A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ARLINGTON, WASHINGTON
ADOPTING THE OFFICIAL SIX-YEAR TRANSPORTATION IMPROVEMENT PLAN FOR THE
CITY OF ARLINGTON
WHEREAS, the City of Arlington has the responsibility to plan for transportation
improvements within the City pursuant to the Growth Management Act and RCW
36.70A.070; and
WHEREAS, the City Council considered the proposed six-year transportation
improvement plan (TIP) at their City Council workshop on November 12, 2024, and at a
public hearing conducted on November 18, 2024 and determined approving the six-year
TIP was in the best interest of the City and its citizens;
NOW,THEREFORE, the City Council of the City of Arlington, Washington, does
hereby resolve:
SECTION 1. That certain comprehensive Transportation Improvement Plan for
the six years commencing on January 1, 2025_as detailed in the attached "Exhibit A" is
hereby adopted as the Official Six-Year Transportation Improvement Plan for the City of
Arlington.
PASSED at a regular meeting of the City of Arlington, Washington held on the
18th day of November 2024.
CITY OF ARLINGTON
Do . Vanney, Mayor
ATTEST:
Zj
Wendy an Der Meersche, City Clerk
APPROVED AS TO FORM:
Steven J. Peiffle, City Attorney
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project I Funding 2025 2026 2027 2028 2029 2030 Fund Total
ANNUAL TRANSPORTATION MAINTENANCE AND PRESERVATION PROJECTS
N/A Pavement Preservation Program (Prof#N/A) Arlington TIF Funds $0
PE $444,000 TBD Funds $900,000 $900,000 $900,000 $950,000 $950,000 $950,000 $5,550,000
ROW $0 WSDOT Funds $0
CN $5,106,000 TIB Grant Funding $0
TOTAL $5,550,000 PSRC/STP Grant Funding $0
Comments: Program to preserve and maintain existing Other Grant Funding $0
transportation infrastructure. Work from 2025 through 2030 Developer Funded $0
is to develop contract plans and specifications and paving. Non-Motorized Funds _ _ $0
Funded by Arlington TBD. Other Funds $0
SUBTOTAL THIS PROJECT $900,000 $900,000 $900,000 $950,000 $950,000 1 $950,000 $5,550,000
N/A Neighborhood Traffic Calming Arlington TIF Funds $0
PE $148,000 TBD Funds $250,000 $250,000 $300,000 $350,000 $350,000 $350,000 $1,850,000
ROW $0 WSDOT Funds $0
CN $1,702,000 TIB Grant Funding $0
TOTAL $1,850,000 PSRC/STP Grant Funding $0
Comments: This work includes the development and adoption Other Grant Funding $0
of a Neighborhood Traffic Calming program followed by the Developer Funded $0
implementation of traffic calming stratagies at selected Non-Motorized Funds $0
neighborhoods. Funded by Arlington TBD. Other Funds $0
SUBTOTAL THIS PROJECT $250,000 $250,000 1 $300,000 $350,000 $350,000 $350,000 $1,850,000
CURRENT FULLY FUNDED TRANSPORTATION&NON-MOTORIZED CONSTRUCTION(CN)PROJECTS
1 Division-Broadway Rehabilitation Arlington TIF Funds $258,191 $258,191
PE $99,306 TBD Funds $400,000 $400,000
ROW $0 WSDOT Funds $0
CN $1,319,347 TIB Grant Funding $0
TOTAL f $1,418,653 PSRC/STP Grant Funding $0
Comments: Perform overlay on Division and Broadway,add Other Grant Funding $760,462 $760,462
two RRFB pedestrian crossings,improve roundabouts,and Developer Funded $0
upgrade 13 curb ramps to be ADA compliant. Project design Non-Motorized Funds $0
complete,WSDOT Backlog delay. NHS Grant Received. Other Funds $0
SUBTOTAL THIS PROJECT $1,418,653 $0 $0 $0 $0 $0 $1,418,653
2 74th Ave Trail Segment (Prof#T-10) Arlington TIF Funds $225,000 $225,000
PE $89,602 TBD Funds $400,000 $400,000
ROW $59,735 WSDOT Funds $0
CN $1,045,356 TIB Grant Funding $0
TOTAL $1,194,693 PSRC/STP Grant Funding $569,693 $559,693
Comments: Construct a multiuse(ped/bike)trail along the Other Grant Funding $0
west side of 74th Ave between north end of Arlington Valley Developer Funded $0
Rd trail and 204th St trail segment. Project out for bid fall Non-Motorized Funds $0
2024. Grant Received. Other Funds $0
SUBTOTAL THIS PROJECT $1,194,693 $0 $0 $0 $0 $0 $1,194,693
3 1211th PI Corridor(67th Ave to SR-530)(Proj#R-4) Arlington TIF Funds $959,610 $959,610
