pavement, curb, gutter and
sidewalk restoration
3. NEH Need Pedestrian Plan for construction. Notes have been added to the SWPPP sheet to
state that the existing asphalt sidewalk is to
remain in place until the proposed sidewalk is
constructed. Pedestrians will be redirected to
the north side of Division St. at the intersections
of Olympic Ave and Centennial Trail.
4. NEH Need to have full curb between parking and building A full curb is now located between the parking
sidewalk (south and west) and building on the south side. Grading and
details are updated to reflect this. The west
parking already had a full curb.
5. NEH Need construction easement from Snohomish County City of Arlington has an interlocal agreement
for trail parking area. with Snohomish County which gives the city
control and maintenance responsibility.
6. NEH Drainage trench A needs to be on owner property, not Trench A is split into three trenches, Trench
city property. A,D, and E. Trench A will mitigate runoff from
Centennial Alley. Trench D will mitigate runoff
from the courtyard portion of the building and
upper portion of the parking (30% onsite
impervious). The remaining 70% impervious
will be mitigated through Trench E.
Page 1 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 6/8/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 1 Report Date: 6/8/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
7. NEH Demolition permit required, must alert Public Works A note is added to the cover sheet that a
when the water and sewer are to be disconnected. demolition permit is required. Public Works is
to be notified when water and sewer are to be
disconnected.
8. NEH This property has one water credit, all others are new. Acknowledged – no action required.
9. NEH Please demonstrate that each commercial unit has All commercial units will be accessible from the
ADA accessible entry. ADA parking stalls. The sidewalk is less than 2%
at the building entrances with an 8% ADA
compliant ramp between the building
entrances. This will provide ADA access to all
commercial units.
10. NEH Signage for the one way A ‘One way Do not enter sign is now located at
the dumpster area and is called out on the sheet
C 3.0 with a detail on sheet C 3.2.
11. BG The site plan does not include removing the overhead The note about relocating the power pole on
lines from the existing book store going south to the Division St is revised to include removing the
pole on the west side of the post office. overhead power lines onsite. See sheet C 2.0
12. BG One way striping is shown on the site plan, but no one A ‘One way Do not enter sign is now located at
way/do not enter signing is shown. the dumpster area and is called out on the sheet
C 3.0 with a detail on sheet C 3.2.
13. BG Show saw cuts required in Olympic and division for Saw cuts are shown on the SWPPP.
water line work, and new driveways.
14. BG The elevation on division drops as you move west from A detail is added to sheet C 7.0 to better show
Olympic. There should be a wall between the building the building along Division Street. The sidewalk
and the wall on the west end of the building, but it is and landscape strip will slope up from the road
not shown in any of the plans. at 2% to the buildings brick façade. The height
between the landscaping and buildings finished
floor will vary across the length of building.
Page 2 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 6/8/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 1 Report Date: 6/8/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
15. RM Install 6" cleanout at building on side sewer to Saddle SSCO #4 is now shown on the plans 5 ft off the
SSMH #1. building.
16. GT The two services on Olympic are not W-50 and are The two water services on Olympic are now
required to be decommissioned at the main. identified on sheet C 5.0 to be decommissioned
at the main with pavement, curb, gutter and
sidewalk restoration
17. RJ Please resubmit (2) two hard copies of all required
documents and submit electronic files to
ced@arlingtonwa.gov.
18.
19.
20.
Page 3 of 3
PLANT
SCHEDULE
S.R. 530 DIVISION
STREET
SR 530 - DIVISION ST.
EXISTING LANDSCAPE BED TO BE TREES
CODE QTY BOTANICAL NAME COMMON NAME SIZE
'FRESHENED UP' WITH ALL WEEDS
REMOVE EXISTING PLANT
REMOVED AND ADDITION OF 2" OF
MATERIAL IN THIS AREA. ANY
MULCH SO AS TO BE IN A NEWLY
AME GRA 2 Amelanchier x grandiflora `Autumn Brilliance` Autumn Brilliance Serviceberry 2" Cal.
POT DRO STUMPS TO BE CUT TO BELOW
TREE SPECIES TO BE CONFIRMED WITH INSTALLED CONDITION
GRADE
CITY OF ARLINGTON MASTER STREET
TREE PLAN
PAR PAR 2 Parrotia persica Persian Parrotia 2" Cal.
21'-0" 30'-7"
PYR CLE 5 Pyrus calleryana `Cleveland Select` Chanticleer Callery Pear 2" Cal.
34'-11"
88 sf
88 sf
MAH RE4
ZEL GRE 8 Zelkova serrata `Green Vase` Green Vase Sawleaf Zelkova 2" Cal.
5'-0"
PIE CA2 ILE GGI SHRUBS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
150 sf POL MU2
1961 sf ILE SKY
18'-0" 165 sf POL MU2
HEU B21 NAN LE8 SYR MEY
CHA GRA 1 Chamaecyparis obtusa `Gracilis` Slender Hinoki Cypress 5 gal.
CHA GRA
HEM YH3
CONTRACTOR MAY INSTALL 'TREE
CIS COR 6 Cistus corbariensis White Rockrose 2 gal.
6-FOOT PLANTING PIT
GATOR' OR EQUAL WATERING BAGS
AND MULCH RING
ON ALL TREES. CONFIRM WITH
3095 sf AROUND TREES IN LAWN.
OWNER.
COR KE3 2 Cornus stolonifera `Kelseyi` Kelsey Dogwood 2 gal.
10 DAFFODIL BULBS
13'-8"
AROUND EACH TREE
ILE SKY 3 Ilex crenata `Sky Pencil` Sky Pencil Japanese Holly 5 gal.
C C C C C C
C C
ILE GGI 10 Ilex glabra `Gem Box` Inkberry Holly 2 gal.
15'-7"
CENTENNIAL TRAIL EXISTING LAWN AREA TO HAVE ALL
MAH RE4 13 Mahonia repens Creeping Mahonia 2 gal.
LOW SPOTS LEVELED WITH TOPSOIL,
OLYMPIC AVE.
HAND SEEDED, AND FERTILIZED
OLYMPIC AVENUE
NAN LE8 4 Nandina domestica `Lemon Lime` Lemon Lime Nandina 2 gal.
12'-10" 9'-1"
ONE WAY 161 sf
ONE WAY 9'-7"
PIE CA2 8 Pieris japonica `Cavatine` Lily of the Valley Bush 2 gal.
Hybrid Daylily
POT DRO 9 Potentilla fruticosa 'Gold Drop' Gold Drop Bush Cinquefoil 2 gal.
ZEL GRE
18'-2"
18'-0"
SYR MEY 2 Syringa meyeri 'Palibin' Dwarf Korean Lilac 2 gal.
152 sf
THU EM2 12 Thuja occidentalis `Emerald` Emerald Arborvitae 5` Ht.
CIS COR
PAR PAR
THU EM2
WEI MID 5 Weigela florida `Midnight Wine` TM Weigela 2 gal.
PERENNIALS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
CAR OS2 4 Carex oshimensis `Everoro` Everoro Japanese Sedge 1 gal.
HEM YH3 18 Hemerocallis x Hybrid Daylily 1 gal.
PLANTING PLAN
HEU B21 10 Heuchera x `Black Beauty` Coral Bells 1 gal.
1" = 20'-0" (CHECK SCALE BAR FOR ACCURACY)
OPH BLA 3 Ophiopogon japonicus `Black` Black Mondo Grass 1 gal.
POL MU2 14 Polystichum munitum Western Sword Fern 1 gal.
Landscape Statistics GROUND
COVERS CODE QTY BOTANICAL NAME COMMON NAME SIZE
S.R. 530 DIVISION STREET
TOTAL LANDSCAPE
SR 530 - DIVISION ST.
ARC UVA 83 Arctostaphylos uva-ursi Kinnikinnick 6"
Site 16,949 sf
Onsite Landscape 313 sf 1.88%
SOD/SEED
CODE QTY BOTANICAL NAME COMMON NAME SIZE
2" caliper approved tree
GRA ENM 5,135 sf Low Grow Lawn Seed Mix Locally Proven Overseed of existing Lawn Area seed
STREET FRONTAGE provided per code.
every 30' o.c. required
C C C C C C
C C
PARKING LOT LANDSCAPE 65 STALLS
CENTENNIAL TRAIL
OLYMPIC AVE.
OLYMPIC AVENUE vehicle accommodation area 10,343 SF
ONE WAY
ONE WAY
793 SF COMBINED
shade required (20% VAC) 2,069 SF required 2,491 SF provided
Number of trees required
258 SF TYPICAL
13 required 14 provided
(1 tree / 5 stalls)
VEHICLE ACCOMOMDATION SHADE AREA
NO SCALE
NORTH
one inch
0 20 40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd
Grandview North
eccosDesign
Paisley Lofts; project # 918 HORIZONTAL : 1" = 20'
DRAWING: 2146 site
2 3.16.22 UPDATED per COA comments pd pd
Paisley Lofts
LANDSCAPE PLAN
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273
E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com
Arlington, WA DRAWN: PD
PL-1
CHECKED: PD
GENERAL NOTES
SOIL NOTES
1. ALL WORK SHALL BE PERFORMED
BY PERSONS FAMILIAR WITH THIS KIND OF WORK AND 1. CONTRACTOR MAY STOCKPILE SITE TOPSOIL FOR POSSIBLE RE-USE IN
UNDER THE SUPERVISION
OF A QUALIFIED FOREMAN. LANDSCAPE BEDS. STOCKPILED TOPSOIL TO BE APPROVED BY OWNERS
REPRESENTATIVE. ROAD BASE, GLACIAL TILL, GRAVEL OR CONTAMINATED
2. ALL PLANT MATERIAL
SIZES AND QUALITY TO CONFORM TO AMERICAN ASSOC. OF SOILS ARE NOT ACCEPTABLE AND WILL BE REJECTED.
NURSERYMEN, AMERICAN
STANDARD FOR NURSERY STOCK, MOST RECENT PUBLISHED.
2. SITE TOPSOIL SHALL HAVE ALL ROCKS, GRASS CLODS AND DEBRIS LARGER
3. PLANT LOCATIONS ON
THE PLANS ARE DIAGRAMMATIC AND MAY BE SUBJECT TO THAN 1" WHENEVER VISIBLE ON THE SURFACE
ADJUSTMENT IN THE FIELD
BY THE LANDSCAPE CONTRACTOR.
3. EXISTING SITE TOPSOIL TO BE AMENDED WITH COMPOST AT A RATIO OF 3:1. 3
4. ALL PLANT MATERIAL
SHALL BE OF NURSERY STOCK AND SHALL BE OF THE TYPE, SIZE UNITS OF EXISTING SOIL TO ONE UNIT OF COMPOST. COMPOST TO BE WSDOT
AND CONDITION SPECIFIED.
THE PLANT MATERIAL SHALL EXHIBIT NORMAL HABITS OF CERTIFIED.
GROWTH FOR THE SPECIES,
SHALL HAVE BUDS INTACT AND SHALL BE FREE OF DISEASE,
INSECTS, SCARS, BRUISES,
BREAKS, SEED AND WEED ROOTS. 4. IN LIEU OF AMENDING SITE TOPSOIL CONTRACTORS MAY CHOOSE TO USE
IMPORTED 2-WAY TOPSOIL.
5. SEE NOTES THIS SHEET
FOR TOPSOIL DEPTH AND SPECIFICATION.
5. TOPSOIL DEPTHS
6. MEDIUM BARK MULCH IS
TO BE INSTALLED AT ALL NEW PLANTING AREAS WITH A MINIMUM
OF 2 INCHES.
5.1. TOPSOIL TO BE PLACED AT A MINIMUM OF 9" IN ALL LANDSCAPE BED AREAS
AND INCORPORATED INTO EXISTING SUBGRADE. LIGHTLY TAMP 6" LAYERS
8. ALL LANDSCAPE AREAS
SHALL HAVE PLANTING BACKFILL AMENDED WITH A WETTING OF SOIL BY HAND OR LIGHTLY WITH EXCAVATOR.
AGENT (TERAWET OR EQUAL)
APPLIED AT MANUFACTURES RECOMMENDED RATE.
5.2. TOPSOIL TO BE PLACE AT AT MINIMUM OF 12" IN ALL TREE-PIT AREAS. SEE
9. LANDSCAPE CONTRACTOR
SHALL VERIFY LOCATION OF ALL SITE UTILITIES PRIOR TO DETAIL THIS PAGE.
