HomeMy WebLinkAboutResolution No. 2022-002 A Resolution Replacing Resolution No. 2020-021, and Adopting a Revised Fee Schedule.docx RESOLUTION NO. 2022-002
A RESOLUTION REPLACING RESOLUTION NO. 2020-021,
AND ADOPTING A REVISED FEE SCHEDULE
WHEREAS, the City Council, through ordinance, has adopted regulations requiring certain
actions and services; and,
WHEREAS, these various ordinances set forth that fees shall be set by resolution; and,
WHEREAS, the cost of providing these various services consistent with applicable codes,
regulations, and policies periodically increase or decrease, or certain services or practices are
discontinued and fees are no longer needed; and,
WHEREAS, it is the intent of the City of Arlington to charge appropriate fees and charges that
are consistent with the services provided and to cover the public cost of providing these various
services so that the public is not subsidizing individual benefits derived therefrom;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ARLINGTON AS
FOLLOWS:
The following rates, fees, and charges for various services provided, actions performed, or items
sold by the city and/or its contract service providers, and fines levied against code violators, are
hereby adopted:
Section 1. Fees and Charges—General.
1.1 Fees. Fees are intended to cover the normal, recurring costs associated with
providing a given service. Fees are non-refundable.
1.2 Prices. In some instances, the City provides certain goods and merchandise for
sale. Prices for these goods may be included in this resolution.
1.3 Payment Due. Fees are due at the time the action is requested (e.g., at time of
application)or occurs(e.g., prior to a specific action).An applicant may pay all fees
of a multi-phased project in advance; however, doing so does not vest applicable
fees due. Fees due are those in effect at the time the specific action or phase of
an action is requested or occurs.
1.4 Waivers. Upon petition by the applicant, the City Council may waive any of the
fees, or portions thereof, for any non-profit organization or government agency.
Page 1
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Section 2. Land Use Fees. Fees for various services, actions, and permits regarding land use,
as per AMC Title 20 Land Use Code, shall be as listed in Table 2: Land Use Fees
Table 2: Land Use Fees
Action Fee($)
Land Use Permits
Zoning Permit 2,300.00
Special Use Permit 3,400.00 plus actual cost of
Hearing Examiner (if req'd)
Conditional Use Permit 4,000.00 plus actual cost of
Hearing Examiner
Administrative Conditional Use Permit
Temporary/Seasonal Event 125.00
Homeless Encampment 500.00
Mobile Sales and Deliveries 150.00
Development Agreement
Associated with Land Use Actions 1,100.00 plus additional costs if accrued
Not Associated with Land Use Actions 2,400.00 plus additional costs if accrued
Preliminary Plats
Conditional Use Permit for a Major Plat or Unit Lot 7,000.00 plus actual cost of Hearing Examiner
Subdivision and consultant
Zoning Permit for a Minor Plat or Unit Lot 3,100.00 plus actual cost of consultant
Subdivision
Final Plats _
Major Plat or Unit Lot Subdivision 3,400.00
Minor Plat or Unit Lot Subdivision 2,000.00
Binding Site Plans _
Conditional Use Permit for Binding Site Plans >_ 10 7,000.00 plus actual cost of
lots Hearing Examiner and consultant
Zoning Permit for Binding Site Plans 5 9 lots 3,100.00 plus actual cost of consultant
Text and/or Design Deviation 750.00
Lot Line Adjustment or Changes to Number of Lots 1,400.00 plus actual cost of consultant
Master Plan 12,500.00 plus actual cost of consultant
Design Review
Administrative 300.00
Design Review Board 450.00
Mixed Use Development
Binding Site Plan 7,000.00 plus actual cost of consultant
Conditional Use Permit 4,000.00 plus actual cost of
Hearing Examiner
Special Use Permit 3,400.00 plus actual cost of
Hearing Examiner (if req'd)
Zoning Permit 2,300.00
Page 2
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Action - Fee($)
Forest Practices Permits
Permit Review 450.00
Forest Practices Permit Application Fee 125.00 plus 125.00 per acre
Review Fee for Conversion Option Harvest Plan 125.00 plus 125.00 per acre
Approval
Review Fee To Lift Moratorium 300.00