PE $201,597 TBD Funds $500,000 $500,000
ROW $94,500 WSDOT Funds $0
_ CN $2,908,513 TIB Grant Funding $1,345,000 $1,345,000
TOTAL $3,204,610 PSRC/STP Grant Funding $0
Comments: Rehab 211th Place into an urban corridor with 12 Other Grant Funding $0
ft wide multiuse trail,street/ped lights,embankment Developer Funded $0
stabilization and improved drainage. Includes new water main. Non-Motorized Funds $0
Construction started 2024,to complete 2025. Grant Received. Other Funds 1 $400,000 $400,000
Other funding is Water&Sewer Utilities. SUBTOTAL THIS PROJECT $3,204,610 1 $0 1 $0 $0 1 $0 $0 $3,204.610
Arlington 6-year TIP(2025-2030) Page 1 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. Transportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
4 Smokey Point Blvd&188th Roundabout(Prof#1-2) Arlington TIF Funds $850,000 $850,000
PE $0 TBD Funds $500,000 $500,000
ROW $604,171 WSDOT Funds $0
CN 3,562,525 TIB Grant Funding $0
TOTAL $4,166,696 PSRC/STP Grant Funding $2,316,696 $2,316,696
Comments: Construct a roundabout at the SPB&188th St Other Grant Funding $0
intersection. Roundabout to be complete with sidewalk, RRFB Developer Funded $0
ped crossing, ped/street lights, landscaping,artwork and Non-Motorized Funds $0
street amenities. Design at 95%, ROW at 100%. Grant Other Funds $500,000 $500,000
Received.Other funding is Water&Sewer Utilities. SUBTOTAL THIS PROJECT $4,166,696 $0 $0 $0 $0 $0 $4,166,696
5 Smokey Point Blvd&180th Roundabout Arlington TIF Funds $300,000 $300,000
PE $0 TBD Funds $500,000 $500,000
ROW $350,000 WSDOT Funds $0
CN $3,150,000 TIB Grant Funding $0
TOTAL $3,500,000 PSRC/STP Grant Funding $2,200,000 $2,200,000
Comments: Construct a roundabout at the SPB&180th St Other Grant Funding $0
intersection. This project received funding from PSRC with a Developer Funded $0
program year of 2026. Design at 30%, ROW not yet started. Non-Motorized Funds $0
(Grant Received. Other funding is Water&Sewer Utilities. Other Funds $500,000 $500,000
SUBTOTAL THIS PROJECT $0 $3,500,000 $0 $0 $0 $0 $3,500,000
6 SPB&174th Roundabout Construction Arlington TIF Funds $0
PE $0 TBD Funds $800,000 $800,000 $1,600,000
ROW $570,938 WSDOT Funds $0
CN $3,996,563 TIB Grant Funding $0
TOTAL $4,567,500 PSRC/STP Grant Funding $2,967,500 $2,967,500
Comments: Seek funding and construct a roundabout at the Other Grant Funding $0
SPB& 174th St intersection per designs developed as part of Developer Funded $0
the Smokey Point Blvd Corridor project. RAB to be complete Non-Motorized Funds $0
with sidewalk, RRFB ped crossing, ped/street lights, Other Funds $o
landscaping,artwork and street amenities. SUBTOTAL THIS PROJECT $0 $0 $0 $3,767,500 $800,000 $0 $4,567,500
7 169th St Connector(43rd to 38th Ave) (Prof#R-19) Arlington TIF Funds $600,000 $213,723 $813,723
PE $250,000 TBD Funds $0
ROW $558,577 WSDOT Funds $0
CN $3,660,039 TIB Grant Funding $0
TOTAL $4,468,616 PSRC/STP Grant Funding $0
Comments: Design, ROW,and construction of the 169th St Other Grant Funding $3,654,893 $3,654,893
Connecting Segment from 43rd Ave to 38th Ave. This will be a Developer Funded $0
two-lane urban freight corridor with sidewalk,multiuse trail, Non-Motorized Funds _ $0
ped/street lights,artwork and street amenities. Design at Other Funds $0
60%, ROW not yet started. Grant Received SUBTOTAL THIS PROJECT $600,000 $3,868,616 $0 $0 $0 $0 $4,468,616
8 SR-531 Widening Project Phase 1 (Proj#R-14A) Arlington TIF Funds $0
PE $4,422,000 TBD Funds $0
ROW $4,422,000 WSDOT Funds _ $0
CN $28,006,000 TIB Grant Funding $0
TOTAL $36,850,000 PSRC/STP Grant Funding $0
Comments: Project to widen SR-531(172nd Street) between Other Grant Funding $0
43rd Ave and 67th Ave. Project will be managed by WSDOT. Developer Funded $0
Other funding is Connecting Washington Program,WSDOT is Non-Motorized Funds $0
managing design, ROW and project funds. Other Funds $18,425,000 $18,425,000 $36,850,000
SUBTOTAL THIS PROJECT $18425,000 $18,425,000 $0 $0 $0 $0 $36,850,000
Arlington 6-year TIP(2025-2030) Page 2 of 10