LANDSCAPE IMPLEMENTATION.
PLANT LOCATIONS MAY BE ADJUSTED TO AVOID CONFLICT.
5.3. TOPSOIL SHALL NOT BE MOVED, MIXED OR PLACE WHILE SATURATED.
10. LANDSCAPE CONTRACTOR
SHALL TAKE NECESSARY PRECAUTIONS TO PROTECT EXISTING
SITE IMPROVEMENTS,
PAVING, WALLS, AND UNDERGROUND UTILITIES. DAMAGE SHALL BE 6. IN ALL INSTANCES, PLACED TOPSOIL TO BE INCOPRPORTED INTO EXISTING
REPAIRED TO THE OWNER'S
SATISFACTION AND AT NO ADDITIONAL COST. GRADE.
11. PLANT COUNT IS FOR THE
CONTRACTOR'S CONVENIENCE; IF THERE IS A DISCREPANCY,
THE PLAN SHALL GOVERN.
ACTUAL PLANT QUANTITIES TO BE DETERMINED BY REQUIRED
PLANT SPACING.
12. ALL AREAS TO BE PLANTED
WITH GROUNDCOVER ARE INDICATED ON THE PLAN WITH A
HATCH PATTERN. SEE
PLANT LIST FOR PLANT TYPE, SIZE, AND SPACING.
13. SUBSTITUTION OF PLANT
VARIETIES DUE TO LACK OF AVAILABILITY SUBJECT TO
APPROVAL BY THE OWNERS
REPRESENTATIVE AND CITY.
MAINTENANCE NOTES -
14. ALL DIMENSIONS ARE ASSUMED
TO BE PARALLEL OR PERPENDICULAR UNLESS
1 COA TREE IN 4X4 GRATE DETAIL
2 COA TREE PLANTING DETAIL OTHERWISE NOTED.
1. UNDER NO CIRCUMSTANCE ARE STREET TREES TO BE TOPPED OR PRUNED
L-2 NO SCALE
L-2 NO SCALE 15. ALL SOIL GRADES TO BE
A MINIMUM SIX INCHES BELOW ADJACENT FINISH FLOOR WITHOUT PERMISSION OF THE CITY ARBORIST.
ELEVATIONS UNLESS NOTED
OTHERWISE ALL GRADES ADJACENT TO A BUILDING SHALL
HAVE A MAXIMUM SLOPE
OF 5% 3' FROM FOUNDATION. 2. UNDER NO CIRCUMSTANCE ARE SHRUBS TO BE SHEARED OR SHAPED
WITHOUT EXPLICIT PERMISSION FROM THE OWNER. SHRUBS ARE DESIGNED
16. ALL FINISH GRADES TO
BE FLUSH WITH ADJACENT SURFACES, SUCH AS TOP OF CURB. TO FILL AND GROW IN TO A PERMANENT MATURE SIZE.
17. ALL GRADES, DIMENSIONS
AND EXISTING CONDITIONS SHALL BE VERIFIED BY THE 3. GROUNDCOVER THAT GROWS 'OUT' OF BEDS AND INTO ADJACENT WALKS OR
CONTRACTOR PRIOR TO
CONSTRUCTION. ANY DISCREPANCIES SHALL BE BROUGHT TO ROADS ARE TO BE CUT-BACK AS NEEDED.
GROUNDCOVER PLANT.
THE ATTENTION OF THE
LANDSCAPE ARCHITECT.
CUTBACK, PULL OUT AND DISTURB ALL
SEE PLANT LIST
4. PERENNIAL AND GRASSES WHICH ARE DECIDUOUS MAY BE CUT BACK AT
CIRCLING ROOTS FROM ANY CONTAINER 1. PLANT SHRUB 1/2"
HIGHER THAN DEPTH
GROWN PLANTS BARK MULCH GROWN AT NURSERY.
18. SUPPLEMENTAL HAND WATERING
TO BE DONE DURING FIRST TWO YEARS TO GUARANTEE OWNERS DISCRETION, ONCE PER YEAR, DURING THE MONTHS OF FEBRUARY,
2. FERTILIZE ALL
PLANTS WITH APPROVED PLANT ESTABLISHMENT.
IF CITY REQUIRES AUTOMATED IRRIGATION SYSTEM THEN MARCH OR APRIL.
STARTER FERTILIZER
APPLIED AT BIDDER DESIGNED SYSTEM WILL
BE PROVIDED.
MANUFACTURER'S
SUGGESTED RATES
5. LAWN TO BE FERTILIZED ONCE PER YEAR MIN PER PRODUCT INSTRUCTIONS.
TOPSOIL DEPTH AND 3. SCARIFY ROOTBALL
OF
TYPE AS SPECIFIED CONTAINER-GROWN
PLANTS. PRIOR TO 19. BASEMAP PROVIDED BY ENGINEERS,
CASCADE SURVEYING AND ENGINEERING, INC,
BACKFILLING
360-435-5551
6. WEEDS TO BE REMOVED IN A TIMELY MANNER BY MECHANICAL OR CHEMICAL
EXISTING
MEANS, IN COMPLIANCE WITH ALL LOCAL AND STATE GUIDELINES AND
SECTION SUBGRADE
REQUIREMENTS.
2" DEPTH BARK MULCH
7. BARK MULCH IN PLANTER BEDS TO BE TOPPED OFF WITH 1" LIFT MIN, ONCE
4" WATERING BASIN
PER YEAR IN THE SPRING.
SURROUNDING PLANT
GROUNDCOVER PLANT
EQUAL
FINISH GRADE
SPACING AS INDICATED
DISTANCE
ON PLANT LIST (TYPICAL)
COMPLETELY REMOVE ALL
DISTANCE
EDGE OF PLANTER
BURLAP, GROWBAG, STRING
EQUAL
AND FOREIGN MATERIALS
60
FROM THE ROOT BALL.
EQUAL
DISTANCE
PLANTING BACKFILL
1/2 DISTANCE
SCARIFY PLANTING PIT WALLS
PLAN
EXISTING SUBGRADE
2 TIMES
SET ROOTBALL ON MOUND OF
ROOTBALL
DIA.
COMPACTED PLANTING BACKFILL MIX
3 TYPICAL PLANTING DETAILS
L-2 NO SCALE
NORTH
one inch
0 20
40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd Grandview North
eccosDesign Paisley Lofts; project
# 918 HORIZONTAL : 1" = 20' DRAWING:
2146 site
2 3.16.22 UPDATED per COA comments pd pd Paisley Lofts
LANDSCAPE DETAILS
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273 E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com Arlington, WA
DRAWN: PD AND NOTES
L-2
CHECKED: PD
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 7/26/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 2 Report Date: 7/26/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
1. NEH Put detail for dumpster on civil plans. (there have Dumpster detail is added to sheet C 3.2 7/25/2022
been issues with civil contractors building the MH
dumpster enclosure and not following standards)
2. NEH Include information about sidewalk restoration along The two water services on Olympic are now 7/25/2022
N Olympic at meter changes, etc. identified on sheet C 5.0 to be decommissioned MH
at the main with pavement, curb, gutter and
sidewalk restoration
3. NEH Need Pedestrian Plan for construction. Notes have been added to the SWPPP sheet to 7/25/2022
state that the existing asphalt sidewalk is to MH
remain in place until the proposed sidewalk is
constructed. Pedestrians will be redirected to
the north side of Division St. at the intersections
of Olympic Ave and Centennial Trail.
4. NEH Need to have full curb between parking and building A full curb is now located between the parking 7/25/2022
sidewalk (south and west) and building on the south side. Grading and MH
details are updated to reflect this. The west
parking already had a full curb.
5. NEH Need construction easement from Snohomish County City of Arlington has an interlocal agreement 7/25/2022
for trail parking area. with Snohomish County which gives the city MH
control and maintenance responsibility.
6. NEH Drainage trench A needs to be on owner property, not Trench A is split into three trenches, Trench 7/25/2022
city property. A,D, and E. Trench A will mitigate runoff from MH
Centennial Alley. Trench D will mitigate runoff
from the courtyard portion of the building and
upper portion of the parking (30% onsite
impervious). The remaining 70% impervious
will be mitigated through Trench E.
Page 1 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 6/8/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 1 Report Date: 6/8/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
7. NEH Demolition permit required, must alert Public Works A note is added to the cover sheet that a 7/25/2022
when the water and sewer are to be disconnected. demolition permit is required. Public Works is MH
to be notified when water and sewer are to be
disconnected.
8. NEH This property has one water credit, all others are new. Acknowledged – no action required. 7/25/2022
MH
9. NEH Please demonstrate that each commercial unit has All commercial units will be accessible from the
ADA accessible entry. ADA parking stalls. There are level landings at
the building entrances with a 7.88% ADA
compliant ramp between the landings. This will
provide ADA access to all commercial units.
10. NEH Signage for the one way A ‘One way Do not enter sign is now located at 7/25/2022
the dumpster area and is called out on the sheet MH
C 3.0 with a detail on sheet C 3.2.
11. BG The site plan does not include removing the overhead The note about relocating the power pole on 7/25/2022
lines from the existing book store going south to the Division St is revised to include removing the MH
pole on the west side of the post office. overhead power lines onsite. See sheet C 2.0
12. BG One way striping is shown on the site plan, but no one A ‘One way Do not enter sign is now located at 7/25/2022
way/do not enter signing is shown. the dumpster area and is called out on the sheet MH
C 3.0 with a detail on sheet C 3.2.
13. BG Show saw cuts required in Olympic and division for Saw cuts are shown on the SWPPP. 7/25/2022
water line work, and new driveways. MH
14. BG The elevation on division drops as you move west from A detail is added to sheet C 7.0 to better show 7/25/2022
Olympic. There should be a wall between the building the building along Division Street. The sidewalk MH
and the wall on the west end of the building, but it is and landscape strip will slope up from the road
not shown in any of the plans. at 2% to the buildings brick façade. The height
between the landscaping and buildings finished
floor will vary across the length of building.
Page 2 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 7/26/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 2 Report Date: 7/26/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
15. RM Install 6" cleanout at building on side sewer to Saddle SSCO #4 is now shown on the plans 5 ft off the 7/25/2022
SSMH #1. building. MH
16. GT The two services on Olympic are not W-50 and are The two water services on Olympic are now 7/25/2022
required to be decommissioned at the main. identified on sheet C 5.0 to be decommissioned MH
at the main with pavement, curb, gutter and
sidewalk restoration
17. MH C2.0 Relocate construction entrance to west side of project Construction entrance is relocated to access from the
to access off alley and not Olympic Ave alley.
18. MH Install silt fence along Olympic Ave and Division St. Silt fence is now shown along the back of sidewalks
frontage. Provide wattles along Division when silt fence is along Olympic Ave and Division St. Wattle is located
disturbed along Division.
19. MH C3.0 Remove existing curb at full joint and pour new curb The note on sheet C 3.0 is revised to state the curb
integral to existing. Batt joint not allowed and gutter is to be connected at nearest full joint and
that no butt joints are permitted.
20. MH C7.0 "Back-In Parking Only" signs to be installed by developer Back in parking only signs are now shown on the
@ 40' spacing plan at 40 ft spacing and the note is updated to 40’
sign spacing.
21. RM C5.0 Both services, Commercial and Residential, on Division Commercial service meter note is revised to be a 2â€
shall be 2" per COA Standard Detail W-050. service.
22. RJ Civil Review Fees Due: $16,824.14 Civil Review Fees are submitted with this
A link for payment has been sent to gv@grandviewinc.net resubmittal.
23. RJ Please resubmit (2) two hard copies of all required Two hard copies and electronic copies are
documents and submit electronic files to resubmitted
ced@arlingtonwa.gov.
Page 3 of 3
PLANT
SCHEDULE
S.R. 530 DIVISION
STREET
SR 530 - DIVISION ST.
EXISTING LANDSCAPE BED TO BE TREES
CODE QTY BOTANICAL NAME COMMON NAME SIZE
'FRESHENED UP' WITH ALL WEEDS
REMOVE EXISTING PLANT
REMOVED AND ADDITION OF 2" OF
MATERIAL IN THIS AREA. ANY
MULCH SO AS TO BE IN A NEWLY
AME GRA 2 Amelanchier x grandiflora `Autumn Brilliance` Autumn Brilliance Serviceberry 2" Cal.