Inspection Fee 150.00 per hour plus 125.00per acre
Tree replacement mitigation in-lieu fee with Permit: 32.50 per replacement tree
Number of trees removed x 3 for replacement tree
total
Appeals
To City Council 250.00
To Planning Commission 250.00
To Hearing Examiner 600.00 plus actual cost of Hearing Examiner
To Shoreline Hearings Board 600.00
Reconsideration of Decision by:
Community Development Director and/or a 100.00
designee
Planning Commission 150.00
Hearing Examiner 250.00 plus actual cost of Hearing Examiner
City Council 150.00
Permit Extension
Extension 200.00
Resubmittal Extension 125.00
Amendment to or Modification of Permit
Insignificant Design Deviations 60.00
Minor Amendment 325.00
Major Amendment 1,100.00 plus actual cost of
Hearing Examiner (if required)
Boundary Line Adjustment
Boundary Line Adjustment/ Lot Line Elimination 1,700.00 plus actual cost of consultant
Land Use Ordinance Amendment
Amendment to Text of Land Use Ordinance 750.00
Amendment to Zoning Map (rezone)
< 5 acres 1,200.00
> or= 5 acres 2,000.00
Comprehensive Plan Amendment
Minor Amendment (annual cycle) 1,500.00
Major Amendment (5-year cycle) 2,200.00
Annexations
Submission of 10% Petition 150.00
Page 3
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Action - � - - Fee
Submission of 60% Petition 1,100.00
Boundary Review Board Application Filing Fee 50.00
If it goes to Boundary Review Board Hearing 800.00
Shoreline Development Permit(SDP)
SDP in conjunction with a Land Use Permit 550.00
SDP not in conjunction with a Land Use Permit 1,100.00
Significant Tree Removal
Significant Tree Replacement: Number of trees 150.00 per replacement tree
removed x 3 or pay in lieu fee per replacement
tree
Variance
Administrative 700.00
If it goes to hearing (fee in addition to that paid for 1,300.00 plus actual cost of Hearing
Admin. Decision) Examiner
Miscellaneous Actions/Items
General Information Meeting
First two meetings 0.00
Subsequent meetings 350.00 per meeting
SEPA Review (note: review of checklist included
within Land Use Permit fee)
SEPA Only (no land use permit required) 550.00
Environmental Impact Statement (EIS) 1,100.00 plus actual cost of consultant
Change of Use of per AMC 20.40.070
Change of Use Land Use Site Plan Review 125.00
(additional Design Review fees may apply)
Critical Area Review
Critical Area Site Plan Review (no land use permit) 125.00
Deferral of Impact Fee
Application 200.00
Request of Utility Services Outside City Limits
Utility Extension Agreement- Single-Family 225.00
Residence/Duplex
Utility Extension Agreement- Other Development 650.00
Property Tax Exemption Certificate
Processing Fee 500.00
Recording
Recording Fees/Conformed Copies Actual cost paid directly to the
Snohomish County Auditor
Page 4
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Action Fee($)
Processing/Technology Fee 1
Added to all Land Use, Civil, Utility, & Building 25.00
Permits
Credit Card Processing Surcharge/Service Fee 3%of actual cost
Electronic Funds Transfer Fee .50 per transaction
Section 3. Public Works Fees. Fees for various services, actions and permits shall be as
listed in Tables 3-1: Review Fees, 3-2: Grading Plan Review Fees, 3-3: Grading Permit Fees,
and 3-4: Public Works Labor and Equipment Charges.
Table 3-1: Review Fees
Action Fee($)
Civil Review 6% E.E.C.C.Z with a minimum charge of 1,600.00
Administrative Review Fee 250.00 each
Miscellaneous Engineering Fee 550.00 each
As-Built Review Fee Included in the site civil review fee
Final Plat Review Fee Included in the site civil review fee
Inspection Fee 150.00 per hour, % hour minimum
Outside Consultant Review Fee Actual cost
Simple Site Plan Review 275.00 per lot
Action Fee($)
Right of Way 6% E.E.C.C.lor maximum 1,100.00 with a minimum
charge of 125.00 plus inspection fees
Right of Way Vacation 1,100.00
Miscellaneous Staff Time 150.00 per hour per person, % hour minimum
Engineering Meetings-after 2 hours 350.00 per meeting
Recovery Contract 1,100.00 plus actual cost
1E.E.C.0 Engineer's Estimated Cost of Construction-Includes labor,equipment, material,overhead and profit. Prices
shall be from RS Means (latest edition) data adjusted for the Snohomish County area or from local sources if not
included in the RS Means database.