EXHIBITA
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 1 2025 2026 2027 2028 2029 2030 Fund Total
CURRENT AND FUNDED THROUGH DESIGN(PE) -TRANSPORTATION&NON-MOTORIZED PROJECTS ,500
9 Island Crossing SR-530 Roundabout Design (Prof#1-1) Arlington TIF Funds $97,500 $9so
PE $67,500 TBD Funds $0
ROW $30,000 WSDOT Funds $0
CN 0 TIB Grant Funding $0
TOTAL $97,500 PSRC/STP Grant Funding $0
Comments: Completion of final design elements to the SR-530 Other Grant Funding $0
and SPB Roundabout project. Project being coordinated with Developer Funded $0
WSDOT,Stillaguamish Tribe, City of Arlington,Snohomish Non-Motorized Funds $0
County. Finishing up NEPA and finalizing ROW.Seeking CN Other Funds $0
funding. SUBTOTAL THIS PROJECT $97,500 $0 $0 $0 $0 ( $0 $97,500
10 Smokey Pt Blvd Corridor Design&ROW(Prof#R-30) Arlington TIF Funds $200,000 f $200,000
PE $200,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN 0 TIB Grant Funding_ $0
TOTAL $200,000 PSRC/STP Grant Funding $0
Comments:Complete preliminary planning, public outreach, Other Grant Funding $0
engineering design,and ROW plan for corridor improvements Developer Funded $0
to expand Smokey Point Blvd's current 2-lane roadway Non-Motorized Funds $0
between 174th Ave and 200th Ave. Includes design of RAB's Other Funds $0
at 174th St, 180thSt, 183rd St,and 188th St. Grant Received SUBTOTAL THIS PROJECT $200,000 $0 $0 $0 $0 $0 $200,000
11 180th Connector Sm Pt Blvd to Airport Blvd Arlington TIF Funds $120,669 $120,669
_ PE $410,876 TBD Funds $0
_ ROW $273,917 WSDOT Funds $0
CN $4,793,554 TIB Grant Funding $0
TOTAL $5,478,347 PSRC/STP Grant Funding $357,678 $357,678
Comments: Design&construct a new two lane urban freight Other Grant Funding $5,000,000 $5,000,000
corridor from Sm Pt Blvd to Airport Blvd. Road will have Developer Funded $0
sidewalks, multi-use trail,ped/street lights,and street Non-Motorized Funds $0
amenities. Connect to Airport Blvd with RAB intersection. Other Funds $0
Design grant received,CN grant pendii i6. SUBTOTAL THIS PROJECT $478,347 $5,000,000 $0 $0 $0 $0 $5,478,347
12 SR-531 Trail Segment Design 67th to Hwy 9 Arlington TIF Funds $200,000 l_ $200,000
PE $270,000 TBD Funds $0
ROW $180,000 WSDOT Funds $0
CN $3,150,000 TIB Grant Funding $0
TOTAL $3,600,000 PSRC/STP Grant Fun din $0
Comments: Construct a multiuse(ped/bike)trail along the Other Grant Funding $1,000,000 $1,000 000
north side of SR-531 between 67th Ave and Highway 9. Developer Funded $0
Federal funding received for design. Design grant received, Non-Motorized_Funds $0
ICN grant pending. Other Funds $2,400,000 $2,400,000
SUBTOTAL THIS PROJECT $1,200,000 $0 $2,400,000 $0 $0 $0 $3,600,000
NEAR TERM AND PLANNED TRANSPORTATION PROJECTS
13 183rd St Connector,SPB to Airport Blvd. Arlington TIF Funds $0
PE $410,875 TBD Funds $850,000 $850,000
ROW $540,625 WSDOT Funds $0
CN $3,373,500 TIB Grant Funding $0
TOTAL $4,325,000 PSRC/STP Grant Funding $2,500,000 $2,500,000
Comments: Construct a two-lane road section with sidewalks Other Grant Funding $0
and multi-use trail from SPB to Airport Blvd. Private developer Developer Funded $500,000 $475,000 $975,000
funded outside Airport Boundary and City funded inside Non-Motorized Funds $0
Airport Boundary.Connections to SPB and Airport Blvd with Other Funds 1 $0
roundabouts. SUBTOTAL THIS PROJECT $0 $500 000 $475,000 $3,350,000 $0 $0 $4,325.000
Arlington 6-year TI (2025-2030) Page 3 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 1 2025 2026 2027 2028 2029 2030 Fund Total
14 Island Crossing_ SR-530 Roundabout CN (Proj#1-1) Arlington TIF Funds i $0
PE $0 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $5,500,000 TIB Grant Funding $0
TOTAL $5,500,000 PSRC/STP Grant Funding $0
Comments: Construction of a roundabout at the SR530 and Other Grant Funding $0
SPB intersection. Project being coordinated with WSDOT, Developer Funded $0
Stillaguamish Tribe,City of Arlington,Snohomish County. This Non-Motorized Funds $0