POT DRO STUMPS TO BE CUT TO BELOW
TREE SPECIES TO BE CONFIRMED WITH INSTALLED CONDITION
GRADE
CITY OF ARLINGTON MASTER STREET
TREE PLAN
PAR PAR 2 Parrotia persica Persian Parrotia 2" Cal.
21'-0" 30'-7"
PYR CLE 5 Pyrus calleryana `Cleveland Select` Chanticleer Callery Pear 2" Cal.
34'-11"
88 sf
88 sf
MAH RE4
ZEL GRE 8 Zelkova serrata `Green Vase` Green Vase Sawleaf Zelkova 2" Cal.
5'-0"
PIE CA2 ILE GGI SHRUBS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
150 sf POL MU2
1961 sf ILE SKY
18'-0" 165 sf POL MU2
HEU B21 NAN LE8 SYR MEY
CHA GRA 1 Chamaecyparis obtusa `Gracilis` Slender Hinoki Cypress 5 gal.
CHA GRA
HEM YH3
CONTRACTOR MAY INSTALL 'TREE
CIS COR 6 Cistus corbariensis White Rockrose 2 gal.
6-FOOT PLANTING PIT
GATOR' OR EQUAL WATERING BAGS
AND MULCH RING
ON ALL TREES. CONFIRM WITH
3095 sf AROUND TREES IN LAWN.
OWNER.
COR KE3 2 Cornus stolonifera `Kelseyi` Kelsey Dogwood 2 gal.
10 DAFFODIL BULBS
13'-8"
AROUND EACH TREE
ILE SKY 3 Ilex crenata `Sky Pencil` Sky Pencil Japanese Holly 5 gal.
C C C C C C
C C
ILE GGI 10 Ilex glabra `Gem Box` Inkberry Holly 2 gal.
15'-7"
CENTENNIAL TRAIL EXISTING LAWN AREA TO HAVE ALL
MAH RE4 13 Mahonia repens Creeping Mahonia 2 gal.
LOW SPOTS LEVELED WITH TOPSOIL,
OLYMPIC AVE.
HAND SEEDED, AND FERTILIZED
OLYMPIC AVENUE
NAN LE8 4 Nandina domestica `Lemon Lime` Lemon Lime Nandina 2 gal.
12'-10" 9'-1"
ONE WAY 161 sf
ONE WAY 9'-7"
PIE CA2 8 Pieris japonica `Cavatine` Lily of the Valley Bush 2 gal.
Hybrid Daylily
POT DRO 9 Potentilla fruticosa 'Gold Drop' Gold Drop Bush Cinquefoil 2 gal.
ZEL GRE
18'-2"
18'-0"
SYR MEY 2 Syringa meyeri 'Palibin' Dwarf Korean Lilac 2 gal.
152 sf
THU EM2 12 Thuja occidentalis `Emerald` Emerald Arborvitae 5` Ht.
CIS COR
PAR PAR
THU EM2
WEI MID 5 Weigela florida `Midnight Wine` TM Weigela 2 gal.
PERENNIALS
CODE QTY BOTANICAL NAME COMMON NAME SIZE
CAR OS2 4 Carex oshimensis `Everoro` Everoro Japanese Sedge 1 gal.
HEM YH3 18 Hemerocallis x Hybrid Daylily 1 gal.
PLANTING PLAN
HEU B21 10 Heuchera x `Black Beauty` Coral Bells 1 gal.
1" = 20'-0" (CHECK SCALE BAR FOR ACCURACY)
OPH BLA 3 Ophiopogon japonicus `Black` Black Mondo Grass 1 gal.
POL MU2 14 Polystichum munitum Western Sword Fern 1 gal.
Landscape Statistics GROUND
COVERS CODE QTY BOTANICAL NAME COMMON NAME SIZE
S.R. 530 DIVISION STREET
TOTAL LANDSCAPE
SR 530 - DIVISION ST.
ARC UVA 83 Arctostaphylos uva-ursi Kinnikinnick 6"
Site 16,949 sf
Onsite Landscape 313 sf 1.88%
SOD/SEED
CODE QTY BOTANICAL NAME COMMON NAME SIZE
2" caliper approved tree
GRA ENM 5,135 sf Low Grow Lawn Seed Mix Locally Proven Overseed of existing Lawn Area seed
STREET FRONTAGE provided per code.
every 30' o.c. required
C C C C C C
C C
PARKING LOT LANDSCAPE 65 STALLS
CENTENNIAL TRAIL
OLYMPIC AVE.
OLYMPIC AVENUE vehicle accommodation area 10,343 SF
ONE WAY
ONE WAY
793 SF COMBINED
shade required (20% VAC) 2,069 SF required 2,491 SF provided
Number of trees required
258 SF TYPICAL
13 required 14 provided
(1 tree / 5 stalls)
VEHICLE ACCOMOMDATION SHADE AREA
NO SCALE
NORTH
one inch
0 20 40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd
Grandview North
eccosDesign
Paisley Lofts; project # 918 HORIZONTAL : 1" = 20'
DRAWING: 2146 site
2 3.16.22 UPDATED per COA comments pd pd
Paisley Lofts
LANDSCAPE PLAN
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273
E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com
Arlington, WA DRAWN: PD
PL-1
CHECKED: PD
GENERAL NOTES
SOIL NOTES
1. ALL WORK SHALL BE PERFORMED
BY PERSONS FAMILIAR WITH THIS KIND OF WORK AND 1. CONTRACTOR MAY STOCKPILE SITE TOPSOIL FOR POSSIBLE RE-USE IN
UNDER THE SUPERVISION
OF A QUALIFIED FOREMAN. LANDSCAPE BEDS. STOCKPILED TOPSOIL TO BE APPROVED BY OWNERS
REPRESENTATIVE. ROAD BASE, GLACIAL TILL, GRAVEL OR CONTAMINATED
2. ALL PLANT MATERIAL
SIZES AND QUALITY TO CONFORM TO AMERICAN ASSOC. OF SOILS ARE NOT ACCEPTABLE AND WILL BE REJECTED.
NURSERYMEN, AMERICAN
STANDARD FOR NURSERY STOCK, MOST RECENT PUBLISHED.
2. SITE TOPSOIL SHALL HAVE ALL ROCKS, GRASS CLODS AND DEBRIS LARGER
3. PLANT LOCATIONS ON
THE PLANS ARE DIAGRAMMATIC AND MAY BE SUBJECT TO THAN 1" WHENEVER VISIBLE ON THE SURFACE
ADJUSTMENT IN THE FIELD
BY THE LANDSCAPE CONTRACTOR.
3. EXISTING SITE TOPSOIL TO BE AMENDED WITH COMPOST AT A RATIO OF 3:1. 3
4. ALL PLANT MATERIAL
SHALL BE OF NURSERY STOCK AND SHALL BE OF THE TYPE, SIZE UNITS OF EXISTING SOIL TO ONE UNIT OF COMPOST. COMPOST TO BE WSDOT
AND CONDITION SPECIFIED.
THE PLANT MATERIAL SHALL EXHIBIT NORMAL HABITS OF CERTIFIED.
GROWTH FOR THE SPECIES,
SHALL HAVE BUDS INTACT AND SHALL BE FREE OF DISEASE,
INSECTS, SCARS, BRUISES,
BREAKS, SEED AND WEED ROOTS. 4. IN LIEU OF AMENDING SITE TOPSOIL CONTRACTORS MAY CHOOSE TO USE
IMPORTED 2-WAY TOPSOIL.
5. SEE NOTES THIS SHEET
FOR TOPSOIL DEPTH AND SPECIFICATION.
5. TOPSOIL DEPTHS
6. MEDIUM BARK MULCH IS
TO BE INSTALLED AT ALL NEW PLANTING AREAS WITH A MINIMUM
OF 2 INCHES.
5.1. TOPSOIL TO BE PLACED AT A MINIMUM OF 9" IN ALL LANDSCAPE BED AREAS
AND INCORPORATED INTO EXISTING SUBGRADE. LIGHTLY TAMP 6" LAYERS
8. ALL LANDSCAPE AREAS
SHALL HAVE PLANTING BACKFILL AMENDED WITH A WETTING OF SOIL BY HAND OR LIGHTLY WITH EXCAVATOR.
AGENT (TERAWET OR EQUAL)
APPLIED AT MANUFACTURES RECOMMENDED RATE.
5.2. TOPSOIL TO BE PLACE AT AT MINIMUM OF 12" IN ALL TREE-PIT AREAS. SEE
9. LANDSCAPE CONTRACTOR
SHALL VERIFY LOCATION OF ALL SITE UTILITIES PRIOR TO DETAIL THIS PAGE.
LANDSCAPE IMPLEMENTATION.
PLANT LOCATIONS MAY BE ADJUSTED TO AVOID CONFLICT.
5.3. TOPSOIL SHALL NOT BE MOVED, MIXED OR PLACE WHILE SATURATED.
10. LANDSCAPE CONTRACTOR
SHALL TAKE NECESSARY PRECAUTIONS TO PROTECT EXISTING
SITE IMPROVEMENTS,
PAVING, WALLS, AND UNDERGROUND UTILITIES. DAMAGE SHALL BE 6. IN ALL INSTANCES, PLACED TOPSOIL TO BE INCOPRPORTED INTO EXISTING
REPAIRED TO THE OWNER'S
SATISFACTION AND AT NO ADDITIONAL COST. GRADE.
11. PLANT COUNT IS FOR THE
CONTRACTOR'S CONVENIENCE; IF THERE IS A DISCREPANCY,
THE PLAN SHALL GOVERN.
ACTUAL PLANT QUANTITIES TO BE DETERMINED BY REQUIRED
PLANT SPACING.
12. ALL AREAS TO BE PLANTED
WITH GROUNDCOVER ARE INDICATED ON THE PLAN WITH A
HATCH PATTERN. SEE
PLANT LIST FOR PLANT TYPE, SIZE, AND SPACING.
13. SUBSTITUTION OF PLANT
VARIETIES DUE TO LACK OF AVAILABILITY SUBJECT TO
APPROVAL BY THE OWNERS
REPRESENTATIVE AND CITY.
MAINTENANCE NOTES -
14. ALL DIMENSIONS ARE ASSUMED
TO BE PARALLEL OR PERPENDICULAR UNLESS
1 COA TREE IN 4X4 GRATE DETAIL
2 COA TREE PLANTING DETAIL OTHERWISE NOTED.
1. UNDER NO CIRCUMSTANCE ARE STREET TREES TO BE TOPPED OR PRUNED
L-2 NO SCALE
L-2 NO SCALE 15. ALL SOIL GRADES TO BE
A MINIMUM SIX INCHES BELOW ADJACENT FINISH FLOOR WITHOUT PERMISSION OF THE CITY ARBORIST.
ELEVATIONS UNLESS NOTED
OTHERWISE ALL GRADES ADJACENT TO A BUILDING SHALL
HAVE A MAXIMUM SLOPE
OF 5% 3' FROM FOUNDATION. 2. UNDER NO CIRCUMSTANCE ARE SHRUBS TO BE SHEARED OR SHAPED
WITHOUT EXPLICIT PERMISSION FROM THE OWNER. SHRUBS ARE DESIGNED
16. ALL FINISH GRADES TO
BE FLUSH WITH ADJACENT SURFACES, SUCH AS TOP OF CURB. TO FILL AND GROW IN TO A PERMANENT MATURE SIZE.
17. ALL GRADES, DIMENSIONS
AND EXISTING CONDITIONS SHALL BE VERIFIED BY THE 3. GROUNDCOVER THAT GROWS 'OUT' OF BEDS AND INTO ADJACENT WALKS OR
CONTRACTOR PRIOR TO
CONSTRUCTION. ANY DISCREPANCIES SHALL BE BROUGHT TO ROADS ARE TO BE CUT-BACK AS NEEDED.
GROUNDCOVER PLANT.
THE ATTENTION OF THE
LANDSCAPE ARCHITECT.
CUTBACK, PULL OUT AND DISTURB ALL
SEE PLANT LIST
4. PERENNIAL AND GRASSES WHICH ARE DECIDUOUS MAY BE CUT BACK AT
CIRCLING ROOTS FROM ANY CONTAINER 1. PLANT SHRUB 1/2"
HIGHER THAN DEPTH
GROWN PLANTS BARK MULCH GROWN AT NURSERY.
18. SUPPLEMENTAL HAND WATERING
TO BE DONE DURING FIRST TWO YEARS TO GUARANTEE OWNERS DISCRETION, ONCE PER YEAR, DURING THE MONTHS OF FEBRUARY,
2. FERTILIZE ALL
PLANTS WITH APPROVED PLANT ESTABLISHMENT.