*Simple Site Plan Review-No water or sewer extension-Single family residence with maximum of 2 lots.
*Additional plan review applies when there is a change,addition or revision to the plan.
*Additional plan review fees will be charged at any point in the project when more than 2 reviews are required.
* Inspection Fee-commercial and residential plats(storm drainage, landscape, right-of-way and bond
inspections).
*Outside Consultant Review Fee.
*Water&Sewer Availability Certificate Fee.
* Engineering Meetings(first 2 hours are no charge).
* Miscellaneous engineering fee-traffic and storm water report/design reviewed in-house.
Page 5
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Action Fee ($�
Permit for Non-Construction use of Right
of Way per AMC Chapter 12.50
Application fee $ 65.00
Lease rate or charge Charge per square foot (annual)
Commercial zones including, but not $.45
limited to, GC, HC, NC
Business zones including, but not $.40
limited to,OTBD-1, OTBD-2, OTBD-3
Appeals fee per AMC 12.50.130 $600.00 plus cost of hearing examiner
Leasehold Tax 12.84%
Table 3-2: Grading Plan Review Fees
Action Fee($)
50 cubic yards or less 100.00
51 to 100 cubic yards 120.00
101 to 1,000 cubic yards 160.00
1,001 to 10,000 cubic yards
First 1,000 cubic yards 200.00
Plus-for each additional 10,000 yards or fraction thereof
10,001 to 100,000 cubic yards
For the first 10,000 cubic yards 300.00
Plus-for each additional 10,000 cubic yards or fraction thereof 40.00
100,001 to 200,000 cubic yards
For the first 100,00 cubic yards 400.00
Plus—for each additional 10,000 cubic yards or fraction thereof 60.00
200,001 cubic yards or more
For the first 200,000 cubic yards 500.00
Plus- for each additional 10,000 cubic yards or fraction thereof 100.00
Other Fees: Additional plan review required by changes, additions or New plan review fee
revisions to approved plans.
Table 3-3: Grading Permit Fees
� Action _ Fee($)
Base Permit Fee 100.00
50 cubic yards or less 120.00
51 to 100 cubic yards 160.00
101 to 1,000 cubic yards
First 100 cubic yards 200.00
Plus—for each additional 100 cubic yards or fraction thereof 20.00
Page 6
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
i Action Fee M
1,001 to 10,000 cubic yards
For the first 1,000 cubic yards 300.00
Plus-for each additional
1,000 cubic yards or fraction thereof 40.00
10,001 to 100,000 cubic yards
For the first 10,000 cubic yards 500.00
Plus-for each additional
10,000 cubic yards or fraction thereof 60.00
100,001 or more cubic yards or more
For the first 100,000 cubic yards 600.00
Plus-for each additional 10,000 cubic yards or fraction thereof 50.00
Table 3-4: Public Works Labor and Equipment Charges
A. Services and work included in the below schedule will be charged a 15%
administrative/overhead fee for accounting, billing and general City administrative
costs.
B. All work or services not included in the below schedule must be mutually agreed upon
prior to the commencement of work.
C. Equipment and machinery that is not explicitly included in the below schedule will be
charged at the rate set forth in the most current Rental Rate Blue Book for Construction
Equipment ("Blue Book"). If the equipment or machinery rate is not available in the Blue
Book, the City will determine an appropriate fee or rate based on the original cost of the
asset plus operating and maintenance cost and/or comparable rates charged by other
organizations.
Item Fee ($)
Labor Rate Cost
Lead Maintenance Worker Hourly 60.00
Sr. Maintenance Worker Hourly 55.00
Maintenance Worker Hourly 50.00
Administrative Staff Hourly 50.00
Equipment Rate Cost
Pick-up Truck Hourly 15.00
Dump Truck Hourly 75.00
Back-hoe Hourly 55.00
Vactor-Jetter Truck Hourly 105.00
Snow Plow Hourly 75.00
Street Sweeper Hourly 55.00
Page 7
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Section 4. Building, Plumbing, Mechanical, Fire Permit and Plan Review Fees.
For determining the value of a structure, the most current Building Valuation Data as
published by the International Code Council, is adopted by reference. Fees shall be as listed
in Tables 4-1: Building Permit Fees,4-2: Building Plan Fees,4-3: Miscellaneous Building Permit
Fees and 4-4: Miscellaneous Building Inspection & Plan Review Fees.