is a vital safety and mobility project to continue support of the Other Funds $2,750,000 $2,750,000 �— $5,500,000
Cascade Industrial Center.Seeking CN funding. SUBTOTAL THIS PROJECT $0 $2,750,000 $2,750,000 $0 $0 $0 $5,500,000
15 SPB&183th RAB and N/S Link Construction Arlington TIF Funds $850,000 $500,000 $1,350,000
PE $0_ TBD Funds $0
ROW $981,250 WSDOT Funds $0
CN $6,868,750 TIB Grant Funding $6,500,000 $6,500,000
TOTAL _ $7,850,000 PSRC/STP Grant Funding $0
Comments: Seek funding and construct a RAB at the SPB& Other Grant Funding $0
183rd intersection along with the 183rd RAB north link to Developer Funded $0
188th RAB and south link to 180th RAB per designs developed Non-Motorized Funds $0
as part of the Smokey Point Blvd Corridor project. Other Funds $0
SUBTOTAL THIS PROJECT 1 $0 $0 $0 $0 $7,350,000 $500,000 $7,850,000
16 173rd St, Phase 2 (Proj#R-28) Arlington TIF Funds $0
PE $185,400 TBD Funds $440,000 $440,000
ROW $450,000 WSDOT Funds $0
CN $2,454,600 TIB Grant Funding $0
TOTAL $3,090,000 PSRC/STP Grant Funding $0
Comments: Project includes redesign of road alignment, Other Grant Funding $2,200,000 $2,200,000
acquisition of right-of-way,and construction of new road and Developer Funded $450,000 $450,000
pedestrian facilities between 40th Ave NE and 43rd Ave NE. Non-Motorized Funds $0
Redesign and ROW is needed to shift Ph2 alignment north. Other Funds - _ $0
Includes ped/street lights,artwork and street amenities. SUBTOTAL THIS PROJECT $0 $0 $0 $890,000 $2,200,000 $0 $3,090,000
17 SR530/SR9/Division/Burke&Broadway (Proj#1-6,#1-7) Arlington TIF Fundsl $75,000 $75,000
PE $783,000 TBD Funds $0
ROW $0 WSDOT Funds $6,450,000 $6,450,000
CN $5,742,000 TIB Grant Funding $0
TOTAL $6,525,000 PSRC/STP Grant Funding $0 $0
Comments: Intersection improvements at the following Other Grant Funding $0
intersections per WSDOTSR9 Route Plan and per WSDOT-COA Developer Funded $0
MOU:SR530/SR9/Division,SR9/SR530/Burke and at Non-Motorized Funds $0
Burke/Broadway.City funding as needed for minor work. Other Funds $0
WSDOT considering roundabouts. SUBTOTAL THIS PROJECT $0 $0 $0 $0 $0 $6,525,000 $6,525,000
18 SR-531 Widening Phase 2 (67th Ave to SR-9) Arlington TIF Funds $0
PE $3 375,000 TBD Funds $0
ROW $2,250,000 WSDOT Funds $0
CN $39,375,000 TIB Grant Funding $0
TOTAL $45,000,000 PSRC/STP Grant Funding $0
Comments: This project proposes to widen SR-531 from 67th Other Grant Funding $0
Ave to SR-9. Project to follow same roadway cross-section Developer Funded $0
established in the SR-531 Widening Project Phase 1.Other Non-Motorized Funds $0
funding to be determined. Other Funds $45,000,000 $45,000,000
SUBTOTAL THIS PROJECT $0 $0 $0 $0 $0 $45,000,000 $45,000,000
Arlington 6-year TIP(2025-2030) Page 4 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
19 67th Ave&188th Intersection Imp. (Proj#1-12,#T-8) Arlington TIF Funds $10,000 $125,000 $135,000
L PE $193,200 TBD Funds $0
ROW $289,800 WSDOT Funds $0
CN 1 127 000 TIB Grant Funding $0
TOTAL $1,610,000 PSRC/STP Grant Funding $0
Comments: Install a signal and at 67th Ave&188th St Other Grant Funding $0
intersection and extend ped crossing across BNSF rail crossing. Developer Funded $200,000 $425,000 $625,000
Work to be coordinated with BNSF for vehicle back-up into Non-Motorized Funds $0
BNSF 188th St rail x-ing and ped at grade x-ing. Other funds Other Funds $850,000 $850,000
from Rail Safety. SUBTOTAL THIS PROJECT $0 $10,000 $200,000 $1,400,000 $0 $0 $1,610,000
20 Burn Road Rehabilitation Arlington TIF Funds $0
PE $250,000 TBD Funds $175,000 $175,000
ROW $0 WSDOT Funds $0
CN 2 125 000 TIB Grant Funding $0
TOTAL $2,375,000 PSRC/STP Grant Funding $0
Comments: This project will begin design and planning to Other Grant Funding $0
rehabilitate Burn Road;includes embankment stabilization, Developer Funded $0
drainage, pedestrian access,and stream channel Non-Motorized Funds $0
enhancement.Other funding To Be Determined. Other Funds $2,200,000 $2,200,000
SUBTOTAL THIS PROJECT $175,000 $0 $2,200,000 $0 $0 $0 $2,375,000