IF CITY REQUIRES AUTOMATED IRRIGATION SYSTEM THEN MARCH OR APRIL.
STARTER FERTILIZER
APPLIED AT BIDDER DESIGNED SYSTEM WILL
BE PROVIDED.
MANUFACTURER'S
SUGGESTED RATES
5. LAWN TO BE FERTILIZED ONCE PER YEAR MIN PER PRODUCT INSTRUCTIONS.
TOPSOIL DEPTH AND 3. SCARIFY ROOTBALL
OF
TYPE AS SPECIFIED CONTAINER-GROWN
PLANTS. PRIOR TO 19. BASEMAP PROVIDED BY ENGINEERS,
CASCADE SURVEYING AND ENGINEERING, INC,
BACKFILLING
360-435-5551
6. WEEDS TO BE REMOVED IN A TIMELY MANNER BY MECHANICAL OR CHEMICAL
EXISTING
MEANS, IN COMPLIANCE WITH ALL LOCAL AND STATE GUIDELINES AND
SECTION SUBGRADE
REQUIREMENTS.
2" DEPTH BARK MULCH
7. BARK MULCH IN PLANTER BEDS TO BE TOPPED OFF WITH 1" LIFT MIN, ONCE
4" WATERING BASIN
PER YEAR IN THE SPRING.
SURROUNDING PLANT
GROUNDCOVER PLANT
EQUAL
FINISH GRADE
SPACING AS INDICATED
DISTANCE
ON PLANT LIST (TYPICAL)
COMPLETELY REMOVE ALL
DISTANCE
EDGE OF PLANTER
BURLAP, GROWBAG, STRING
EQUAL
AND FOREIGN MATERIALS
60
FROM THE ROOT BALL.
EQUAL
DISTANCE
PLANTING BACKFILL
1/2 DISTANCE
SCARIFY PLANTING PIT WALLS
PLAN
EXISTING SUBGRADE
2 TIMES
SET ROOTBALL ON MOUND OF
ROOTBALL
DIA.
COMPACTED PLANTING BACKFILL MIX
3 TYPICAL PLANTING DETAILS
L-2 NO SCALE
NORTH
one inch
0 20
40 60 80
NO. DATE REVISION BY REV. prepared for:
prepared by:
ISSUE DATE: 3.21.2022
SCALES:
1 12.22.21 Special Use Submittal pd pd Grandview North
eccosDesign Paisley Lofts; project
# 918 HORIZONTAL : 1" = 20' DRAWING:
2146 site
2 3.16.22 UPDATED per COA comments pd pd Paisley Lofts
LANDSCAPE DETAILS
Landscape Architecture and Planning
VERTICAL : N/A
JOB NO.: 2146
Mount Vernon, WA 98273 E. DivisionStreet
p. 360.419.7400
DESIGNED: PD
SHEET:
f. 800.508.2017
contact: Scott Wammack
eccosDesignLLC www.eccosdesign.com Arlington, WA
DRAWN: PD AND NOTES
L-2
CHECKED: PD
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 8/26/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 3 Report Date: 8/26/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
1. NEH Put detail for dumpster on civil plans. (there have Dumpster detail is added to sheet C 3.2 7/25/2022
been issues with civil contractors building the MH
dumpster enclosure and not following standards)
2. NEH Include information about sidewalk restoration along The two water services on Olympic are now 7/25/2022
N Olympic at meter changes, etc. identified on sheet C 5.0 to be decommissioned MH
at the main with pavement, curb, gutter and
sidewalk restoration
3. NEH Need Pedestrian Plan for construction. Notes have been added to the SWPPP sheet to 7/25/2022
state that the existing asphalt sidewalk is to MH
remain in place until the proposed sidewalk is
constructed. Pedestrians will be redirected to
the north side of Division St. at the intersections
of Olympic Ave and Centennial Trail.
4. NEH Need to have full curb between parking and building A full curb is now located between the parking 7/25/2022
sidewalk (south and west) and building on the south side. Grading and MH
details are updated to reflect this. The west
parking already had a full curb.
5. NEH Need construction easement from Snohomish County City of Arlington has an interlocal agreement 7/25/2022
for trail parking area. with Snohomish County which gives the city MH
control and maintenance responsibility.
6. NEH Drainage trench A needs to be on owner property, not Trench A is split into three trenches, Trench 7/25/2022
city property. A,D, and E. Trench A will mitigate runoff from MH
Centennial Alley. Trench D will mitigate runoff
from the courtyard portion of the building and
upper portion of the parking (30% onsite
impervious). The remaining 70% impervious
will be mitigated through Trench E.
Page 1 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 6/8/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 1 Report Date: 6/8/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
7. NEH Demolition permit required, must alert Public Works A note is added to the cover sheet that a 7/25/2022
when the water and sewer are to be disconnected. demolition permit is required. Public Works is MH
to be notified when water and sewer are to be
disconnected.
8. NEH This property has one water credit, all others are new. Acknowledged – no action required. 7/25/2022
MH
9. NEH Please demonstrate that each commercial unit has All commercial units will be accessible from the 8/25/22
ADA accessible entry. ADA parking stalls. There are level landings at MH
the building entrances with a 7.88% ADA
compliant ramp between the landings. This will
provide ADA access to all commercial units.
10. NEH Signage for the one way A ‘One way Do not enter sign is now located at 7/25/2022
the dumpster area and is called out on the sheet MH
C 3.0 with a detail on sheet C 3.2.
11. BG The site plan does not include removing the overhead The note about relocating the power pole on 7/25/2022
lines from the existing book store going south to the Division St is revised to include removing the MH
pole on the west side of the post office. overhead power lines onsite. See sheet C 2.0
12. BG One way striping is shown on the site plan, but no one A ‘One way Do not enter sign is now located at 7/25/2022
way/do not enter signing is shown. the dumpster area and is called out on the sheet MH
C 3.0 with a detail on sheet C 3.2.
13. BG Show saw cuts required in Olympic and division for Saw cuts are shown on the SWPPP. 7/25/2022
water line work, and new driveways. MH
14. BG The elevation on division drops as you move west from A detail is added to sheet C 7.0 to better show 7/25/2022
Olympic. There should be a wall between the building the building along Division Street. The sidewalk MH
and the wall on the west end of the building, but it is and landscape strip will slope up from the road
not shown in any of the plans. at 2% to the buildings brick façade. The height
between the landscaping and buildings finished
floor will vary across the length of building.
Page 2 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
Project Name: Paisley Lofts Permit No.: PWD-3104 Review Date: 7/26/2022
Contact: Randy Devoir Phone No.: 360-435-7171 Review Phase: 2 Report Date: 7/26/2022
Reviewing Dept.: CED Applicant: Scott Wammack DWG Issue Date:
# Rev. Dwg. or Add’l Ref.
City
Comment Response/Resolution
Spec. Ref. Approved
15. RM Install 6" cleanout at building on side sewer to Saddle SSCO #4 is now shown on the plans 5 ft off the 7/25/2022
SSMH #1. building. MH
16. GT The two services on Olympic are not W-50 and are The two water services on Olympic are now 7/25/2022
required to be decommissioned at the main. identified on sheet C 5.0 to be decommissioned MH
at the main with pavement, curb, gutter and
sidewalk restoration
17. MH C2.0 Relocate construction entrance to west side of project Construction entrance is relocated to access from the 8/25/22
to access off alley and not Olympic Ave alley. MH
18. MH Install silt fence along Olympic Ave and Division St. Silt fence is now shown along the back of sidewalks 8/25/22
frontage. Provide wattles along Division when silt fence is along Olympic Ave and Division St. Wattle is located MH
disturbed along Division.
19. MH C3.0 Remove existing curb at full joint and pour new curb The note on sheet C 3.0 is revised to state the curb 8/25/22
integral to existing. Batt joint not allowed and gutter is to be connected at nearest full joint and MH
that no butt joints are permitted.
20. MH C7.0 "Back-In Parking Only" signs to be installed by developer Back in parking only signs are now shown on the 8/25/22
@ 40' spacing plan at 40 ft spacing and the note is updated to 40’
MH
sign spacing.
21. RM C5.0 Both services, Commercial and Residential, on Division Commercial service meter note is revised to be a 2†8/25/22
shall be 2" per COA Standard Detail W-050. service. MH
22. RJ Civil Review Fees Due: $16,824.14 Civil Review Fees are submitted with this 8/12/22
A link for payment has been sent to gv@grandviewinc.net resubmittal. RJ
23. MH General Remove Nova Heaton signature block and use updated Signature Block is updated on sheets C1.1, C2.1,
block on sheets: C1.1, C2.1, C4.1, C4.2 C4.1, and C4.2
https://www.arlingtonwa.gov/DocumentCenter/View/7341/
Construction-Approval-Block-PDF
24. RM Measurements show the existing ADA ramp on the SW SWPP is updated to call for the removal of the
corner of Division and Olympic does not meet current existing ADA ramp. Division St. frontage sheet is
requirements and needs to be upgraded. The ramp slope is updated to call for installation of perpendicular curb
greater than the minimum 8.33%. ramp per WSDOT F-40.15-04 at the SW corner of
Division and Olympic.
Page 3 of 3
18204 59th Avenue NE
REVIEW COMMENT FORM Arlington, WA 98223
360-403-3551
25. RJ Please resubmit (2) two hard copies of all required Two hard copies and electronic copies are
documents and submit electronic files to resubmitted
ced@arlingtonwa.gov.
Page 4 of 3
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
2
PARKING CALCULATIONS:
SITE INFORMATION: AREAS ONSITE:
GRAPHIC SCALE
SITE
AREAS OFFSITE:
DATUM: NAVD 88
CASCADE
SR 530
TO 1-5
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
·
E 0
RESIDENTIAL UNIT MIX:
7
& 91
G
NI E
C
BIKE RACK CALCULATIONS:
Y
E N
V I
R S
U
VICINITY MAP
S
E
D
LEGEND:
ACSAC
OPEN SPACE CALCULATION:
SHADING CALCULATIONS:
LEGAL DESCRIPTION:
MINI PARKS CALCULATION:
BUILDING
GRADING QUANTITIES:
·
·
TAX PARCEL NUMBER: CIVIL ENGINEER:
·
SITE ADDRESS:
OWNER/APPLICANT: SURVEYOR:
E. DIVISION STREET
LANDSCAPE ARCHITECT: CONTACT PERSON:
GEOTECHNICAL ENGINEER:
DATEDATEDATE
NOTES:
DRAWING SHEET INDEX
DESIGNEDDRAWNCHECKEDFIELD BOOK
SHEET NUMBER SHEET TITLE
C C C C C C
C C
CENTENNIAL TRAIL
ONE WAY
N. OLYMPIC AVENUE
ONE WAY
CITY FILE NO.:PWD-3104
PAISLEY LOFTSCOVER SHEET
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 1.0
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
CITY OF ARLINGTON PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
GENERAL CONSTRUCTION NOTES:
CITY OF ARLINGTON CITY OF ARLINGTON
CITY OF ARLINGTON
SANITARY SEWER SYSTEM CONSTRUCTION NOTES: STORM DRAINAGE NOTES:
WATER SYSTEM CONSTRUCTION NOTES:
CASCADE
SURVEYING &
’
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
††“ â€
ACSAC
’
â€
†– â€
“ – â€
“ â€
“ â€
’
’
CITY OF ARLINGTON T.E.S.C.P. NOTES:
’
’
’
’
CITY OF ARLINGTON ADA NOTES:
CSE SUPPLEMENTAL NOTES:
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
CONSTRUCTION SEQUENCE :
··
··
CITY FILE NO.:PWD-3104
NOTES
PAISLEY LOFTS
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 1.1
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
DATUM: NAVD 88
E. DIVISION STREET
CASCADE
NOTES:
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
LEGEND:
CENTENNIAL TRAIL
N. OLYMPIC AVENUE
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
SOIL AMENDED NOTES:
KEY NOTES:
1
C 2.1
3
C 2.1
2
C 2.1
CITY FILE NO.:PWD-3104
·
CALL TWO
BUSINESS DAYS
4
C 2.1
BEFORE YOU DIG PAISLEY LOFTS
1-800-424-5555
GRANDVIEW NORTH LLC
SWPPP & DEMOLITION PLAN
CITY OF ARLINGTON
C 2.0
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE
NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
RETRIEVAL SYSTEM (TYP.)
