Loading...
HomeMy WebLinkAbout19223 68th Dr Ne_BLD2410- Inspection Reports Part 2_2025 M E M O R A N D U M DATE: August 28, 2019 TO: Mr. Dave Prause FROM: Khaled M. Shawish, PE Katelyn S. Brower, GIT RE: Supplemental Stormwater Infiltration Memorandum R+L Carriers Truck Terminal Development 69th Drive NE Arlington, Washington NGA File No. 10572C19 This memo presents our supplemental geotechnical recommendations and opinions regarding the proposed stormwater infiltration within the proposed R+L Carriers Truck Terminal development project located at 68th Drive NE in Arlington, Washington. Introduction We have previously prepared a geotechnical and stormwater evaluation report for the project titled “Geotechnical Engineering Evaluation – R&L Truck Terminal Development – 68th Drive NE – Arlington, Washington,” dated October 30, 2018. We concluded that stormwater infiltration was feasible within the property based on our on-site infiltration testing performed within the site. We generally encountered native fine to coarse sand and gravel with silt throughout the site at depth. Our infiltration test within the central-western portion of the site obtained a field measured rate of 27.5 inches per hour rate. A long-term design infiltration rate of 14.85 inches per hour for infiltration systems within the west- central portion of the site was provided in our previous report, however, we understand you wish to perform a supplemental test at the bottom of the proposed infiltration gallery onsite to verify the long-term design rate. Supplemental Stormwater Infiltration Memorandum NGA File No. 10572C19 R+L Carriers Truck Terminal Development August 28, 2019 Arlington, Washington Page 2 _______________________________________________________________________________________________ Stormwater Infiltration We performed a supplemental infiltration evaluation on August 9th, 2019. The 2014 WSDOE Stormwater Management Manual for Western Washington was utilized to determine the long-term design infiltration rate of the site soils. At the request of the client and according to this manual, on-site infiltration testing consisting of the Small-Scale Pilot Infiltration Test (PIT) was used to determine the long-term design infiltration rates. We conducted a small PIT within the bottom of the proposed infiltration system within Infiltration Pit 101, as shown on the attached Schematic Site Plan in Figure 21. The subsurface soils generally consisted of gravel with medium to coarse sand and silt that we interpreted as native glacial soils. The test was conducted within a pit that measured 4.0-feet long by 3.0-feet wide by 1.0-foot deep. As soon as the infiltration pit was excavated, the pit was attempted to be filled with 12 inches of water and we began the soaking period of the PIT. At this time, the water flow rate into the hole was monitored with a water flow meter for the pre-soak period. After the soaking period was completed, the water level was maintained at approximately 9-inches for one hour for the steady-state period. The flow rate for Infiltration Pit 1 stabilized at 4.52 gallons per minute (271 gallons per hour). This equated to an approximate infiltration rate of 36.2 inches per hour. The water was shut off after the steady-state period and monitored constantly. After approximately 20 minutes, the water level within the pit had completely dissipated, resulting in an infiltration rate of 27.0 inches per hour. In accordance with the Table 3.5 of the 2014 WSDOE Stormwater Management Manual for Western Washington, correction factors of 0.8, 0.75, and 0.9 for CFv, CFt, and the long-term conductivity loss factor, respectively were applied to the field measured infiltration rate. A total correction factor of 0.54 was applied to the measured field infiltration rate obtained from the falling head portion of the test to determine the long- term design infiltration rate. The 27.0 inches per hour rate obtained from the steady state period was utilized as the overall measured field infiltration rate. Using the above correction factor, we calculated a long-term design infiltration rate of approximately 14.58 inches per hour, which could be utilized to design the on-site infiltration systems within the gravel and fine to coarse sand found on this site. We recommend that the base of any on-site infiltration systems be terminated within the native clean granular soils. We should stress that this rate can be significantly reduced through over-compaction of the native soils and/or contamination with less permeable materials. We trust this memorandum should satisfy your needs at this time. Please contact us if you have any questions or require additional services. o-o-o One Figure Attached NELSON GEOTECHNICAL ASSOCIATES, INC. Project Number 10572C19 Figure 1 R&L Truck Terminal Development Site Plan (425) 486-1669 / Fax: 481-2510Geotechnical Engineers & Geologists 17311-135th Ave. NE, A-500 Woodinville, WA 98072N Woodinville OfficeG A Nelson Geotechnical www.nelsongeotech.comAssociates, Inc. (509) 665-7696 / Fax: 665-7692 East Wenatchee, WA 98802 INF-101 5526 Industry Lane, #2East Wenatchee Office No. 1 8/22/19Date OriginalRevision LEGEND 0 100 200 INF-101 DPN By Property line Number and approximate Scale: 1 inch = 100 feet KSB CK location of infiltration test pit Reference: Site plan based on a plan dated April 16, 2019 titled "New Buildings for R+L Carriers Arlington, WA," prepared by Group Four, Inc. \\hill\company\2019 NGA Project Folders\10572C-19 R&L CM\Drafting\SP.dwg