21 Highland Dr.Corridor Improvement(Proj#R-5,#T-23) Arlington TIF Funds $300,000 $300,000
PE $42,500 TBD Funds $125,000 $125,000
ROW $63,750 WSDOT Funds $0
CN $318,750 TIB Grant Funding $0
TOTAL $425,000 PSRC/STP Grant Funding $0
Comment.: Internal planning,design,and ROW needs Other Grant Funding $0
assessment for improvements to Highland Drive corridor from Developer Funded $0
SR-9 to Stillaguamish Ave. Corridor to be consistent with city Non-Motorized Funds $0
urbanized arterial roadway standards, including ped access Other Funds $0
ways(SW/Trail)and improved SR-9 signal. SUBTOTAL THIS PROJECT $0 $0 1 $0 $425,000 $0 $0 $425,000
22 51st Ave Improvements(169th to CL) (Proj#R-20) Arlington TIF Funds $35,000 $600,000 $635,000
PE $676,200 TBD Funds $0
ROW $563,500 WSDOT Funds $0
CN 4 395 300 TIB Grant Funding $1,500,000 $1,500,000
TOTAL $5,635,000 PSRC/STP Grant Funding $3,500,000 $3,500,000
Comments: Improve 51st Ave NE into a three-lane urban Other Grant Funding $0
freight corridor roadway from 169th Ave to south Arlington Developer Funded $0
city limits,consistent with Arlington-Marysville CIC Non-Motorized Funds $0
Transportation Planning efforts. Include ROW for making this Other Funds $0
road into a five-lane urban corridor. SUBTOTAL THIS PROJECT $0 $0 $0 $0 $35,000 $5,600,000 $5,635,000
23 SR-531 and 63rd Ave NE Roundabout Arlington TIF Funds $0
_ PE $770,000 TBD Funds $0
ROW $715,000 WSDOT Funds $0
CN $4,015,000 TIB Grant Funding $0
TOTAL $5,500,000 PSRC/STP Grant Funding $0
Comments: Construct roundabout at 63rd Ave&SR-531. The Other Grant Funding $0
63rd Ave RAB to be completed with Connecting Washington Developer Funded $0
funds that are left over because Amazon development Non-Motorized Funds $0
constructed the 43rd Ave RAB. Costs included in SR-531 Other Funds $5,500,000 $5,500,000
Widening Project(TIP-01). SUBTOTAL THIS PROJECT $0 $0 $5,500,000 $0 $0 $0 $5,500,000
Arlington 6-year TIP(2025-2030)
Page 5 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 2025 2026 2027 2028 2029 2030 F Fund Total
NEAR TERM AND PLANNED NON-MOTORIZED PROJECTS
24 SR-531 Trail Segment CN 67th to Hwy 9 Arlington TIF Funds $0
PE $180,000 TBD Funds $0
ROW $120,000 WSDOT Funds $0
CN 2,100,000 TIB Grant Funding $0
TOTAL $2,400,000 PSRC/STP Grant Funding $0
Comments: Construct a multiuse(ped/bike)trail along the Other Grant Funding $0
north side of SR-531 between 67th Ave and Highway 9. Developer Funded $0
Federal funding received for design (Project#12)City seeking Non-Motorized Funds $0
funding for construction. Other Funds $2,400,000 $2,400,000
SUBTOTAL THIS PROJECT $0 $0 $2,400,000 $0 $0 $0 $2,400,000
25 E.Gilman Trail Segment(Prof#T-14 and#T-15) Arlington TIF Fundsl $0
PE $91,850 TBD Funds $135,000 $135,000
ROW $0 WSDOT Funds $0
CN $743,150 TIB Grant Funding $0
TOTAL $835,000 PSRC/STP Grant Funding $0
Comments:Conctruct a 12-ft wide multiuse trail connecting Other Grant Funding $0
the Centennial Trail to Country Charm Park,trail to be within Developer Funded $0
existing ROW of Gilman Ave. Project also includes trail Non-Motorized Funds $700,000 $700,000
segment to provide pedestrian access to Twin Rivers Park. Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $835,000 $0 $0 $835,000
26 2nd Street Sidewalk Completion Arlington TIF Funds, $0
PE $56,000 TBD Fundsl $150,000 $150,000
ROW $20,000 WSDOT Funds $650,000 $650,000
CN $724,000 TIB Grant Funding $0
TOTAL $800,000 PSRC/STP Grant Funding $0
Comments: Project to install sidewalks on 2nd St(French Ave Other Grant Funding $0
to Washington Ave)where none exist. Project funding Developer Funded $0
possible grant from Washington State Pedestrian Safety grant Non-Motorized Funds $0
program. Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 1 $0 $800,000 $0 $0 $800,000
27 N Airport Blvd Trail to 67th Ave Trail Arlington TIF Funds $750,000 $750,000
PE $276,500 TBD Funds $350,000 $350,000
ROW $493,750 WSDOT Funds $0
CN $3,179,750 TIB Grant Funding $0