DRAINAGE GRATE
~ RECTANGULAR GRATE SHOWN
CASCADE
SURVEYING &
OVERFLOW BYPASS (TYP.)
BELOW INLET GRATE DEVICE ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
5" MAX. & 91
G
NI E
C
Y
DRAINAGE GRATE
E N
TRIM V I
R S
U
S
E
D
ACSAC
GRATE FRAME
SEDIMENT AND DEBRIS
OVERFLOW BYPASS
TYPICAL SPLICE DETAIL
BELOW INLET GRATE DEVICE
RAILROAD BALLAST
FILTERED
WATER
SILT FENCE NOTES:
DETAIL NOTES:
SECTION A
WSDOT STANDARD PLAN I-80.10-02
WSDOT STANDARD PLAN I-30.15-02
WSDOT STANDARD PLAN I-40.20-00
1 STABILIZED CONSTRUCTION ENTRANCE (BMP C105)
2 SILT FENCE DETAIL (BMP C233)
3 STORM DRAINAGE INLET PROTECTION (BMP C220)
C 2.1
C 2.1
C 2.1
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
WATTLE NOTES:
×
×
CITY FILE NO.:PWD-3104
CALL TWO
BUSINESS DAYS
WSDOT STANDARD PLAN I-30.30-00
BEFORE YOU DIG PAISLEY LOFTS
STRAW WATTLE DETAIL (BMP C235)
1-800-424-5555 SWPPP DETAILS
4
C 2.1
GRANDVIEW NORTH LLC
CITY OF ARLINGTON
C 2.1
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE
NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
E. DIVISION STREET
GRADING QUANTITIES:
3
DATUM: NAVD 88
2 3
C 7.2
C 7.2 C 7.2
NOTES:
3
C 7.2
CASCADE
6
6
C 7.2
SURVEYING &
C 7.2
·
ENGINEERING, INC.
6
ING
ER
C 7.2
NE
I
G
N
0
E
7
& 91
G
OLYMPIC ENTRANCE
LEGEND:
NI E
C
Y
E N
V I
3
R S
U
S
C 3.1
ED
ACSAC
C C C C C C
C C
3
CENTENNIAL TRAIL
C 3.1
SOUTH DRIVE AISLE FLOWLINE
5
2 6
C 3.1 C 3.1 C 3.1 N. OLYMPIC AVENUE 9
5
C 3.1
10
C 3.1
TYPICAL ROAD SECTION
C 3.2
N-S 1 N-S 2
5
C 3.1
1
C 3.1
4
C 3.1
DATEDATEDATE
9
C 3.1
DESIGNEDDRAWNCHECKEDFIELD BOOK
OLYMPIC - ENTRANCE PROFILE
CITY FILE NO.:PWD-3104
N-S 2 PROFILE
CALL TWO
BUSINESS DAYS
BEFORE YOU DIG PAISLEY LOFTS
1-800-424-5555 GRADING PLAN
GRANDVIEW NORTH LLC
CITY OF ARLINGTON
SOUTH DRIVE AISLE FLOWLINE PROFILE
C 3.0
N-S 1 PROFILE
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
2
C 3.1
7
C 3.1
CASCADE
CITY STANDARD DETAIL R-190 SURVEYING &
ASPHALT THICKENED EDGE DETAIL
4
NOTES:
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
WSDOT STANDARD PLAN M-17.10-02
6 TWO ACCESSIBLE STALLS
·
·
WSDOT STANDARD PLAN F-40.12-03
2 ADA ACCESS RAMP
1 WHEEL STOP DETAIL
1
3 WHEEL STOP AND ELEVATED SIDEWALK SECTION DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
WSDOT STANDARD PLAN F-45.10-02
8 DETECTABLE WARNING SURFACE
CALL TWO
BUSINESS DAYS
BEFORE YOU DIG PAISLEY LOFTS
1-800-424-5555
GRADING DETAILS 1
GRANDVIEW NORTH LLC
WSDOT SIGN R7-801 CITY STANDARD DETAIL R-220 CITY STANDARD DETAIL R-200
7 RESERVED PARKING SIGN 9 TYPE 1 CEMENT DRIVEWAY APPROACH 5 EXTRUDED CONCRETE CURB DETAIL
CITY OF ARLINGTON
C 3.1
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
CASCADE
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
PLAN VIEW
BACK VIEW
18" X 24" SIGN
10 ONE WAY DO NOT ENTER SIGN 11 DUMPSTER ENCLOSURE DETAIL
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
CALL TWO
BUSINESS DAYS
BEFORE YOU DIG PAISLEY LOFTS
1-800-424-5555
GRANDVIEW NORTH LLCGRADING DETAILS 2
CITY OF ARLINGTON
C 3.2
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE
NO.: PWD 3104GRAPHIC SCALE
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
DATUM: NAVD 88
E. DIVISION STREET
CASCADE
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
3
Y
E N
V I
3 C 4.1
R S
U
C 4.1
S
E
D
ACSAC
4 6
C 4.2 C 4.2
3
C 4.1
CENTENNIAL TRAIL
SOUTH DRIVE AISLE FLOWLINE
N. OLYMPIC AVENUE
3
4 6
2 5 6
C 4.1
C 4.2 C 4.2
C 4.1 C 4.2 C 4.2
2 5 6
C 4.1 C 4.2 C 4.2
4 6
LEGEND:
C 4.2 C 4.2
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
LEGEND:
CITY FILE NO.:PWD-3104
1
PAISLEY LOFTSSEWER PLAN
C 4.1
SOUTH DRIVE AISLE FLOWLINE PROFILE
GRANDVIEW NORTH LLC
3
C 4.1
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 4.0
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
CASCADE
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
PLAN
SECTION
PAVED AREAS
NOTES:
NOTES:
12" CAST IRON LOCKING RING AND COVER
ELEVATION
CITY OF ARLINGTON STANDARD DETAIL SS-080
CITY OF ARLINGTON STANDARD DETAIL SS-120 CITY
OF ARLINGTON STANDARD DETAIL SS-130
3 SEWER CLEANOUT DETAIL
1 TYPICAL TRENCH SECTION 2
MONITORING MANHOLE
C 4.1
C 4.1 C 4.1
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
PAISLEY LOFTS
SEWER DETAILS
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
C 4.1
1-800-424-5555
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
NOTES:
CASCADE
NOTES:
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
DA
CSAC
NOTES:
A
A
PLAN
SECTION A-A
DATEDATEDATE
CITY OF ARLINGTON STANDARD DETAIL SS-020
CITY OF ARLINGTON STANDARD DETAIL SS-010 CITY OF ARLINGTON
STANDARD DETAIL SS-030
4 SADDLE MANHOLE
5 SEWER MANHOLE TYPE 1 DETAIL 6 MANHOLE COVER
DETAIL
C 4.2
C 4.2 C 4.2
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
PAISLEY LOFTS
SEWER DETAILS 2
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 4.2
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE
NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
DATUM: NAVD 88
CASCADE
SURVEYING &
ENGINEERING, INC.
·
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
3 4 5
C 5.1 C 5.1 C 5.1
1 2 11
E. DIVISION STREET
C 5.1 C 5.1 C 5.2
3 4 5
C 5.1 C 5.1 C 5.1
1 2 11
7 9
C 5.1 C 5.1 C 5.2
C 5.2 C 5.2
6 10
C 5.1 C 5.2
LEGEND:
12
C 5.2
2 3 5
C 7.2 C 7.2 C 7.2 LEGEND:
CENTENNIAL TRAIL
DATEDATEDATE
N. OLYMPIC AVENUE
8
C 5.2
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
PAISLEY LOFTSWATER PLAN
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 5.0
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
CASCADE
PLAN PLAN
SURVEYING &
ENGINEERING, INC.
4
ING
ER
E
C 5.1
N
I
G
N
0
E
7
NOTES AND MATERIALS:
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
DA
CSAC
ELEVATION ELEVATION
STEEL FABRICATED EPOXY FABRICATED STAINLESS STEEL
COATED TAPPING SLEEVE TAPPING SLEEVE
NOTES:
CITY OF ARLINGTON STANDARD DETAIL W-050
CITY OF ARLINGTON STANDARD DETAIL
W-165
CITY OF ARLINGTON STANDARD DETAIL W-200 THRUST BLOCK DETAIL
1 RESIDENTIAL/COMMERCIAL WATER SERVICE
5
3 TAPPING SLEEVES DETAIL
C 5.1
C 5.1
C 5.1
DATEDATEDATE
PLAN ELEVATION
MATERIAL LIST:
DESIGNEDDRAWNCHECKEDFIELD BOOK
ELEVATION
PLAN
NOTES:
CITY FILE NO.:PWD-3104
NOTES:
CITY OF ARLINGTON STANDARD DETAIL
W-030
6 HYDRANT GUARD POST
C 5.1
PAISLEY LOFTS
WATER DETAILS 1
GRANDVIEW NORTH LLC
CITY OF ARLINGTON STANDARD DETAIL W-090
CALL TWO
CITY OF ARLINGTON STANDARD DETAIL W-160 BUSINESS DAYS
CITY OF ARLINGTON
DOUBLE CHECK VALVE ASSEMBLY FOR 2"
BEFORE YOU DIG
DCVA ASSEMBLY FOR 2"
4 TYPICAL THRUST BLOCK DETAIL
C 5.1
2
1-800-424-5555
C 5.1
C 5.1
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
5' MIN
6"
CASCADE
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
MATERIAL LIST:
VALVE BOX AND EXTENSION
VALVE OPERATING NUT EXTENSION
CITY OF ARLINGTON STANDARD DETAIL W-225
FIRE LINE UNDERGROUND NOTES:
9
FLOOR FLANGE DETAIL
C 5.2
CITY OF ARLINGTON STANDARD DETAIL W-220
7 FIRE LINE CONNECTION
C 5.2
CITY OF ARLINGTON STANDARD
DETAIL W-190
VALVE BOX
AND
11 OPERATING NUT EXTENSION
C 5.2
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
NOTES:
UNPAVED AREA PAVED AREA
NOTES:
CITY FILE NO.:PWD-3104
12 FIRE DEPARTMENT CONNECTION DETAIL
PAISLEY LOFTS
C 5.2
WATER DETAILS 2
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
CITY STANDARD DETAIL W-270
CITY OF ARLINGTON STANDARD DETAIL W-010
BEFORE YOU DIG
C 5.2
8 TYPICAL TRENCH DETAIL
10 FIRE HYDRANT ASSEMBLY 1-800-424-5555
C 5.2
C 5.2
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2,
TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
DATUM: NAVD 88
CASCADE
SURVEYING &
·
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E. DIVISION STREET
E N
V I
R S
U
S
E
D
ACSAC
LEGEND:
5
C 6.1
1
C 6.1
LEGEND:
1
C 6.1
CENTENNIAL TRAIL
1
C 6.1 5
C 6.1
1
C 6.1
N. OLYMPIC AVENUE
1
C 6.1
DATEDATEDATE
5
C 6.1
DESIGNEDDRAWNCHECKEDFIELD BOOK
NOTES:
2
3 4
C 6.1
C 6.1 C 6.1
6 7
C 6.1 C 6.1
CITY FILE NO.:PWD-3104
PAISLEY LOFTS
DRAINAGE PLAN
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
1-800-424-5555
C 6.0
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
NOTES:
NOTE:
CASCADE
SURVEYING &
INFILTRATION TRENCH
SECTION ENGINEERING, INC.
1
C 6.1 ING
ER
E
N
I
G
N
0
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
6" OR 12"
24"
6" 2' MAX
MIN COVER
6" MIN
44"
18"
CITY STANDARD DETAIL SD-030 CITY STANDARD DETAIL SD-020
2 CATCH BASIN TYPE 1-L DETAIL 6 CATCH BASIN TYPE 1 DETAIL
C 6.1 C 6.1
32"
CITY OF ARLINGTON STANDARD DETAIL SD-120
3 STANDARD OIL/WATER SEPARATOR
C 6.1
DATEDATEDATE
NOTES:
DESIGNEDDRAWNCHECKEDFIELD BOOK
SECTION B-B
PLAN SECTION B-B TOP VIEW
NOTE:
12" CAST IRON LOCKING RING AND COVER
PAVED AREAS CITY FILE NO.:PWD-3104
NOTES:
SECTION A-A
CITY OF ARLINGTON STANDARD DETAIL SS-080
SECTION A-A
5 CLEANOUT DETAIL PAISLEY LOFTS
C 6.1
GRANDVIEW NORTH LLCDRAINAGE DETAILS
CITY STANDARD DETAIL SD-060
4 CATCH BASIN GRATE DETAIL
SECTION C-C
C 6.1
CITY STANDARD DETAIL SD-080
CALL TWO
BUSINESS DAYS CITY OF ARLINGTON
7 CATCH BASIN SOLID COVER DETAIL
BEFORE YOU DIG
C 6.1
1-800-424-5555 C 6.1
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE
NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
GRAPHIC SCALE
3
C 7.2
4
DATUM: NAVD 88
C 7.2
E. DIVISION GUTTERLINE
CASCADE
SURVEYING &
DIVISION BUILDING ENTRANCE
ENGINEERING, INC.