Table 4-1: Building Permit Fees
Total 2021 Fee Calculation ($)
Valuation($)
1.00—500.00 34.00 0.00 to 500.00
501.00— 34.00 For the first 500.00
2,000.00 4.57 PLUS for each additional 100.00, or fraction thereof, to and including
2,000.00
2001.00— 102.55 For the first 2,000.00
25,000.00 21.03 PLUS for each additional 1,000.00, or fraction thereof, to and
including 25,000.00
25,001.00— 586.24 For the first 25,000.00
50,000.00 15.24 PLUS for each additional 1,000.00, or fraction thereof, to and
including 50,000.00
50,001.00— 967.24 For the first 50,000
100,000.00 10.61 PLUS for each additional 1,000.00, or fraction thereof to and
including 100,000.00
100,001.00— 1,497.74 For the first 100,000 PLUS for each additional 1,000.00, or fraction
500,000.00 8.41 thereof, to and including 500,000.00
500,001.00— 4861.74 For the first 500,000.00 PLUS for each additional 1,000.00 or fraction
1,000,000.00 thereof
1,000,001.00 8,456.74 For the first 1,000,000.00 PLUS for each additional 1,000.00, or
and up 5.49 fraction thereof
Table 4-2: Building Plan Review Fees
Total Valuation($) Per Current ICC Building Valuation Data
All valuations 65%of Building Permit Fee based on valuation calculation per Table 4-1
Table 4-3: Miscellaneous Building Permit Fees
Action Fee ($)
Demolitions 100.00+ Inspection fee
Espresso Stands 250.00+ Inspection fee
(portable and stand-alone)
Fences Over 6 feet in height 100.00 plan review+ Inspection fee
Fuel Tank Underground Installation 500.00
Fuel Tank Underground Removal 500.00
Page 8
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Action Fee ($)
Fuel Tank LPG Installation 100.00
Marijuana Extraction Table 4.1 & 4.2
Minimum Housing Inspection 75.00
Mobile Homes Installation 500.00
Modular Offices Installation 500.00
Moved Buildings 100.00
Re-roofing Permit—Residential 75.00
Re-roofing Permit—Commercial 100.00 plan review; permit fee,Table 4.1
Retaining walls (permit not required under four 100.00 or IBC valuation, whichever is greater
(4) feet
Signs Permits Permit Fee Only, Table 4.1; minimum 100.00
Swimming Pool or Spa Table 4.1 & 4.2
Fee per each pool or spa; private or public
Washington State Surcharge RCW 19.27.085
Residential Building Permits 6.50
Each Additional Residential Unit (This does not apply to the first unit) 2.00
Table 4-4: Miscellaneous Building Inspection & Plan Review Fees
- --- Action Fee($)
Inspections outside of normal business hours 150.00 per hour (minimum charge 1 hour)
Re-inspection fees (includes two inspections) 75.00 per hour
Inspection for which no fee is specifically indicated 75.00 per hour (minimum charge 1 hour)
For use of outside consultants for plan review and Actual costs3
inspections, or both.
Stop work order (working without perm it)4 Double permit fees or 500.00, whichever is less
Revise site plan after plan review completed 100.00
Revise building plans during plan review
<50% review completion 75.00
>50% review completion New plan review fee
Revised building plans after issuance of permit New plan review fee-
2 The total hourly cost to the City,whichever is greatest.This cost shall include supervision,overhead,equipment,hourly wages,
and benefits of the employees involved.
3 Actual costs include administrative and overhead costs.
4 Stop work order(SWO):failure to obtain a valid permit
Page 9
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
4.2 Plumbing Permit and Plan Fees. Plumbing fees shall be as listed in Table 4-5:
Plumbing Permit Fees and Table 4-1: Plumbing Plan Review Fees.
Table 4-5: Plumbing Permit Fees
PLUMBING PERMIT FEES(per unit)
Commercial plumbing permits are required to submit line drawings. A permit fee shall be calculated per
unit.A plan review fee of 65% per Table 4-6 for plumbing permits will be assessed at time of submittal.
Includes two (2) inspections with permit.
Residential plumbing permits will be assessed a base fee, fee per unit, and inspection fee.