TOTAL $3,950,000 PSRC/STP Grant Funding $0
Comments: Create multiuse trail from Airport Blvd Trail to Other Grant Funding $0
Centennial Trail at 67th Ave. Includes improvements to Developer Funded $0
existing Airport Trail (fencing to meet FAA requirements). This Non-Motorized Funds $350,000 $350,000
is a joint project with SnoCo, other funds are SnoCo and Other Funds $2,500,000 $2,500,000
federal non-motorized funds. SUBTOTAL THIS PROJECT $0 1 $0 $0 $3,950,000 1 $0 $0 1 $3,950,000
28 204th St NE Portage Creek Trail (Prof#T-4) Arlington TIF Funds $0
PE $47,250 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $627,750 TIB Grant Funding $0
TOTAL $675,000 PSRC/STP Grant Funding $0
Comments: Multi-use trail along Portage Creek from SR-9 to Other Grant Funding $0
Centennial Trail. Developer driven and funded. Developer Funded $675,000 $675,000
Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $675,000 $0 $0 $0 $675,000
Arlington 6-year TIP(2025-2030) Page 6 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. iTransportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
29 59th Ave NE Sidewalk and Airport Trail gap project Arlington TIF Fundsl $450,000 $450,000
PE $91,000 TBD Funds $0
ROW $32,500 WSDOT Funds $0
CN $1,176,500 TIB Grant Funding $0
TOTAL $1,300,000 PSRC/STP Grant Funding $0
Comments: Connect gaps in sidewalk on east side of 59th Ave Other Grant Funding $0
NE(SR-531 to 192nd St)and make improvements to the Developer Funded $0
Airport Trail on the west side of 59th Ave(SR-531 to Cemetery Non-Motorized Funds $0
Road). Work includes fencing for FAA requirements. Other Funds $850,000 $850,000
SUBTOTAL THIS PROJECT $0 $0 $1,300,000 $0 $0 $0 $1,300,000
30 188th St NE/BNSF Rail/Trail Crossing Project Arlington TIF Funds $0
PE $0 TBD Funds $0
ROW $0 WSDOT Funds $0
CN LO TIB Grant Funding $0
TOTAL $0 PSRC/STP Grant Funding $0
Comments: Project combined with 188th St&67th Ave Other Grant Funding $0
Instersection Project (#18 above) Developer Funded $0
Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $0 $O 1 $O 1 $0
NEAR TERM AND PLANNED DEVELOPER FUNDED PROJECTS
31 89th Ave from 172nd to 186th (Prof#R-12,#T-29) Arlington TIF Funds $0
PE $274,050 TBD Funds $440,000 $440,000
ROW $97,875 WSDOT Funds $0
CN $3,543,075 TIB Grant Funding $2,200,000 $2,200,000
TOTAL $3,915,000 PSRC/STP Grant Funding $0
Comments: Rehabilitating 89th Ave from 172nd St to 182nd St Other Grant Funding $0
to Arlington standards. The 182nd St to 186th St will be new Developer Funded $1,275,000 $1,275,000
road construction funded by the City. Entire road to include Non-Motorized Funds $0
lighting,sidewalk,amenities and 12-ft wide multiuse trail. Other Funds $0
Developer funded effort. SUBTOTAL THIS PROJECT $0 ( $0 $0 f $0 $0 $3,915,000 $3,915,000
32 204th St NE Corridor improvements(74th to 69th) Arlington TIF Funds $0
PE $0 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $1,150,000 TIB Grant Funding $0
TOTAL $1,150,000 PSRC/STP Grant Funding $0
Comments: Design and construct improvements on 204th St Other Grant Fundin $0
from 69th Ave to 74th Ave as urban corridor with two through Developer Funded $450,000 $450,000 $250,000 $1,150,000
lanes,separated on-street reverse-angle parking,shared drop Non-Motorized Funds $0
lanes,and bike lanes,planted median. Developer driven and Other Funds $0
funded. SUBTOTAL THIS PROJECT $450,000 $450,000 $250,000 1 $0 $0 $0 $1,150,000
33 180th St NE Improvements_,59th Ave to BNSF ROW Arlington TIF Funds $0
PE $68,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $782,000 TIB Grant Funding $0
TOTAL $850,000 PSRC/STP Grant Funding $0
Comments: Improve 180th St NE to a 2-lane industrial road Other Grant Funding $0
section with an improved trail section on the north side. Developer Funded $350,000 $350,000 $150,000 $850,000
Drainage improvements,overlay,and restriping. Developer Non-Motorized Funds $0
driven and funded. Other Funds $0
SUBTOTAL THIS PROJECT $350,000 $350,000 $150,000 $0 $0 $0 $850,000
Arlington 6-year TIP(2025-2030)