3
ING
ER
E
N
I
C 7.2
G
N
0
E
7
& 91
1
G
NI E
(SEE C 7.1)
2 3 C 7.2
Y C
ALLEYWAY CL ALLEY ENTRANCE
E N
C 7.2 C 7.2
V I
R S
(SEE C 7.1)
U
S
E
D
ACSAC
E. DIVISION GRADING DETAIL
LEGEND:
DATEDATEDATE
LEGEND:
DESIGNEDDRAWNCHECKEDFIELD BOOK
E. DIVISION - GUTTERLINE
PROFILEE. DIVISION GUTTERLINE PROFILE
CITY FILE NO.:PWD-3104
E. DIVISION BUILDING ENTRANCE PROFILEDIVISION
- ENTRANCE PROFILE
PAISLEY LOFTS
GRANDVIEW NORTH LLC
FRONTAGE - DIVISION ST. NE
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
E. DIVISION DETAIL
BEFORE YOU DIG
C 7.0
1-800-424-5555
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E, W.M.
LEGEND:
C
C
GRAPHIC SCALE
CASCADE
SURVEYING &
DATUM: NAVD 88
ENGINEERING, INC.
LEGEND:
ALLEY ENTRANCE
ING
ER
E
N
ALLEYWAY CL
I
G
N
0
E
7
1
& 91
G
C 7.1
NI E
C
Y
E N
V I
R S
U
S
E
· D
ACSAC
1
C 7.2
1 UTILITY POLE ANCHOR
DATEDATEDATE
C 7.1
DESIGNEDDRAWNCHECKEDFIELD BOOK
CITY FILE NO.:PWD-3104
PAISLEY LOFTS
ALLEY ENTRANCE PROFILE
ALLEYWAY CL PROFILE
GRANDVIEW NORTH LLC
FRONTAGE - CENTENNIAL ALLEY
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
BEFORE YOU DIG
C 7.1
1-800-424-5555
# 22923
CITY OF ARLINGTON - PAISLEY LOFTS
FILE NO.: PWD 3104
PORTION SW1/4, SE1/4, SEC.2, TWP.31N, RGE.5E,
W.M.
3
C 7.2
CASCADE
TYPICAL SECTION
SURVEYING &
ENGINEERING, INC.
ING
ER
E
N
I
G
N
0
DETAIL A
E
7
& 91
G
NI E
C
Y
E N
V I
R S
U
S
E
D
ACSAC
DETAIL B
PLAN VIEWS
NOTES:
NOTES:
CITY STANDARD DETAIL R-170 CITY STANDARD DETAIL R-160
2 CEMENT CONCRETE SIDEWALK 6 PEDESTRIAN HANDRAIL DETAILS
C 7.2 C 7.2
1 STREET TREE DETAIL
C 7.2
EXISTING ASPHALT CONCRETE OVER CEMENT CONCRETE
DATEDATEDATE
DESIGNEDDRAWNCHECKEDFIELD BOOK
TYPICAL SECTION
NOTES:
EXISTING ASPHALT CONCRETE OVER PREPARED GRADE
CITY FILE NO.:PWD-3104
EXISTING CEMENT CONCRETE OVER PREPARED GRADE
CITY STANDARD DETAIL R-180
PAISLEY LOFTS
NOTES: 3 CEMENT CONCRETE CURB & GUTTER
C 7.2
FRONTAGE DETAILS
GRANDVIEW NORTH LLC
CALL TWO
BUSINESS DAYS
CITY OF ARLINGTON
CITY STANDARD DETAIL R-140
BEFORE YOU DIG
4 BACK IN ANGLED PARKING DETAIL
5 PAVEMENT PATCH 1-800-424-5555
C 7.2
C 7.2
C 7.2
# 22923
From: Ryan Morrison
To: Raelynn Jones
Cc: Brian Grieve; Joshua Jones
Subject: RE: Paisley Lofts ADA Ramp
Date: Wednesday, July 20, 2022 3:52:18 PM
Attachments: image001.png
image002.png
I’ll add it under the PW-Admin review even though it was last completed in May, if that’s the proper
location. Just wanted to make sure it didn’t get missed if PW-Admin was closed out.
Thanks!
Ryan
From: Raelynn Jones <rjones@arlingtonwa.gov>
Sent: Wednesday, July 20, 2022 15:39
To: Ryan Morrison <RMorrison@arlingtonwa.gov>
Cc: Brian Grieve <bgrieve@arlingtonwa.gov>; Joshua Jones <jjones@arlingtonwa.gov>
Subject: RE: Paisley Lofts ADA Ramp
Hi Ryan,
We have not sent out comments as of yet so these would just need entered into iworqs. Thank you!
Sincerely,
Raelynn Jones | Permit Technician I
Phone: 360-403-3436
Email: rjones@arlingtonwa.gov
Website: www.arlingtonwa.gov
18204 59th Ave NE, Arlington, WA 98223
From: Ryan Morrison <RMorrison@arlingtonwa.gov>
Sent: Wednesday, July 20, 2022 3:32 PM
To: Raelynn Jones <rjones@arlingtonwa.gov>
Cc: Brian Grieve <bgrieve@arlingtonwa.gov>; Joshua Jones <jjones@arlingtonwa.gov>
Subject: Paisley Lofts ADA Ramp
Hi Raelynn,
In the process of measuring the ADA ramps on Division for next year’s overlay project we found that
the ADA ramp on the SW corner of Division and Olympic was not up to current standards, despite it
appearing so. The ramp running slope exceeds the required minimum slope.
I’d like to include in the next batch of review comments that the ramp will need to be replaced and
upgraded to current standards as part of their frontage improvements. This will also avoid us having
to impact their new frontage with construction next year as we would have no choice but to replace
it.
Thank you,
Ryan
Ryan R. Morrison, P.E.
Deputy PW Director/City Engineer
City of Arlington
desk: 360-403-3512 fax: 360-435-7944 cell: 360-913-1224
154 W Cox St., Arlington, WA 98223
rmorrison@arlingtonwa.gov
www.arlingtonwa.gov
PRE-CONSTRUCTION MEETING AGENDA
Community and Economic Development
City of Arlington • 18204 59th Avenue NE • Arlington, WA 98223 • Phone (360) 403 3551
Project Name: Paisley Lofts Project No.: PWD#3104 Date: 9/29/2022
Contractor: Grandview North, LLC Superintendent: Scott Benham Ph. No.: 425-422-0250
The purpose of this meeting is to provide the most common inspections and noteworthy information. This meeting is not
intended to be all-encompassing.
It is the responsibility of the Owner, Developer and Contractor to adhere to the approved plans, verify compliance with the
City of Arlington Municipal Code, Public Works Design and Construction Standards, International Code Council (ICC),
applicable local, state and federal requirements or any order, proclamation, guidance or decision of the Governor.
In addition, construction sites shall adhere to current COVID-19 Jobsite Safety Requirements as per local, state and
federal regulations.
INSPECTIONS
• INSPECTIONS (360-403-3417) MUST BE CALLED IN BEFORE 3:30 PM TO BE ON THE NEXT BUSINESS DAY
INSPECTION SCHEDULE
• Inspections are Monday-Friday with exception of Local, State or Federal Holidays.
Building, Storm and Civil Inspections - 8 am to 4:30 pm; Water or Sewer inspections - 8:00 am to 3:30 pm
• To cancel or modify an inspection - Building, Storm or Civil call 360-403-3433; Water or Sewer call 360-403-3526
• It is the responsibility of the Owner, Developer and Contractor to call and arrange for appropriate inspections. Onsite
tailgate meetings are advised with each individual inspector prior to installation of their related facilities with those
persons who are actually performing the work.
• Failure to call for inspection may result in work being left exposed and/or removed and reconstructed
• Re-inspections may be charged at $127.00 per hour, ½ hour minimum for failure to call for inspection.
Submittal Documents ï²
 Contractor contacts and 24 hr. emergency numbers:  Copies of other agency permits or proof that the
Scott Benham 425-422-0250 application is in progress:
 Proof of insurance listing the City of Arlington as additional  One week prior to the pre-construction
insured: 164GL0022768-05 Exp. 3/21/2023 meeting. Submittals for all materials and
 subcontractor approvals: DISCUSS AT PRE-CON
Performance Bond must be on file: PB#09405870
AS NECESSARY
 Contractor’s License: GEANDNL013K Exp:  City of Arlington Business License: Current
 Testing Company Name and Contact Information: CESCL Name: N/A
ï²
MTC 360-755-1990 CESCL#: Exp.:
ï² Drafts of easements and dedications must be in for review:
~Need separate legal and exhibit map for City Council Approval – REQUIRED WITH AS-BUILT SUBMITTAL
 Contact State Historical Preservation Officer and Stillaguamish Tribe if required per Land Use Permit
Dept. of Archaeology Historic Preservation
Stillaguamish Tribe of Indians - THPO@stillaguamish.com
360-586-3065
Kerry Lyste Ph.: 360-572-3072; klyste@stillaguamish,.com
Sam Barr Ph.: 360 -622-7055; sbarr@stillaguamish.com
 City of Arlington Design and Construction Standards and Specifications. (Available online)
 Construction Work Hours – Monday – Saturday 7 am to 7pm. No Sundays City recognized or Federal Holidays
UPCOMING HOLIDAYS – SEE FULL LIST OF 2022 FEDERAL HOLIDAYS
ï² Binders and approved plans shall be kept onsite
 As-built plans will be required – submit contractor redlined plans with as-built submittal
MISCELLANEOUS:
1. Bulk Hydrant Use – 360-403-3526
2. Call for Locates
3. Planting schedule and methods
4. Onsite inspection prior to and during planting
5. Inspect final grade for lawn installation (Hydro-seed/sod)
6. Verify root barrier installation
7. Planting methods & before planting mulch installation
8. Staking & top mulch installation
GENERAL CIVIL AND STORM DRAINAGE REQUIREMENTS:
9. Keep road clean and overall site.
10. Dust control required.
11. Maintain construction entrance – use railroad ballast – no spawls.
12. Silt fence as needed – contact for tailgate discussion.
13. All grouting shall be inspected inside and out.
14. Sand collars required unless otherwise specified.
15. All risers to be wet set and mudded inside and out.
16. All infiltration areas to be inspected before cover.
17. Provide protection for all infiltrating materials / amended soils, railroad ballast, drain rock
18. ECO Pans required for concrete clean up or approved wash down area with water tight containment.
19. CDF is required in right of way per R-140, up to the bottom of asphalt; no compaction required. Only for
trenching within the roadway prism.
20. A Traffic Control Plan shall be submitted and approved prior to any work within the public Right of Way.
21. Landscaping – root barriers are required per Standard Detail R-270.
22. CALL INSPECTION LINES AND NOT INDIVIDUAL CELL PHONES!!
23. Right of Way site plan and TCP is required for any right of way work. WSDOT TCP is acceptable or TCP
per MUTCD.
GENERAL UTILITY REQUIREMENTS:
24. Do not cover without inspection.
25. Maintain survey staking.
26. All pipe in ground shall be inspected before cover.
27. Take pictures.
28. Call if you have any questions.
29. No pipe received on site without the ends covered; covers will remain in place until installation.
30. Signed set of approved construction drawings will be on site.
31. General site maintenance - No garbage in the ditch; no fittings/pipe in the mud; fitting assembly in a
clean area.
32. Maintain horizontal and vertical clearance with other utilities.
33. Maximum amount of open trench shall not exceed 100 feet.
34. Dropped and/or damaged pipe will be removed from the site and replaced.
35. High ground water a potential and dewatering plan may be required. De-watering pumps will need to be
available and in good working condition if needed.