Additional Plan Review fees $ 75.00
Alteration/repair piping $ 15.00
Backflow Assembly $25.00
Base Plumbing Fee $ 25.00
Bath/Shower Combo $ 15.00
Building Main Waste $ 25.00
Clothes Washer $ 15.00
Dishwasher $ 15.00
Drinking Fountain $ 15.00
Floor Drains $ 15.00
Grease Interceptor $ 75.00
Grease Trap $ 25.00
Hose Bibb $ 15.00
Icemaker/Refrigerator $ 15.00
Irrigation-per meter $ 25.00
Kitchen Sink & Disposal $ 15.00
Laundry Tray $ 15.00
Lavatory $ 15.00
Med Gas Piping 15 5 inlets/outlets $ 60.00
Med Gas Piping> 5 inlets/outlets (plus 15 5 $ 5.00
inlets/outlets)
Miscellaneous-regulated by plumbing code, not $ 15.00
otherwise specified
Pretreatment Interceptor $ 15.00
Re-inspection Fee (all) $ 75.00
Roof Drains $ 15.00
Shower (only) $ 15.00
Sink (bar, service, etc.) $ 15.00
Toilets $ 15.00
Urinal $ 15.00
Vacuum Breakers $ 25.00
Page 10
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
PLUMBING PERMIT FEES(per unit)
Water Heater $ 25.00
Water Heater-Tankless $ 25.00
Table 4-6: Plumbing Plan Review Fees
4.3 Mechanical Permit Fees. Mechanical permit fees shall be as listed in Table 4-7:
Mechanical Permit Fees and Table 4-8: Mechanical Plan Review Fees.
PLUMBING PLAN REVIEW FEES
Total Valuation($) Per Current]CC Building Valuation Data
All valuations 65% of Building Permit Fee based on valuation calculation per Table 4-1
Table 4-7: Mechanical Permit Fees
MECHANICAL PERMIT FEES(per unit)
Commercial mechanical permits are required to submit line drawings.A permit fee shall be calculated
per unit.A plan review fee of 65%per Table 4-8 for mechanical permits will be assessed at time of
submittal. Includes two(2) inspections with permit.
Residential mechanical permits will be assessed a base fee, fee per unit and inspection fee.
Additional Plan Review fees $ 75.00
Air Cond. Unit <_100Btu/h $ 15.00
Air Cond. Unit >100Btu/h $ 25.00
Air Cond. Unit >500Btu/hp $ 50.00_
Air Handling Units $ 15.00
Base Mechanical'Fee $ 25.00
Boiler<100Btu/h >3hp $ 15.00
Boiler>1 million Btu/h<50hp $ 25.00
Boiler>1.5 million Btu/h<50hp $ 50.00
Boiler>100Btu/h 3-15hp $ 15.00
Boiler >500Btu/h 15-30hp $ 25.00
Commercial Hoods -Type I / II $ 25/50
Diffusers $ 15.00
Dryer Ducting $ 15.00
Ductwork (drawings required) $ 25.00
Evaporative Coolers $ 15.00
Exhaust/Ventilation Fans $ 15.00
Fireplace/Insert/Stove $ 15.00
Forced Air Heat <_100 Btu/h $ 15.00
Forced Air Heat >100 Btu/h $ 25.00
Gas Clothes Dryer $ 15.00
Gas Fired AC<_100 Btu/h $ 15.00
Page 11
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
MECHANICAL PERMIT FEES (per unit)
Commercial mechanical permits are required to submit line drawings.A permit fee shall be calculated
per unit. A plan review fee of 65%per Table 4-8 for mechanical permits will be assessed at time of
submittal. Includes two(2) inspections with permit.
Residential mechanical permits will be assessed a base fee, fee per unit and inspection fee.