Page 7 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
34 59th Ave Extension 195th to Cemetery Rd (Prof#R-10) Arlington TIF Funds $0
PE $95,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN 905 000 TIB Grant Funding $0
TOTAL $1,000,000 PSRC/STP Grant Funding $0
Comments: Extend 59th Ave from 195th St(approx)to Other Grant Funding $0
Cemetery Road. New road section to be a three lane urban Developer Funded $650,000 $350,000 $1,000,000
industrial roadway with multi-use trail and intersection Non-Motorized Funds $0
improvements at Cemetery Road. Developer driven and Other Funds $0
funded. SUBTOTAL THIS PROJECT $0 $0 $0 $650,000 $350,000 $0 $1,000,000
35 169th St Extension 51st Ave to 59th Ave (Prof#R-19) Arlington TIF Funds $30,000 $30,000
PE $501,200 TBD Funds $0
ROW $465,400 WSDOT Funds $0
CN $2,613,400 TIB Grant Funding $0
TOTAL $3,580,000 PSRC/STP Grant Funding $0
Comments: Extend 169th St as a two lane freight carrying Other Grant Funding $0
urban roadway with sidewalk and multiuse trail from 51st Ave Developer Funded $3,550,000 $3,550,000
,NEto591hAveNE. Developer Funded project. COA funds Non-Motorized Funds $0
available for artwork. Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $3,580,000 $0 $0 $0 $3,580,000
36 47th Ave from 169th South to City Limits (Prof#R-21) Arlington TIF Funds $10,000 $10,000
PE $266,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $2,394,000 TIB Grant Funding $0
TOTAL $2,660,000 PSRC/STP Grant Funding $0
Comments: Construct 47th as a two lane freight carrying Other Grant Funding $0
urban roadway with sidewalk and multiuse trail from 169th to Developer Funded $2,650,000 $2,650,000
south to city limits. Developer Funded project. COA funds Non-Motorized Funds $0
available for artwork. Other Funds $0
SUBTOTAL THIS PROJECT $0 1 $0 1 $0 $2,660,000 $0 $0 $2,660,000
37 163rd Ave Ph2 188th St South through HCl (Prof#16-A) Arlington TIF Funds $0
PE $255,500 TBD Funds $0
ROW $91,250 WSDOT Funds $0
CN $3,303,250 TIB Grant Funding $0
TOTAL _ $3,650,000 PSRC/STP Grant Funding $0
Comments: Extend 63rd Ave as a three-lane roadway with a Other Grant Funding $0
12-ft wide multiuse trail. Developer driven and funded. Developer Funded $3,650,000 $3,650,000
Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $3,650,,000 $0 $0 $3,650,000
38 63rd Ave NE Phase 3-Gap from HCl to SMARTCAP Arlington TIF Funds $0
PE $259,000 TBD Funds $0
ROW $92,500 WSDOT Funds $0
CN $3,348,500 TIB Grant Funding $0
TOTAL $3,700,000 PSRC/STP Grant Funding $0
Comments: Extend 63rd Ave as a (two lane alley)to be Other Grant Funding $0
increased in the future to a three-lane roadway with 12-ft Developer Funded $3,700,000 $3,700,000
wide multiuse trail. Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $0 $3,700,000 $0 $3,700,000
Arlington 6-year TIP(2025-2030) Page 8 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. Transportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
39 63rd Ave NE Phase 4-Gap from PUD to 172nd St NE Arlington TIF Funds $0
PE $262,500 TBD Funds $0
ROW $93,750 WSDOT Funds $0
CN $3,393,750 TIB Grant Funding $0
TOTAL $3,750,000 PSRC/STP Grant Funding $0
Comments: Extend 63rd Ave as a three-lane roadway with 12- Other Grant Funding $0
ft wide multiuse trail. With roundabout at 172nd St NE. Developer Funded $3,750,000 $3,750,000
Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $0 $0 $3,750,000 $3,750,000
40 74th Ave Extension from 204th North to Portage Creek Arlington TIF Funds $0
PE $210,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN $1,540,000 TIB Grant Funding $0
TOTAL $1,750,000 PSRC/STP Grant Funding 1 $0
Comments: Extend 74th Ave as a three-lane urban section Other Grant Funding $0
from the intersection at 204th to Hazel St. Developer driven Developer Funded $1,750,000 $1,750,000
and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $1,750,000 $0 $0 $0 $0 $1,750,000
41 71st Ave Extension from 204th to 74th Ave Arlington TIF Funds $0
PE $270,000 TBD Funds $0