36. A Red Line copy of the construction drawings will be submitted to the COA at the project completion
with the as-built plans.
37. Tracer Tape is required over side sewer pipes, stubs and any undetectable pipe at 24 to 48 inches below
finished grade extending the full length.
Page 2 of 5 REV6.2021
GENERAL WATER REQUIREMENTS:
38. Irrigation requires a separate tap for irrigation or a variance can be requested; send to Ryan Morrison
rmorrison@arlingtonwa.gov.
39. CDF not required but compaction shall be met.
40. Inspectors shall be contacted and pictures will be taken.
41. All service lines shall be 2 inches and reduced at meter.
42. No 2 inches setters will be installed without restraint rods/spacer (Spud) in place. No wood spacers.
43. Pipe handling - Anticipate low water flows for flushing, keep the pipe/fittings clean. Water tight plug
shall be used.
44. Once fittings arrive on site they need to be verified that they conform to approved submittals/COA STD.
45. Reduced Pressure Backflow Assembly (RPBA) is required, preferably inside the building. The RPBA
must be in line where the water enters the building. Placement of the RPBA is a minimum of 1 foot and a
maximum of 5 feet from ground level.
46. Mega Lugs and Field Locks are required.
47. All valves to be in the closed position to prevent debris/water from entering pipe.
48. Heavy plastic (4 mil. min.) on all fittings prior the thrust blocking.
49. Pre-block and post-block inspections are required. An ecology block may be used with crushed rock
backfill compacted to 95%, as needed.
• Ecology ½ block - 2’x2’x3’ (1900 lbs.); or
• Ecology full block – 2’x2’x6’ (3850 lbs.); or
• Per standard detail W-160 thru W-175.
50. All Services will be flushed prior to testing or connecting to the check valve to prevent the check valve
from damage.
51. What type of chlorination will you use? Disposal of the Super Chlorinated water?
52. Tie-in connections shall be less than 18 feet and swabbed with a chlorinated water solution of
appropriate strength.
53. Water meter will not be set until connection fees have been paid. Contact the Permit Center for or apply
online. 360-403-3551 or www.arlingtonwa.gov/254/Construction-Utility-Applications
54. Limited hydrant meters, PUD may supply.
GENERAL SANITARY SEWER REQUIREMENTS
55. Inspectors will take pictures.
56. Side sewer pipe and stubs shall be 6 inches.
57. Bedding shall be 3/8 inch clean washed pea gravel or imported clean sand, 6 inches below pipe and 12
inches above pipe.
58. Cleanouts shall be placed 5 feet from the building where each sewer stub exits the building. Cleanouts
are required every 100 feet, must be at grade with ring, cover and internal plug, not a cap. If a clean out
is not located in a solid surface, it will require a concrete pad.
59. All grouting shall be inspected inside and out.
60. All risers to be wet set and mudded inside and out. Do not use Jet set.
61. Sanitary Sewer Pipe shall be cleaned and tested after backfilling by either exfiltration or low pressure
air method.
62. Sewer main will be CCTV and inspector shall be onsite.
63. Clean outs will be a “Y†at 45°.
Page 3 of 5 REV6.2021
64. Monitoring manhole (MMH) is required for each commercial use within the city. If multi-tenant, each
unit needs to connect separately to a MMH. Maximum of three (3) units may connect to one (1) MMH.
Detail SS-130.
BUILDING REQUIREMENTS
65. Special Inspections
66. Wall/rockeries separate building permit
67. Field Revisions to Issued Permit – Level 1:
Minor changes that Inspectors may add to the approved building permit file. The inspector may also
determine that a level 2 requirement is necessary based on the extent and complexity of the changes
proposed.
“Minor Changes†would include small scale changes, such as:
• Updates to floor plan with no increases in footprint, change of uses, or heights.
• Minor structural changes from the engineer and/or designer of record; such as:
o basic beam changes,
o changes of covered porches, patios,
o over framed areas from trusses to stick framed roofs w/50 psf. or less roof snow loads
without roof pitch changes,
o window changes without egress change,
o minor footing/foundation adjustments).
• All changes/modifications should be noted/documented on the permit file and as necessary
within the permitting system.
68. Revisions to Issued Permit – Level 2
New applications may be required for minor revisions where staff review is necessary for proposed
revisions. Only 1 revision is allowed to any issued building permit.
• Types of potential changes may include but are not limited to:
o Reallocation of floor area use if it would include and/or cause an increase in bedroom
count(s).
o Site plan changes in orientation or location on a site without any structural changes.
o Roof pitch changes.
o Structural changes and alterations that would then require some type of building plan
review.
o Slight increases and/or adjustments to previously permitted details and/or features which
would increase the area and/or footprint square footage, including, but not limited to:
ï‚§ decks,
ï‚§ covered porches/decks,
ï‚§ existing room(s)/habitable space,
ï‚§ garage
• Increases shall not exceed 10% of the existing detail/floor area up to a maximum total of 250
sq. ft.
• Increases and/or adjustments shall not create a nonconforming structure (e.g. setbacks,
floodplain, critical area, shoreline, ADU limitations, or would create other type of
nonconforming use).
69. Revisions to Issued Permit – Level 3
Requirements for new Permit application and full review of Substantial Changes:
Changes in the scope and scale of the structure and/or structural design that would necessitate a new
permit.
Page 4 of 5 REV6.2021
• “Substantial Changes†would include changes, such as:
o Changing from wood to reinforced concrete or other change in the type of construction.
o Changes in occupancy that require extensive changes to the construction and life safety
design of the structure.
o Altered projects resulting in a totally new configuration/layout.
o A completely new design, new elements, and/or features not part of the original prior
approved building permit.
GENERAL REQUIREMENTS:
70. Permit numbers shall be added to all required reports and emailed to the following:
• Marc Hayes – mhayes@arlingtonwa.gov 360-403-3457
• Kevin Olander – kolander@arlingtonwa.gov 360-403-3433
• Brian Grieve- bgrieve@arlingtonwa.gov 360-403-3438 / 360-913-1396 (cell)
• Permit Center – ced@arlingtonwa.gov 360-403-3551
71. Utility General Contact Information: 360-403-3526
• Water Department Contact:
o Gus Tararan – gtararan@arlingotnwa.gov 425-754-7438
o Inspections – 360-403-3526
• Wastewater Department Contact:
o Joe Wilson – jwilson@arlingotnwa.gov 425-754-7442
o Inspections – 360-403-3508
72. Plan Revisions shall be submitted via hard copy to CED Department for review.
• Two (2) copies of revised plans shall be required along with an electronic copy
Page 5 of 5 REV6.2021
City of Arlington
Community & Economic Development
7/26/2022
Grandview North LLC
PO Box 159
Arlington, WA 98223
RE: Pre-Construction Requirements
Project Name: Paisley Lofts
Project Address: 102 E Division St., Arlington, WA 98223
Project No.: PWD-3104
Dear Scott,
In order for work to commence at the Paisley Lofts project site, the following items need to be
submitted to the City of Arlington:
1. Civil Review Fees Due: $16,824.14
a. A link for payment has been sent to gv@grandviewinc.net
2. A performance bond will need to be on file with the City of Arlington. The City of Arlington
Performance Bond form is included. We will require submittal of the original document.
This bond is to insure completion of the following and shall be indicated on the security:
All included infrastructure relating to water, sanitary sewer, and stormwater drainage
systems, any right of way improvements along with any private and public landscaping.
Performance Bond Estimated Cost of Construction is $172,479.38 x 150% = $258,719.06
3. Contractor Information:
a. License No. and 24 hour emergency contact information
b. Contractor must obtain a City of Arlington Business License
c. Contractor Proof of Insurance with the City of Arlington named as Additional
Insured
4. Project CESCL with current certificate (1 acre or more)
5. Project Testing Company with contact information
6. Material submittals for all proposed water, sewer and stormwater infrastructure shall be
18204 59th Avenue NE, #B - Arlington, WA, 98223 - 360-403-3551 – www.arlingtonwa.gov
approved. Allow one (1) weeks’ time for review of material submittals.
Once the items above have been received and approved, a pre-construction meeting will be
scheduled.
Project closeout information
The performance bond shall be released when inspection and approval of all work has been
completed, as-built plans, easements, dedications, and bills of sale have been approved and a two-
year, 20% maintenance bond is on file with the City of Arlington. The City does not have a template
for the maintenance bond, however Surety’s standard form is acceptable and shall consist of
following of which shall be indicated on the security.
“All included infrastructure relating to the public water, and sanitary sewer systems, right of
way improvements along with any private and public landscaping.â€
“The bond shall not be released without written discharge from the City of Arlingtonâ€
Maintenance Bond Estimated Cost of Construction $168,491.25 x 20% = $33,698.25
Should you have any questions or require additional information, please contact me at 360.403.3551
or rjones@arlingtonwa.gov .
Sincerely,
Raelynn Jones
Permit Technician I
Community & Economic Development
Department of Community & Economic Development
CIVIL INSPECTION DAILY REPORT
PROJECT INFORMATION
REPORT DATE PROJECT NAME PREPARED BY
10/25/2023 Paisley Lofts Brian Grieve
WORK PERFORMED
Was work performed today?
☒ - Yes
☠- No
TYPE OF WORK PERFORMED APPROVED APPROVED NOTES
PLANS? MATERIALS?
Infiltration Trench Yes Yes Crews are installing the parking lot infiltration
trench.
TEMPORARY TRAFFIC CONTROL
Was Temporary Traffic Control required?
☠- Yes
☒ - No
Is the contractor maintaining the traffic control devices?
☠- Yes
☠- No
☒ - N/A
CLOSURE TYPE APPROVED NOTES
PLAN?
N/A
TEMPORARY EROSION & SEDIMENT CNTROL
Are the contractor’s erosion control measures in place?
☒ - Yes
☠- No
Is the contractor maintaining erosion control BMPs?
☒ - Yes
☠- No
☠- N/A
EROSION CONTROL ISSUE NOTES
N/A
INSPECTOR COMMENTS
None
Page 2
Department of Community & Economic Development
CIVIL INSPECTION DAILY REPORT
PROJECT INFORMATION
REPORT DATE PROJECT NAME PREPARED BY
10/26/2023 Paisley Lofts Brian Grieve
WORK PERFORMED
Was work performed today?
☒ - Yes
☠- No
TYPE OF WORK PERFORMED APPROVED APPROVED NOTES
PLANS? MATERIALS?
Utilities Yes N/A Crews are installing utilities to the building. L&I
is inspecting that work.
TEMPORARY TRAFFIC CONTROL
Was Temporary Traffic Control required?
☠- Yes
☒ - No
Is the contractor maintaining the traffic control devices?
☠- Yes
☠- No
☒ - N/A
CLOSURE TYPE APPROVED NOTES
PLAN?
N/A
TEMPORARY EROSION & SEDIMENT CNTROL
Are the contractor’s erosion control measures in place?
☒ - Yes
☠- No
Is the contractor maintaining erosion control BMPs?
☒ - Yes
☠- No
☠- N/A
EROSION CONTROL ISSUE NOTES
N/A
INSPECTOR COMMENTS
None
Page 2
City of Arlington
Community & Economic Development
March 18, 2024
Grandview North LLC
PO Box 159
Arlington, WA 98223
RE: Project Closeout Requirements
Project Name: Paisley Lofts
Project Address: 102 E Division St
Project No.: PWD-3104
Dear Mr. Wammack,
Portions of the construction project are nearing completion. Prior to Certificate of Occupancy
issuance and performance bond #09405870 release, review and approval of all items related to the
project closeout are required.
1. All punch list items shall be completed and approved (punch list attached); it is the
responsibility of the Contractor to arrange reinspection of all punch list items.
a. For all punch list items except water and sewer; contact Brian Grieve for reinspection:
i. 360-913-1396 or bgrieve@arlingtonwa.gov.
b. For Water and Sewer Punch list items contact:
i. Public Works Department: 360-403-3526
2. As-Built plans:
a. Plans shall adhere to the Public Works Design and Construction Standard 1-11.
b. Shall include all public and private infrastructure, and right of way improvements
c. Submit one (1) full paper set along with the electronic format (PDF)
d. AutoCAD files will be required with As-Built plan final approval
3. Easement / Right of Way Dedication:
a. A 20-foot easement is required for any public water system on private property.
b. Submittal of legal description and exhibit map by a Professional Engineer or Surveyor
licensed in the state of Washington
i. All text shall be a minimum of 8-point font.
ii. Avoid low contract colors and highlighting
c. Right of Way Dedications require Council approval, which may extend the project
closeout timeline.