Gas Fired AC>100 Btu/h $ 25.00
Gas Fired AC > 500 Btu/h $ 50.00
Gas Piping:5 5 units $ 15.00
Gas Piping > 5 units (plus <5 units) $ 2.00
Heat Exchangers $ 15.00
Heat Pump-Condensing Unit $ 25.00
Hot Water Heat Coils $ 15.00
Miscellaneous Appliance - regulated by mechanical $ 15.00
code, not otherwise specified
Pkg. Units 5100btu/>100btu $ 25/50
Range/Cook top-Gas Fired $ 15.00
Refrigeration Unit <_100Btu/h $ 15.00
Refrigeration Unit >100Btu/h $ 25.00
Refrigeration. Unit >500Btu/h $ 50.00
Re-inspection fee (all) $ 75.00
Residential Range Hood $ 15.00
Unit Heaters 15 100 Btu/h $ 15.00
Unit Heaters >100 Btu/h $ 25.00
VAV Boxes (Variable Air Volume, part of air $ 10.00
conditioning system)
Wall Heaters-Gas Fired $ 25.00
Water Heater-Gas Fired $ 25.00
Table 4-8: Mechanical Plan Review Fees
MECHANICAL PLAN REVIEW FEES l
Total Valuation($) Per Current ICC Building Valuation Data
All valuations 65% of Building Permit Fee based on valuation calculation per Table 4-1
4.4 Fire Permit and Plan Review Fees. Fire Permit Fees shall be as listed in Table 4-9:
Fire Permit Fees Table 4-10: Fire Plan Review Fees.
Page 12
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Table 4-9: Fire Permit Fees
FIRE SPRINKLER SYSTEMS (105.7.1,105.7.4, 105.7.11)
TENANT IMPROVEMENT OR SYSTEM MODIFICATION (NFPA 13/13R)
Number of Sprinklers or Devices** Fee
1 to 2 $ 75.00
3 to 5 $125.00
6 to 10 $175.00
11 to 20 $225.00
21 to 40 $300.00
41 to 100 $375.00
101 to 200 $475.00
201 to 300 $575.00
>300 $600.00 plus $50.00 per 100 additional devices
For Hydraulically designed systems multiply the
fees above by 2.
NEW COMMERCIAL SYSTEM (NFPA 13/13R)
Number of Sprinklers or Devices** Fee
1 to 100 $375.00
101 to 200 $475.00
201 to 300 $600.00
>300 $625.00 plus $50.00 per 100 additional devices
RESIDENTIAL(NFPA 13D)
Number of Sprinklers or Devices** Fee*
Ito 10 _ $175.00
_ 11 to 25 $225.00
26+ $275.00
*NFPA 13D SYSTEM INSTALLED - NOT REQUIRED —fee reduced 50%
HOOD SUPPRESSION SYSTEM
Type of System Fee
Pre-Engineered $200.00
Custom Engineered $275.00
STANDPIPE SYSTEM
Type of Standpipe Fee
Class I —new or existing $150.00
Class II - new or existing $150.00
Fire Pump $300.00 each
Page 13
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
PHASED INSTALLATION
Additional Fee
Additional Hydrostatic Pressure Test $150.00
(1 test included per permit)
Additional Cover Inspection $75.00
(1 cover inspection included per permit)
** Devices include separate individual portions of a Fire Sprinkler System such as: Sprinklers, Risers,
Valves, Pull Stations, Beam Detectors and other such devices. (Each piece is one device)
SPRAY BOOTHS(105.7) & INDUSTRIAL OVENS(105.7.7)
Spray Booths 1_ Fee
Pre-Engineered w/documents $150.00
Site-built or used w/o documents $250.00
Industrial Oven $250.00
NOTE:SEPARATE SPRINKLER PERMIT REQUIRED
FIRE ALARM SYSTEM - NFPA 72 (105.7.3)
TENANT IMPROVEMENT OR SYSTEM MODIFICATION
Number of Devices* Fee
1 to 2 $75.00
3 to 5 $125.00
6 to 10 $175.00
11 to 20 $225.00
21 to 40 $300.00
41 to 100 $375.00
101 to 200 $475.00
>200 $500.00 plus$50.00 per 100 additional devices
NEW COMMERCIAL SYSTEM
Number of Devices* Fee
1 to 100 $350.00
101 to 200 $475.00
>200 $500.00 plus$50.00 per 100 additional devices
NOTE: In additional to device* fees shown, the following fees also apply:
FACP AND/OR TRANSMITTER
New $200.00
Replace $125.00
NOTE: All Central Station Monitoring must be UL or FM listed.
*Devices include separate individual portions of a Fire Alarm System such as:
Initiating Devices, Notification Appliances, Flow Switches, Supervisory Switches, Magnetic Door Hold-
Open Devices, Remote Annunciators, Pull Stations, Beam Detectors and other such devices.