ROW $0 WSDOT Funds $0
CN 51,980,000 TIB Grant Funding $0
TOTAL $2,250,000 PSRC/STP Grant Funding $0
Comments:Extend 71st Ave as a 3 lane urban section from the Other Grant Funding $0
intersection at 204th northeast to meet up with and Developer Funded $2,250,000 $2,250,000
interconnect to 74th Ave. Includes intersection Non-Motorized Funds $0
improvements. Developer driven and funded. Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $2,250,000 $0 $0 1 $2,250,000
42 71st Ave&204th St Roundabout Arlington TIF Funds $0
PE $257,000 TBD Funds $0
ROW $385,500 WSDOT Funds $0
CN $1,927,500 TIB Grant Funding $0
TOTAL $2,570,000 PSRC/STP Grant Funding $0
Comments: Installation of a roundabout at the intersection Other Grant Funding $0
of 71st Ave and 204th St-must be capable of WB-67 turning Developer Funded $2,570,000 $2,570,000
movements(min). Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $2,570,000 $0 $0 $0 $2,570,000
43 68th Ave from Woodlands Way to 188th St NE Arlington TIF Funds $0
PE $245,000 TBD Funds $0
ROW $367,500 WSDOT Funds $0
CN $1,837,500 TIB Grant Funding $0
TOTAL $2,450,000 PSRC/STP Grant Funding $0
Comments: New road construction of 68th Ave as a two-lane Other Grant Funding $0
urban residential corridor from 188th St to Woodlands Way. Developer Funded $2,450,000 $2,450,000
,Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $2,450,000 $0 $0 $0 $2,450.000
Arlington 6-year TIP(2025-2030) Page 9 of 10
EXHIBIT A
City of Arlington Six Year Transportation Improvement Plan (2025 - 2030)
No. ITransportation Project Funding 2025 2026 2027 2028 2029 2030 Fund Total
44 37th Ave from 178th Place to 183rd St Arlington TIF Funds $0
PE $335,000 TBD Funds $0
ROW $502,500 WSDOT Funds $0
CN 2 512 500 TIB Grant Funding $0
TOTAL $3,350,000 PSRC/STP Grant Funding $0
iComments: New road construction within the 37th Ave Other Grant Funding $0
alignment as a two-lane urban residential corridor from 178th Developer Funded $3,350,000 $3,350,000
Place to 183rd St. Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $0 $3,350,000 $0 $0 $3,350,000
45 80th Dr. NE and SR 531 Roundabout Arlington TIF Funds $0
PE $350,000 TBD Funds $0
ROW $525,000 WSDOT Funds $0
CN $2,625,000 TIB Grant Funding $0
TOTAL $3,500,000 PSRC/STP Grant Funding $0
Comments: : Installation of a roundabout at the Other Grant Funding $0
intersection of 80th Dr. NE and SR-531. Coordination with Developer Funded $3,500,000 $3,500,000
WSDOT and Developer driven and funded. Non-Motorized Funds $0
Other Funds $0
SUBTOTAL THIS PROJECT $0 $0 $3,500,000 $0 $0 $0 $3,500,000
46 85th Dr. NE and SR 531 Roundabout Arlington TIF Funds $0
PE $300,000 TBD Funds $0
ROW $450,000 WSDOT Funds $0
CN $2,250,000 TIB Grant Funding $0
TOTAL $3,000,000 PSRC/STP Grant Funding 1 $0
Comments: : Installation of a roundabout at the Other Grant Funding $0
intersection of 80th Dr. NE and SR-531. Coordination with Developer Funded $3,000,000 $3,000,000
WSDOT and Developer driven and funded. Non-Motorized Funds $0
Other Funds _ $0
SUBTOTAL THIS PROJECT $0 $0 $0 1 $3,000,000 $0 $0 $3,000,000
TOTAL PROJECT COST ESTIMATE $33,110,499 $37,753,616 $31,600,000 1 $32,277,500 $15,735,000 $66,590,000 $217,066,615
Indicates New Project not on previous 6 Year TIP Arlington TIF Funds $3,510,970 $523,723 $480,000 $1,185,000 $885,000 $1,175,000 $7,759,693
TBD Funds $3,125,000 $1,650,000 $1,200,000 $4,150,000 $2,100,000 $1,740,000 $13,965,000
WSDOT Funds $0 $0 $0 $650,000 $0 $6,450,000 $7,100,000
TIB Grant Funding $1,345,000 $0 $0 $0 $6,500,000 $3,700,000 $11,545,000
PSRC/STP Funding $3,244,067 $2,200,000 $0 $5,467,500 $0 $3,500,000 $14,411,567
Other Grant Funding $1,760,462 $8,654,893 $0 $0 $2,200,000 $0 $12,615,355
Developer Funded $800,000 $3,050,000 $13,820,000 $16,425,000 $4,050,000 $5,025,000 $43,170,000
Non-Motorized Funds $0 $0 $0 $1,050,000 $0 $0 $1,050,000
Other Funding $19,325,000 $21,675,000 $16,100,000 $3,350,000 $0 $45,000,000 $105,450,000
Arlington 6-year TIP(2025-2030) Page 10 of 10