4. Maintenance Bond:
a. A 2-year maintenance bond is required.
i. The City of Arlington maintenance bond form may be used; or
ii. An Assignment of Funds
iii. The Following shall be indicated on the security:
1. The Bond shall not be released without written discharge from the City
of Arlington
2. All items related to on and off site landscaping, public water and sewer
systems, public stormwater drainage systems and right of way
improvements.
b. Maintenance Bond Estimated Cost of Construction $168,491.25 x 20% = $33,698.25
5. Copy of recorded Snohomish County PUD easement.
All of the above requested information must be submitted with the as-built plans to be considered a
complete submittal for review. Please feel free to reach out should you have any questions at 360-
403-3551 or kfoster@arlingtonwa.gov.
Sincerely,
Kristin Foster
Permit Technician II
Community & Economic Development
18204 59th Avenue NE, #B - Arlington, WA, 98223 - 360-403-3551 – www.arlingtonwa.gov
Punch List Items:
• Complete Alley Paving
• Seal paving joint between Division St & the new street parking
• Division crosswalk striping at the alley
• Complete Concrete Curb around the new alley and trail parking spaces
• Install Tire Stops
• Dumpster Enclosure Doors
• Division Street Trees & Grates
• Centennial Trail Trees & Bushes
• Parking Lot Landscaping
o Contact Brian Grieve about the landscaping where the electrical transformer was
installed in the southeast corner of the development
o The electrical transformer will need to be wrapped
• Clean up/stabilize the grading between the development and the post office
• Remove temporary erosion & sediment control devices (final item)
• The transformer that was installed in the landscape strip along Olympic will need to be
wrapped
• Contact Public Works for Water & Sewer Punch Lists
18204 59th Avenue NE, #B - Arlington, WA, 98223 - 360-403-3551 – www.arlingtonwa.gov
City of Arlington
Community & Economic Development
April 19, 2024
Grandview North LLC
PO Box 159
Arlington, WA 98223
RE: Project Closeout Requirements
Project Name: Paisley Lofts
Project Address: 102 E Division St
Project No.: PWD-3104
Dear Mr. Wammack,
Portions of the construction project are nearing completion. Prior to Certificate of Occupancy
issuance and performance bond #09405870 release, review and approval of all items related to the
project closeout are required.
1. All punch list items shall be completed and approved (punch list attached); it is the
responsibility of the Contractor to arrange reinspection of all punch list items.
a. For all punch list items except water and sewer; contact Brian Grieve for reinspection:
i. 360-913-1396 or bgrieve@arlingtonwa.gov.
b. For Water and Sewer Punch list items contact:
i. Public Works Department: 360-403-3526
2. As-Built plans:
a. Plans shall adhere to the Public Works Design and Construction Standard 1-11.
b. Shall include all public and private infrastructure, and right of way improvements
c. Submit one (1) full paper set along with the electronic format (PDF)
d. AutoCAD files will be required with As-Built plan final approval
3. Easement / Right of Way Dedication:
a. A 20-foot easement is required for any public water and sewer system on private
property.
b. Submittal of legal description and exhibit map by a Professional Engineer or Surveyor
licensed in the state of Washington
i. All text shall be a minimum of 8-point font.
ii. Avoid low contract colors and highlighting
c. Right of Way Dedications require Council approval, which may extend the project
closeout timeline.
4. Maintenance Bond:
a. A 2-year maintenance bond is required.
i. The City of Arlington maintenance bond form may be used; or
ii. An Assignment of Funds
iii. The Following shall be indicated on the security:
1. The Bond shall not be released without written discharge from the City
of Arlington
2. All items related to on and off site landscaping, public water and sewer
systems, public stormwater drainage systems and right of way
improvements.
b. Maintenance Bond Estimated Cost of Construction $168,491.25 x 20% = $33,698.25
5. Copy of recorded Snohomish County PUD easement.
All of the above requested information must be submitted with the as-built plans to be considered a
complete submittal for review. Please feel free to reach out should you have any questions at 360-
403-3551 or kfoster@arlingtonwa.gov.
Sincerely,
Kristin Foster
Permit Technician II
Community & Economic Development
18204 59th Avenue NE, #B - Arlington, WA, 98223 - 360-403-3551 – www.arlingtonwa.gov
Punch List Items:
• Complete Alley Paving
• Seal paving joint between Division St & the new street parking
• Division crosswalk striping at the alley
• Complete Concrete Curb around the new alley and trail parking spaces
• Install Tire Stops
• Dumpster Enclosure Doors
• Division Street Trees & Grates
• Centennial Trail Trees & Bushes
• Parking Lot Landscaping
o Contact Brian Grieve about the landscaping where the electrical transformer was
installed in the southeast corner of the development
o The electrical transformer will need to be wrapped
• Clean up/stabilize the grading between the development and the post office
• Remove temporary erosion & sediment control devices (final item)
• The transformer that was installed in the landscape strip along Olympic will need to be
wrapped
• Contact Public Works for Water & Sewer Punch Lists
18204 59th Avenue NE, #B - Arlington, WA, 98223 - 360-403-3551 – www.arlingtonwa.gov
STORMWATER DRAINAGE UTILITY
0 BILL OF SALE AND WARRANTY
Community and Economic Development
City of Arlington • 18204 59th Avenue NE • Arlington, WA 98223 • Phone (360) 403 3551
(Items that will be dedicated to the City of Arlington and will become part of the Public Utility System)
Grandview North, LLC, Grantor, does hereby grant, bargain, sell and convey, for a valuable consideration,
to the City of Arlington, Washington, a municipal corporation, all of that certain stormwater drainage pipe
and appurtenances, situated and described below:
QUANTITY SIZE DESCRIPTION CONSTRUCTION COST
8.00 -
Z,.Z.. l.f. (tJ inch Pipe $ '2,7
\ 62. l.f. ?�t<:.� �inch Pipe $ I q I 7: '6,8 -
5 ea. iv?� 1L Catch Basin(s) $ VJS-[2..5'0 -
ea. inch Manhole(s) $ -
5 ea. Oil Separator( s) $ \SO,,;!>O -
ea. Vault(s) $ -
l.s. 4-5cy Infiltration Galleries $ \Sr B. ,s -
l.s. Pond(s) $ -
l.f. Fence(s) $ -
ea. - Landscaping $ -
2.. Other* C Le.A t-J o u i � $ l+DD-DO -
Other* t./-5cy A�.r:..t--Soe..� SC>IL.. $ I l{}Bt,'50 -
Total $ � �I /.t-�lf-,-2.:,
*Not Required: Items outside the City's right of way or utility easements.
in the development of Paisley Lofts PWD#3104, and more particularly in easements, streets, and public
right-of-ways as described and as shown on an as-built drawing of said installation, attached hereto and
made a part of this document.
The Grantor represents and warrants .that:
•all of the expenses in connection with construction and installation of said pipe line and appurtenances
have been full paid and the same is free from liens and debts; and
•said line and appurtenances were constructed and installed in accordance with City standards and
specifications.
The Grantor agrees to indemnify and hold the City harmless from:
•any lawful claims of any party for labor or materials arising out of construction and installation of said
line and appurtenances.
•any and all claims for damages arising from defective materials or workmanship for a period of two years
from the date of maintenance bond acceptance by the City.
AUTHORIZED SIGNATORY ACCEPTED BY CITY OF ARLINGTON
Signature: Signature:
Print Name: Print Name:
Title: Title: PERMIT TECHNICIAN
This record was acknowledged before me on ________ _ by
Punch list for Paisley Lofts 4/19/24
Ex Saddle manhole-2
*Interior grout all seams, pick holes, risers
*Clean ladders and shelf, channel
Manhole-1
*Interior grout all seams, pick holes, risers
*Clean ladders, shelf, and channel
Manhole-3
*Interior grout all seams pick holes, risers
*clean ladders, shelf, and channel
*Add a ladder rung
Cleanouts 1,3,4 are good just bolt down lids.
Clean out-3 replace plug with unbroken one.
Make sure any hanging ladders are bolted down
From: Brian Grieve
To: dangroendyk@comcast.net
Cc: Kristin Foster; Kevin Olander; Brian Grieve
Subject: Paisley Lofts Punch List
Date: Friday, April 26, 2024 4:56:30 PM
Dan,
Here’s the remaining list for Paisley lofts civil permit.
Concrete curb around the alley parking & dumpster enclosure
Final lift of pavement
Seal joint between the new paving and Division
Mulch the planter strip between the alley and the centennial trail
Install 4’x4’ grates on the trees in the sidewalk along the Division parking stalls
Thanks,
Brian
From: Joe Wilson
To: Dan
Cc: Kristin Foster; Kevin Olander; Brian Grieve
Subject: Punch list completed for Paisley Loft
Date: Thursday, May 9, 2024 11:54:41 AM
Dan,
After inspection today your sewer final punch list was completed and sewer looked good for
Paisley Lofts.
Thanks,
Joe Wilson
Collection System Specialist lll
City of Arlington
Phone: 425-754-7442
Fax: 360-403-3514
E-mail: jwilson@arlingtonwa.gov
Punch list for Paisley Lofts 4/19/24
Ex Saddle manhole-2
*Interior grout all seams, pick holes, risers
*Clean ladders and shelf, channel
Manhole-1
*Interior grout all seams, pick holes, risers
*Clean ladders, shelf, and channel
Manhole-3
*Interior grout all seams pick holes, risers
*clean ladders, shelf, and channel
*Add a ladder rung
Cleanouts 1,3,4 are good just bolt down lids.
Clean out-3 replace plug with unbroken one.
Make sure any hanging ladders are bolted down
From: Brian Grieve
To: dangroendyk@comcast.net
Cc: Kristin Foster; Kevin Olander; Brian Grieve
Subject: Paisley Lofts Punch List
Date: Friday, April 26, 2024 4:56:30 PM
Dan,
Here’s the remaining list for Paisley lofts civil permit.
Concrete curb around the alley parking & dumpster enclosure
Final lift of pavement
Seal joint between the new paving and Division
Mulch the planter strip between the alley and the centennial trail
Install 4’x4’ grates on the trees in the sidewalk along the Division parking stalls
Thanks,
Brian
From: Joe Wilson
To: Dan
Cc: Kristin Foster; Kevin Olander; Brian Grieve
Subject: Punch list completed for Paisley Loft
Date: Thursday, May 9, 2024 11:54:41 AM
Dan,
After inspection today your sewer final punch list was completed and sewer looked good for
Paisley Lofts.
Thanks,
Joe Wilson
Collection System Specialist lll
City of Arlington
Phone: 425-754-7442
Fax: 360-403-3514
E-mail: jwilson@arlingtonwa.gov
!"#
$%#&&%'( (
)
*+,-./-
0
12
/-
3+ 24
*.3 556(%7
833)4-29:;<=;>?@<=A:
B40
C.0
D2. 3E
B
3
E FFG;HI=;@>7I=A
E5JKL;==IG#@J=AMN@:
#AO;AP
E$A:N@:LI>HAQ@>M
#ARJ;:AM
EI;>=A>I>HAQ@>M
#ARJ;:AM
E <SQJ;G=$GI><#ARJ;:AM
E#"T$A:L;=#ARJ;:AM
UE#"T7AM;HI=;@>#ARJ;:AM
VETI=A:%I<ALA>=#ARJ;:AM
E5APA:%I<ALA>=#ARJ;:AM
E5=@:L%I<ALA>=#ARJ;:AM
ETI=A:Q;GG@N5IGA#ARJ;:AM
E5APA:Q;GG@N5IGA
#ARJ;:AM
E5=@:LQ;GG@N5IGA
#ARJ;:AM
E#AO;AP@LLA>=<5A>=S
!
!
!
!
"
" "
"
# $
# %
&
' ('
(
! )*%
$
! #
(
!+),
#
!!,$
!")-# (
!&
*''
! #
*''
! #
.
!# & .
+
!# (
/
% 3
1
!/ #0 (
# 4+' 0
2
0
" #0 "4 4 "1 # 50 0 0'0 . 0
2 0 ! " 0
0'0 " "%
! "#$%
(
& ! "$'$ *
)
+/ 0 "" !
+, - . (
$'$ 1 " ! "
& )
" " '
2 " (
+$$
! " )
3% 4&