(Each piece is one device)
Page 14
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Table 4-10: Fire Plan Review Fees
Total Valuation Fee ($)
< $5,000.00 200.00
$5,000.00 and over 65% of Building Permit Fee based on valuation
calculation per Table 4-1
Section 5. Fire Department Life-Safety Inspection Fees. Fees for re-inspections for life-
safety issues conducted by the Fire Department shall be as listed in Table 5: Fire
Department Life-Safety Inspection Fees.
Table 5: Fire Department Life-Safety Inspection Fees
Action Fee($)
Life/Safety Inspections of Businesses
Initial Inspection 0.00
First re-inspection for corrections 0.00
Second re-inspection for corrections 100.00
Third re-inspection for corrections 150.00
Additional inspections to complete life/safety corrections 250.00
and attain compliance
Section 6. Fees for the Use of City Owned Facilities. Fees for various services, actions, and
permits regarding use of City owned facilities shall be as listed in Table 6: Fees for the Use of
City Owned Facilities.
Table 6: Fees for the Use of City Owned Facilities
Stillaguamish Conference Room at Public Works Administration (154 W. Cox). Room usage fees for
community youth related activities and Neighborhood Watch meetings may be waived.
Use/Activity Fee ($)
One to three hours 15.00 per hour
Over three hours 75.00
Pop-up Shops at Innovation Center and Depot
One to four days $100.00 per rental
Athletic Fields
Field Use $10.00 per hour
Lighting $3.00 per 1.5 hours
Community Garden
4 X 20 foot bed $20.00 per season
4 X 8 foot bed $15.00 per season
2 X 8 foot bed $10.00 per season
Page 15
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Section 7. Appeal Fees for Violations and Abatement. Fees for various services and actions
regarding violations and abatement as per Chapter 11.01 of the Arlington Municipal Code
shall be as listed in Table 7: Appeal Fees for Violations and Abatement.
Table 7:Appeal Fees for Violations and Abatement
Action Fee
Appeals
To Hearing Examiner 582.00 plus actual cost of Hearing Examiner
Fines
C Forest Practice Violation Fine 317.00
Section 8. Licensing Fees. Licensing fees for various licenses issued under various sections of
the Arlington Municipal Code shall be as listed in Table 8:- Licensing Fees.
Table 8: Licensing Fees
License/Activity Fee($)
New application / renewal business license under AMC Chapter 60.00
5.28
Peddlers & Solicitors License under AMC Chapter 5.04 25.00
Vehicles for Hire License under AMC Chapter 5.12
- First vehicle 35.00
- Each vehicle thereafter 15.00
Sexually Oriented Adult Entertainment under AMC Chapter 5.36
Annual license for license of manager and entertainers required 100.00
Annual license for the adult entertainment business is required 500.00
Section 10. Dog Licensing Fees.
10.1 Fees for dog licenses as called for in Arlington Municipal Code Chapter 8.09
shall be listed in Table 10: Dog Licensing Fees
10.2 Per RCW 49.60.380, the City of Arlington shall honor a request by a blind
person or hearing impaired person not to be charged a fee to license his or her guide
dog, or a request by a physically disabled person not to be charged a fee to license his
or her service animal.
10.3 All dogs require proof of current Rabies vaccination to be licensed.
Page 16
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Table 10: Dog Licensing Fees
License Annual Fee($) l
Dog—unaltered (annual tag) 40.00
Dog—altered (lifetime tag) 20.00
Dog—altered (senior citizen owner—lifetime tag) 10.00
Replacement Tag fee 5.00
Section 11. Fees for Police Services. Fees for various services, actions, and permits for polic
e
services shall be as listed in Table 11: Fees for Police Services.
Table 11: Fees for Police Services
Action/Service/ License Fee($)
Fingerprinting 20.00
Concealed Weapons Permits: All charges per RCW 9.41.070
1. New permit
2. Permit Renewal
3. Lost or stolen permit
4. Late renewal of permit
Lamination of Concealed Weapons Permit 4.25
Anti-Harassment Order Service (Includes service, return of 80.00
service, mileage &fuel costs)
Fine for Parking:
1. Fine for parking as described in Arlington Municipal 50.00
Code 10.54.060, Prohibited Parking
2. Fine if paid within 24 hours of issuance 25.00
3. Fine if not paid within 15 days of issuance 100.00
Section 12. Fees for Duplication of Public Records.
12.1 Fees for various services and actions for duplication of public records shall be
consistent with the provisions of RCW 42.56.120 and listed in Table 12: Fees for Public
Records Services.
12.2 The City of Arlington finds that calculating the actual costs of scanning per page
in order to fulfill a public records request would be unduly burdensome for the following
reasons:
(a) The City employs over 120 employees. Because all City employees contribute to
the production of public records requests and all employees earn different
salaries or rates of pay, the public records officer would have to be privy to
salaries of all employees in order to calculate the invoice;
Page 17
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
(b) Employees supplying scanned records to the public records officer would be
required to track time spent, thereby creating a burden for those employees
without work stations as well as additional work not assigned in many
employees'job descriptions and or union contracts;
(c) The City's public records officer would be required to maintain a record of all
employees who contribute to each part of a public record request and
potentially charge different amounts for multiple scanned pages;
(d) The City uses more than seven document scanning machines with different
costs and lease agreement fees which change from time to time. The cost of
supplies for the City's various scanning machines is subject to change based on
current market rates. Calculating the portion of the machines and supplies used
toward scanning public records would require knowledge of the cost of supplies
and an in-depth analysis of timing and application multiplied by each
contributing employee's hourly rate of pay; and
(e) The response time to a public records request may be delayed in order to
calculate scanning costs and create an invoice with different rates of scanning
charges.
Table 12: Fees for Public Records Services
Action/Service Fee($)
In house copying of City documents for the public __ 0.15 per page
In house copying of City documents to PDF when original 0.10 per page
document is not in electronic format
Provision of files or attachments and provided by electronic 0.05 per 4 files or attachments
delivery
Electronic records transmission 0.10 per gigabyte (GB)
Storage media (USB, CD), container, envelope, and postage Actual cost
delivery charge
Duplication of documents and other media printed by outside Actual cost to reproduce
party
Staff redaction time for body-worn camera footage* .8266 (.83) per minute average
*The City will charge all requestors requesting body-worn camera footage
except those listed in RCW 42.56.240(e)(i)for the time it takes the City to
redact the footage,See RCW 42.56.240(14)(f)(1).These charges are based
on the average per-minute salaries of the City employees responsible for
video redaction. For the purposes of providing requestors estimated costs
of a request under RCW 42.56.120(2)(f),the City estimates that redaction
takes ten minutes of staff time per minute of raw footage for targeted video
redaction(with or without audio redaction);five minutes of staff time per
minute of raw footage for targeted audio redaction alone;and one minute
total per video for complete screen blur and audio removal.
Page 18
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION NO.2022-002
Section 13. Fees for Franchise Applications. Pursuant to AMC Title 21, fees for various
services and actions for franchise applications shall be listed in Table 13: Fees for Franchise
Applications.
Table 13: Fees for Franchise Applications
Action/Service Fee($)
Franchise Application Fee $1,000
Legal Review of Franchise Application Actual costs
Section 14. Fees for GIS Services. Fees for various services and actions for GIS shall be
listed in Table 14: Fees for GIS Products
Table 14: Fees for GIS Products
Action/Service Fee ($)
Zoning and Land Use Maps _ 10.00
11x17 5.00
2x3 13.00
30 19.00
3x4 25.00
Map CD 26.00
Data CDs/FTP 26.00 per client
Hourly Rate for Custom Work 127.00 per hour, % hour
minimum
Laminating 3.00/sq ft
Shipping Actual Cost of container and
postage
Section 15. Finance Department Services. Fees for various services, actions, and permits
for finance services shall be as listed in Table 15: Fees for Finance Department Services.
Table 15: Fees for Finance Services
Action/Service Fee($)
Non-Sufficient Funds—Dishonored or disallowed draft or check $35.00
Establishing a new utility account $18.00
Reactivating an existing utility account $18.00
Shut off processing fee $50.00
Page 19
CITY OF ARLINGTON FEE SCHEDULE RESOLUTION 1\10. 2-02 27-oOZ
Section 16. Repeal of Previous Fee Resolution. Resolution 2021-021 is hereby repealed.
Section 17. Effective Date. This resolution will become effective immediately upon
passage.
PASSED by the City Council and APPROVED by the Mayor this 22"d day of February, 2022.
CITY OF ARLINGTON
Barbara Tolbert, Mayor
ATTEST:
AIA dL
Wendy Van er Meersche, City Clerk
APPROVED AS TO FORM:
Stev P ' IV, City Attorney
Page 20